Mautz v. J.P. Patti Co.

688 A.2d 1088, 298 N.J. Super. 13, 1997 N.J. Super. LEXIS 81
CourtNew Jersey Superior Court Appellate Division
DecidedFebruary 24, 1997
StatusPublished
Cited by15 cases

This text of 688 A.2d 1088 (Mautz v. J.P. Patti Co.) is published on Counsel Stack Legal Research, covering New Jersey Superior Court Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mautz v. J.P. Patti Co., 688 A.2d 1088, 298 N.J. Super. 13, 1997 N.J. Super. LEXIS 81 (N.J. Ct. App. 1997).

Opinion

The opinion of the court was delivered by

KING, P.J.A.D.

I.

This case involves interpretation of a contractual indemnification clause in an agreement between a general contractor and a subcontractor. The case arises from a personal injury claim made by the subcontractor’s employee sustained at a June 4, 1990 job-site accident during installation of a drainage system. The Law Division judge dismissed the general contractor’s claim for contractual indemnity, finding the “hold harmless” clause in the contract nonefficacious. We disagree and reverse. We find that the clause expressly and unambiguously provides for partial indemnity, to the extent the subcontractor’s negligent acts or omissions contributed to its employee’s injury.

II.

In 1992 plaintiff Derek Mautz sued several defendants for his severe personal injury, partial amputation of an arm, suffered on June 4, 1990 while installing a drainage grate in a catch-basin at a [16]*16construction site in Ringwood Industrial Park, Ringwood, New Jersey. Plaintiff was an employee of Gagliano Brothers Excavating Company (Gagliano), a subcontractor. Plaintiff sued Remy Associates (Remy), the owner acting as general contractor on the job-site; Caterpillar, Inc., the manufacturer- of the front-end loader involved in the accident; and Foley Machinery Co., which sold the loader to his employer, Gagliano. Remy then joined plaintiffs employer, Gagliano, as a third-party defendant seeking contractual indemnification.

In August 1994 Gagliano moved to dismiss Remy’s claim for contractual indemnity. Remy responded by filing a cross-motion for summary judgment. After argument, the Law Division judge granted Gagliano’s motion and denied Remy’s motion, ruling as a matter of law that the contractual indemnity clause was ambiguous and ineffective in shifting any portion of the cost of plaintiffs claim from Remy to Gagliano.

After this adverse ruling, Remy settled plaintiffs claim for about $1,150,000. A consent judgment memorialized the settlement. A few months later plaintiff settled with the remaining defendants, Caterpillar and Foley, for $400,000. Remy then appealed from the adverse ruling on its indemnity claim.

III.

Plaintiff was working for Gagliano laying pipe and installing a catch-basin in an excavated trench about five-feet deep. Joe Gagliano was operating a Caterpillar 920 front-end loader. While plaintiff was lowering a two-hundred-pound steel grate for the catch-basin into the excavation, the Caterpillar lunged forward, fell into the excavation, and trapped plaintiffs arm and hand between the catch-basin and the bucket. Plaintiff lost part of his arm.

Remy was the general contractor. (Patti Roofing, an affiliate of Remy, was actually the owner.) Gagliano was a subcontractor hired to perform site clearing, excavation and drainage work. Remy contracted with Gagliano in a standard-form written sub[17]*17contract entitled “Standard Form of Agreement Between Contractor and Subcontractor,” American Institute of Architects (AIA) Document A401, executed on September 7,1989.

Plaintiff recovered his workers’ compensation benefits and then targeted Remy, as general contractor, in this third-party action. Plaintiff relied on two expert engineers, Robert Ehrlich and James Vigani, to establish Remy’s liability in this action. Their reports are part of this record and were relied upon in the summary judgment proceedings. These two experts blamed the accident in substantial part on both Remy and Gagliano.

Ehrlich said the accident was caused by the collapse of the trench wall because it was not properly shored as required by Occupational Health and Safety Administration (OSHA) regulations. Ehrlich concluded responsibility fell on: (1) Gagliano Brothers for not shoring the walls of the trench; (2) Joe Gagliano, personally, for operating the front-end loader too close to the excavation wall; (3) Remy, acting as both owner and general contractor, as “responsible for the general safety of the worksite and responsible that safe work practices were observed;” (4) Foley for selling an unsafe vehicle; and (5) Caterpillar for failure to warn and improper design.

Vigani concluded that two OSHA violations caused the accident: (1) no shoring or stabilization of the excavation walls existed, and (2) no stop logs or barricades placed to prevent the operator from driving the equipment into the excavation. Vigani said that:

Based upon my review of the material provided, and the above understandings, it is my opinion that the accident in which Mr. Mautz was injured was a direct result of the lack of an adequate safety program at the job site, and by improper and unsafe procedures being used by Gagliano Brothers Excavation. It is my further opinion that it was the general contractor’s LRemy] responsibility to implement a safety program and to ensure, through monitoring of the work performed, that the program was being complied with. Had an appropriate safety program been in place and been complied with, the subject accident would not have occurred.

Confronted with this proposed evidence supporting plaintiffs liability case, Remy settled and turned to this contractual indemnity claim.

[18]*18IV.

The indemnification clause in the contract between Remy, the general contractor, and Gagliano, the subcontractor, states:

11.11 Indemnification
11.11.1 To the fullest extent permitted by law, the Subcontractor shall indemnify and hold harmless the Owner, the Architect and the Contractor and all of their agents and employees from and against all claims, damages, losses and expenses including but not limited to attorney’s fees, arising out of or resulting from the performance of the Subcontractor’s Work under this Subcontract, provided that any such claim, damage, loss, or expense is attributable to bodily injury, sickness, disease, or death, or to injury to or destruction of tangible property (other than the Work itself) including the loss of use resulting therefrom, to the extent caused in whole or in part by any negligent act or omission of the Subcontractor or anyone for whose acts he may be liable, regardless of whether it is caused in part by a party indemnified hereunder. Such obligation shall not be construed to negate, or abridge, or otherwise reduce any other right or obligation of indemnity which would otherwise exist as to any party or person described in this Paragraph 11.11.
11.11.2 In any and all claims against the Owner, the Architect, or the Contractor or any of their agents or employees by any employee of the Subcontractor, anyone directly or indirectly employed by him or anyone for whose acts he may be liable, the indemnification obligation under this Paragraph 11.11 shall not be limited in any way by any limitation on the amount or type of damages, compensation or benefits payable by or for the Subcontractor under workers’ or workmen’s compensation acts, disability benefit acts or other employee benefit acts.
[emphasis supplied.]

Perhaps also pertinent to the understanding of the parties is:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Paul Sobotor v. Mt. Arlington Holdings, LLC
New Jersey Superior Court App Division, 2025
W. C. English, Inc. v. Rummel, Klepper & Kahl, LLP
934 F.3d 398 (Fourth Circuit, 2019)
Concord & Cumberland Horizontal Prop. Regime v. Concord & Cumberland, LLC
819 S.E.2d 166 (Court of Appeals of South Carolina, 2018)
Oltmans Construction Co. v. Bayside Interiors, Inc.
10 Cal. App. 5th 355 (California Court of Appeal, 2017)
Estate of Jack D'Avila by Tiago D'avila, Administrator Ad
121 A.3d 388 (New Jersey Superior Court App Division, 2015)
MT BUILDERS, LLC v. Fisher Roofing Inc.
197 P.3d 758 (Court of Appeals of Arizona, 2008)
Englert v. the Home Depot
911 A.2d 72 (New Jersey Superior Court App Division, 2006)
North American Site Developers, Inc. v. MRP Site Development, Inc.
63 Mass. App. Ct. 529 (Massachusetts Appeals Court, 2005)
East-Harding, Inc. v. Horace A. Piazza & Associates
91 S.W.3d 547 (Court of Appeals of Arkansas, 2002)
Ryan v. United States
233 F. Supp. 2d 668 (D. New Jersey, 2002)
Azurak v. Corporate Prop. Investors
790 A.2d 956 (New Jersey Superior Court App Division, 2002)
Hagerman Construction Corp. v. Long Electric Co.
741 N.E.2d 390 (Indiana Court of Appeals, 2000)
Pingaro v. Rossi
731 A.2d 523 (New Jersey Superior Court App Division, 1999)
Mautz v. JP PATTI COMPANY
700 A.2d 876 (Supreme Court of New Jersey, 1997)
Leitao v. Damon G. Douglas Co.
693 A.2d 1209 (New Jersey Superior Court App Division, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
688 A.2d 1088, 298 N.J. Super. 13, 1997 N.J. Super. LEXIS 81, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mautz-v-jp-patti-co-njsuperctappdiv-1997.