Mattson v. Julian

678 P.2d 654, 209 Mont. 48
CourtMontana Supreme Court
DecidedMarch 28, 1984
Docket83-445
StatusPublished
Cited by4 cases

This text of 678 P.2d 654 (Mattson v. Julian) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mattson v. Julian, 678 P.2d 654, 209 Mont. 48 (Mo. 1984).

Opinion

MR. JUSTICE WEBER

delivered the Opinion of the Court.

Defendant Gordon Julian appeals from the judgment of the Eighteenth Judicial District Court, Gallatin County, *50 awarding plaintiffs $6,382.33, plus interest, due on a house construction contract. We affirm.

The issues are:

1. Whether evidence of defective performance is admissible under a general denial?

2. Whether there is substantial evidence to support the District Court’s determination that cost estimates did riot limit the cost-plus payment term of the construction contract?

3. Whether the District Court’s finding of an account stated was erroneous?

On June 1, 1978, George Mattson, Dick Prugh and James Lenon, doing business as Design Construction, entered into a contract for the construction of a house for Gordon Julian in Bear Canyon, Gallatin County, Montana. The written contract was a standard form agreement between the owner and the contractor, printed by the American Institute of Architects, with individual provisions filled in by the parties. The contract provided that the contractor would be compensated for services at 15% of the cost of the work. Such a contract is known as a “cost-plus” contract.

Design Construction performed services, supplied materials and submitted statements to Julian on a regular basis from July 10, 1978 to January 5, 1979. Julian made payments of $31,636.90 out of an alleged'total of $38,519.23 due under the contract. On December 5, 1978, Design Construction sent Julian a statement and a letter discussing the work that remained to be done. No payment was made on that statement. Another statement was sent on January 5, 1979 and no payment was received. Design Construction contended that there remained an unpaid balance of $6,882.33. Julian moved into the house in early December 1978.

On or about January 29, 1979, plaintiffs and Julian met to review the account. After the meeting, Design Construction sent Julian several statements confirming $6,882.33 as the amount due and on April 17, 1980, a letter was sent reiter *51 ating the amount due and demanding payment. On April 30,1980, Julian paid $500 on the account, reducing the balance to $6,382.33. No further payments were made by Julian. Plaintiffs received no objection to the stated amount due.

Plaintiffs filed their complaint on May 14, 1981. Default was entered on June 5, 1981, but a motion to dismiss was filed by Julian on June 8, 1981 and the District Court allowed the default to be set aside. On July 15, 1981, Julian filed an answer, generally denying the claim of work and services performed pursuant to the contract and generally denying that an account had been stated. The answer contained no specific denial of conditions precedent nor any statement of counterclaim.

The case was heard by the District Court without a jury on January 6 and 17, 1983. At trial Julian presented evidence that some of the work performed by Design Construction was defective. Other evidence established that plaintiffs agreed to meet with Julian on two separate occasions to review alleged defective work, but Julian failed to appear. Also, Design Construction sent a mason to the house to repair alleged defects but the mason was refused entrance to the house. Plaintiffs objected to admission of evidence on claimed defects because Julian had failed to plead defects as a defense as required by the Rules of Civil Procedure. Julian never attempted to amend his pleadings or obtain a continuance. The Court ruled that failure to specifically plead defects barred evidence of defects under the Rules.

The Court found that the total cost of materials and services by Design Construction was $38,519.23, or approximately 10% over the estimated cost of $35,000. The Court found that the $35,000 figure was merely an estimate and that Julian’s payment obligation was controlled by the cost-plus agreement. The Court found that Design Construction substantially performed the contract and that the sum of $6,382.33 plus interest was due. Julian appeals.

*52 I

Julian argues that defective workmanship defeats recovery under the contract and that he is entitled to show defects in workmanship under a general denial. He contends that correction of defects was a condition precedent to recovery and that evidence of defects is defensive and need not be pled as a counterclaim. He contends that the District Court has deprived him of his right to present a defense. We disagree.

Whether Julian’s evidence of alleged defective performance was intended to support a counterclaim or was merely defensive does not affect the outcome of this issue. In either event, Julian failed to properly plead and his evidence was properly rejected by the District Court.

Julian contends that correction of defects was a condition precedent to recovery by plaintiffs. Section 28-1-403, MCA defines “condition precedent” as “one which is to be performed before some right dependent thereon accrues or some act dependent thereon is performed.” Julian’s theory was that alleged defective performance and failure to correct by Design Construction precluded accrual of their right to receive payment.

However, Rule 9(c)), M.R.Civ.P. provides:

“In pleading the performance or occurrence of conditions precedent, it is sufficient to aver generally that all conditions precedent have been performed or have occurred. A denial of performance or occurrence shall be made specifically and with particularity.” (Emphasis added.)

In Treasure State Industries v. Leigland (1968), 151 Mont. 288, 443 P.2d 22, decided after Montana’s adoption of Rule 9(c), we stated:

“The conditions precedent referred to in this rule are those the performance or occurrence of which are prerequisite to a claim upon which relief can be granted. In most instances there is no question of the performance of conditions precedent and Rule 9(c) thus puts the burden on the defendant to raise the issue when there is actually a question. Under this rule a general denial will not put the per *53 formance or occurrence of any condition in issue.” 151 Mont. at 295-96, 443 P.2d at 26 (Emphasis added.)

Other authorities are in agreement with the Treasure State Industries rule. 1 Moore’s Federal Practice Rules Pamphlet section 9.3[3] (1984); McKee-Berger-Mansueto v. Board of Education (7th Cir. 1980), 626 F.2d 559.

Plaintiffs alleged in their complaint that the parties executed a construction contract on a cost-plus basis, that plaintiffs had performed work under the contract and that defendant owed plaintiffs $6,382.33. Julian’s answer generally denied all allegations in the complaint on the basis of insufficient knowledge. Julian did not plead defective performance or failure to correct. No specific denial of any condition precedent appears in Julian’s pleadings.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Masters Group v. Comerica Bank
2021 MT 161 (Montana Supreme Court, 2021)
Zimmerman v. Connor
1998 MT 131 (Montana Supreme Court, 1998)
Able, Inc. v. Kuzara
785 P.2d 1021 (Montana Supreme Court, 1990)
Julian v. Mattson
710 P.2d 707 (Montana Supreme Court, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
678 P.2d 654, 209 Mont. 48, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mattson-v-julian-mont-1984.