Matter of Kandiyohi Co-Op. Elec. Power

455 N.W.2d 102, 1990 WL 57623
CourtCourt of Appeals of Minnesota
DecidedMay 8, 1990
DocketC8-89-2025
StatusPublished
Cited by1 cases

This text of 455 N.W.2d 102 (Matter of Kandiyohi Co-Op. Elec. Power) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Matter of Kandiyohi Co-Op. Elec. Power, 455 N.W.2d 102, 1990 WL 57623 (Mich. Ct. App. 1990).

Opinion

455 N.W.2d 102 (1990)

In the Matter of the Complaint by KANDIYOHI COOPERATIVE ELECTRIC POWER ASSOCIATION against Willmar Municipal Utilities Commission for Extending Electric Facilities in and Adjacent to Westwind Estates.

No. C8-89-2025.

Court of Appeals of Minnesota.

May 8, 1990.

*103 Richard L. Ronning, Willmar City Atty., Willmar, Byron F. Starns, Susan M. Robiner, Leonard, Street & Deinard, Minneapolis, for Relator Willmar Mun. Utilities Com'n.

Harold P. LeVander, Jr., Seth M. Colton, Maun & Simon, St. Paul, William N. Bernard, Bernard & Johnson, Willmar, for Kandiyohi Co-op. Elec. Power Ass'n.

Hubert H. Humphrey, III, Atty. Gen., Margie Hendriksen, Sp. Asst. Atty. Gen., St. Paul, for Minnesota Public Utilities Com'n.

Jocelyn F. Olson, Asst. Atty. Gen., St. Paul, for Minnesota Dept. of Public Service.

Considered and decided by SHORT, P.J., NORTON and MULALLY,[*] JJ.

OPINION

EDWARD D. MULALLY, Judge.

Relator Willmar Municipal Utilities Commission challenges two orders by the Minnesota Public Utilities Commission prohibiting relator from extending electrical service to new customers in an area previously assigned to respondent Kandiyohi Cooperative Power Association but recently annexed by the City of Willmar. We affirm.

FACTS

Relator City of Willmar Municipal Utilities Commission (Willmar) is an electric utility owned by the City of Willmar (city). Respondent Kandiyohi Cooperative Power Association (Kandiyohi) is a rural electric cooperative association whose principal offices are located in the city.

In 1975 and thereafter, Kandiyohi and Willmar were assigned service areas in and around the city, pursuant to orders by the Minnesota Public Utilities Commission (MPUC). The orders resulted in the assignment to both Kandiyohi and Willmar of separate areas within a development known as Westwind Estates.

On or about April 5, 1989, the city annexed property located in Westwind Estates. Several of the annexed lots were located in Kandiyohi's assigned service area.

Although there were not yet any customers in the annexed area, Kandiyohi did have electric facilities bordering the area. Specifically, Kandiyohi had an overhead distribution line running along the south end of Lot 1 Block 1. The line was the type normally used to serve residential customers, although it had not been outfitted with transformers. In addition, Kandiyohi had a three-phase distribution line located at the south boundary of Lot 1 Block 1, capable of serving residential customers or delivering higher grade power. On the date of annexation, Willmar had no electric facilities in or bordering the annexed area.

In June 1989, the new owner of Lot 1 Block 1 began constructing a house. Willmar thereafter extended an electric line into Kandiyohi's assigned area to serve this customer. Willmar did not receive prior consent from Kandiyohi and did not obtain approval from the MPUC. Kandiyohi objected to Willmar's extension of service in its assigned area, and also began preparations to provide temporary power to the new house.

Willmar filed a motion in district court, seeking to prohibit Kandiyohi from extending service to customers in the annexed area without a franchise from the city. On July 14, 1989, the district court issued an order permanently enjoining Kandiyohi from extending electric service within Westwind Estates unless Kandiyohi obtained such a franchise.

Kandiyohi thereafter filed a complaint with the MPUC, alleging that Willmar's extension of services was improper and duplicative. Kandiyohi requested that the MPUC order Willmar to remove its facilities from Kandiyohi's assigned area.

On August 9, 1989, the MPUC issued an order determining that Kandiyohi had facilities *104 in place capable of adequately serving the annexed area. The MPUC concluded that before Willmar could serve the area, it was obligated to negotiate the necessary terms of acquiring Kandiyohi's facilities. The MPUC subsequently issued an order denying reconsideration. Willmar has obtained a writ of certiorari, seeking review of the MPUC's order and order denying reconsideration.

ISSUES

1. Did the MPUC have jurisdiction to determine who should serve the annexed area?

2. Did the MPUC err by determining that the annexed area was already receiving electric service from Kandiyohi?

3. Did the MPUC err by failing to conduct a contested case hearing?

ANALYSIS

I.

In a prior appeal to this court, Kandiyohi and the MPUC sought review of the district court order in this matter. City of Willmar Municipal Utilities Commission v. Kandiyohi Cooperative Power Assoc., 452 N.W.2d 699 (Minn.App.1990). In that opinion, we addressed Willmar's estoppel, jurisdiction, and separation of powers arguments, and determined that the MPUC, rather than the district court, had the authority to determine whether the assigned service area was previously receiving electric service from Kandiyohi.

II.

When statutory interpretation is at issue, * * * a reviewing court is not bound by the agency's determination. An agency decision is entitled to some deference, "where (1) the statutory language is technical in nature, and (2) the agency's interpretation is one of longstanding application."

In re Hibbing Taconite Co., 431 N.W.2d 885, 889 (Minn.App.1988) (citations omitted).

Minnesota electric utilities' assigned service areas are governed by Minn.Stat. §§ 216B.37-.44 (1988). Minn.Stat. § 216B.40 provides for exclusive service rights within an assigned area, and Minn. Stat. § 216B.41 indicates that annexation of any part of an assigned area shall not affect the existing utility's rights to serve that area, unless the municipally owned utility elects to purchase the existing utility's facilities and property as provided in Minn.Stat. § 216B.44.

Minn.Stat. § 216B.44 is the statutory provision which has led to the dispute in the present case.

Notwithstanding the provisions of sections 216B.38 to 216B.42, whenever a municipality which owns and operates an electric utility * * * extends its corporate boundaries through annexation * * * the municipality shall thereafter furnish electric service to those areas unless the area is already receiving electric service from an electric utility, in which event, the municipality may purchase the facilities of the electric utility serving the area.

Id. If the municipality elects to purchase the facilities of the utility serving the area, the parties must arrive at a decision regarding appropriate compensation. If the parties are unable to arrive at an agreement regarding compensation, either party may apply to the MPUC for a hearing to determine the sale terms. Minn.Stat. § 216B.44.

Although Minn.Stat. § 216B.44 provides for a hearing by the MPUC after it is determined that an annexed area was already receiving service, the legislature has not specifically indicated what to do if there is a question whether the area was "receiving electric service" prior to annexation. Here, the parties' dispute centers on the question whether the area annexed by the city was already "receiving electric service" from Kandiyohi.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Decision to Deny the Petitions for a Contested Case Hearing
924 N.W.2d 638 (Court of Appeals of Minnesota, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
455 N.W.2d 102, 1990 WL 57623, Counsel Stack Legal Research, https://law.counselstack.com/opinion/matter-of-kandiyohi-co-op-elec-power-minnctapp-1990.