Matter of Stange v. Thompson-Starrett Co.

183 N.E. 485, 261 N.Y. 37, 1933 N.Y. LEXIS 1254
CourtNew York Court of Appeals
DecidedJanuary 17, 1933
StatusPublished
Cited by9 cases

This text of 183 N.E. 485 (Matter of Stange v. Thompson-Starrett Co.) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Matter of Stange v. Thompson-Starrett Co., 183 N.E. 485, 261 N.Y. 37, 1933 N.Y. LEXIS 1254 (N.Y. 1933).

Opinion

Kellogg, J.

Thompson-Starrett Company contracted with the owner of certain premises for the dismantling of the buildings standing thereupon, and the erection of a department store in their place. It subcontracted with Ottomar Stange and Anna A. Stange, composing the firm of Stange Construction Company, for the performance of a substantial portion of the work. This included all dismantling, all excavating, the building of foundation walls, the laying of all concrete below the under side of the first floor level, and various other items. The contract provided: The sum to be paid by Contractor to Sub-Contractor for the work shall be Four Hundred Thirty-two Thousand and No/100 dollars ($432,000.00), subject to additions and deductions as herein provided, which sum is herein referred to as the Price.”

The contract made provision that the contractor should have the right, as construction proceeded, to direct any changes in the work to be made, which it might deem expedient, whether these changes increased or diminished the work. However, no such changes should be made except upon written order of contractor signed by an executive officer, stating the additional time allowed, if any, and the amount to be added or deducted from the Price.” The following clause was to govern in case of changes: “ Unit prices, if any are named in this contract, shall be used in determining the value of such changes.” *40 There followed this clause: In case of disagreement as to the adjustment of the Price or of the time of completion Sub-Contractor shall proceed with the work and the determination of such amount or time shall be referred to arbitration as herein provided.”

During the progress of the work some fifty changes were ordered made, and the cost of the work was greatly increased. The parties were unable to agree that the prices stated in the orders for the changes fairly expressed the additional cost. Consequently, the subcontractor, as provided in the contract, proceeded with the work, awaiting a subsequent determination by arbitration of increased costs. After completion, pursuant to an order of Special Term, modified by an order of the Appellate Division, arbitrators were appointed who took up the work assigned to them. An award was finally made in favor of the subcontractor against the contractor in the sum of $234,702.12, with interest. The contractor moved to set aside the award; the subcontractor moved to confirm the award. The award was confirmed, and judgment has followed for the amount of the award.

The contract does in fact contain a provision naming unit prices. The schedule therein given is preceded by the following clause: “ It is hereby understood and agreed that should any changes be made in the work as herein contemplated, the Price ” mentioned in article III shall be increased or decreased, as the case may be, by the amount of work added or omitted, multiplied by the following unit prices.” Then follow twenty-eight items, describing work to be done or materials to be furnished, and the agreed sum per unit to be paid therefor. Thus excavating by steam shovel is priced at $0.95 per cubic yard place measurement; hand excavating, for general purposes, is priced at $2.25 per cubic yard; for piers, pits and trenches at $2.45; for underpinning at $3.25. These prices are to prevail whether the additional excavation is done at a high or a low level, whether the *41 material excavated is sand, hard pan or rock. All concrete work is to be done for named prices “ per cubic yard, in place,” various types of work commanding greater or less prices. Thus concrete “ in place,” whether laid in the wet or in the dry, no matter what difficulties might attend the laying, is to be paid for at a set and invariable figure, named for a particular type of work.

It was evidently the concept of the parties that all subcontracting work, whether done in precise accord with the work originally specified and planned, or whether done in accord with altered plans, increasing or diminishing the work, should constitute an integral part of the subject-matter of the express contract, to be governed by its terms, and to be paid for at contract prices. “All clauses of this Contract shall apply to any changes, omissions, or extra work in like manner and to the same extent as to the work contracted for, and no changes, omissions, or extra work shall annul or invalidate this contract.” With this thought in mind the parties made provision for arbitration as follows: In case the parties hereto disagree in relation to any clause in this contract, the question shall be referred to a Board of Arbitration consisting of three (3) disinterested parties, one nominated by Contractor, one by Sub-contractor, these two to select a third.” We have construed this particular clause to signify that disputes “ not being referable to any clause of this contract,’ were not made arbitrable by the parties.” (Matter of Smith Fireproof Constr. Co. v. Thompsom-Starrett Co., 247 N. Y. 277, 279.) Specifically, the contract provided, in reference to alterations of the contract work, as we have already noted: “ In case of disagreement as to the adjustment of the Price or of the time of completion Sub-contractor shall proceed with the work and the determination of such amount or time shall be referred to arbitration as herein provided.”

The controversy to be arbitrated must be “ in relation to any clause in this contract.” Obviously a claim made *42 for the reasonable value of the work done, on the theory that the contract has been abandoned and no longer governs, cannot constitute an issue under any clause in this contract.” Again, the disagreement, so far as it relates to alteration, in order to be arbitrable, must be one involving the adjustment of the Price.” If the contract is to be regarded as abandoned, and a recovery to be had upon a quantum meruit, no “ adjustment ” of the contract Price ” can be involved, for to allow such a recovery would be, not to modify the price, but to scrap it utterly. Self-evidently, if a contract does not apply to control a price, it does not apply to compel an arbitration of the price. The respondents would, therefore, appear to be in this inescapable dilemma: If the award made by the arbitrators is a recovery, based solely upon the reasonable value of the work done, regardless of the price, they had no authority to make it, since only contract disagreements were arbitrable. On the other hand, if the award is intended as a recovery based upon liability under the contract, it may not stand, since it involves a repudiation of every contract term, in relation to the adjustment of the price.

That the subcontractors, the petitioners herein, regarded the contract as having been utterly abandoned by the parties, and, therefore, wholly inapplicable to determine their claim, is clearly apparent. They presented a claim in quantum meruit for the recovery of the actual cost to them of all work done and materials furnished, plus a percentage for profit.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Norris v. Cooper
461 N.E.2d 1261 (New York Court of Appeals, 1984)
Allen Knitting Mills, Inc. v. Dorado Dress Corp.
39 A.D.2d 286 (Appellate Division of the Supreme Court of New York, 1972)
Tufano Contracting Corp. v. State
25 A.D.2d 329 (Appellate Division of the Supreme Court of New York, 1966)
Johnson, Drake & Piper, Inc. v. New York State Thruway Authority
22 A.D.2d 321 (Appellate Division of the Supreme Court of New York, 1965)
In re the Arbitration between Deering Milliken & Co. & Boepple Sportswear Mills, Inc.
4 A.D.2d 652 (Appellate Division of the Supreme Court of New York, 1957)
Scovill Local 1604 v. Scovill Manufacturing Co.
17 Conn. Super. Ct. 420 (Connecticut Superior Court, 1951)
Delma Engineering Corp. v. John A. Johnson Contracting Corp.
267 A.D. 410 (Appellate Division of the Supreme Court of New York, 1944)

Cite This Page — Counsel Stack

Bluebook (online)
183 N.E. 485, 261 N.Y. 37, 1933 N.Y. LEXIS 1254, Counsel Stack Legal Research, https://law.counselstack.com/opinion/matter-of-stange-v-thompson-starrett-co-ny-1933.