Matter of Green Earth Farms Rockland, LLC v. Town of Haverstraw Planning Bd.

2017 NY Slip Op 6273, 153 A.D.3d 823, 60 N.Y.S.3d 381
Appellate Division of the Supreme Court of the State of New York·Decided August 23, 2017·No. 2015-00526·Published·Cited by 4 cases

Opinion

Appeal from a judgment of the Supreme Court, Rockland County (Victor J. Alfieri, Jr., J.), dated October 15, 2014. The judgment, insofar as appealed from, (1) granted a petition filed pursuant to CPLR article 78 challenging the approval of a *824 development project, (2), in effect, annulled a determination that a second Supplemental Environmental Impact Statement was not required, (3) annulled a site plan approval, and (4) remitted the matter to the respondent Town of Haverstraw Planning Board for further proceedings.

Ordered that the appeal by the Town of Haverstraw Building Department is dismissed, as that party is not aggrieved by the judgment appealed from (see CPLR 5511); and it is further,

Ordered that on the appeal by the Town of Haverstraw Planning Board and Mt. Ivy Partners, Inc., the judgment is modified, on the law, (1) by adding to the first decretal paragraph thereof, after the phrase “the petition is granted,” the words “insofar as asserted by the petitioners Paint’n Place, Inc., Parkway Realty Corp., Good Counsel Realty Ltd., and 202 United Development Corp.,” and (2) by adding a decretal paragraph thereto dismissing the petition insofar as asserted by the petitioner John McDowell; as so modified, the judgment is affirmed insofar as appealed from by the Town of Haverstraw Planning Board and Mt. Ivy Partners, Inc., with costs payable to the petitioners.

In 2004, a developer, Davies Farm, LLC (hereinafter Davies Farm), applied for site plan approval and a zoning amendment in connection with proposed residential and commercial development of a 53.3-acre parcel of land located in the adjacent towns of Haverstraw and Ramapo (hereinafter the proposed development plan). In April 2005, the Town of Haverstraw Planning Board (hereinafter the Planning Board), as the lead agency under the State Environmental Quality Review Act (ECL art 8; hereinafter SEQRA), issued a positive declaration regarding the application for the proposed development plan and required the preparation of a draft environmental impact statement (hereinafter DEIS). After the DEIS was submitted in 2006, Davies Farm changed the proposed development plan by eliminating the proposed residential development in the Town of Haverstraw to avoid the need for a zoning amendment (hereinafter the supplemental proposed development plan). In response, the Planning Board required a Supplemental Environmental Impact Statement (hereinafter SEIS) as to the supplemental proposed development plan. In November 2009, the Planning Board accepted a final SEIS and, pursuant to SEQRA, adopted a findings statement certifying that the approved supplemental proposed development plan minimized or avoided adverse environmental impacts to the maximum extent practicable. The supplemental proposed development plan at that time consisted of proposed com *825 mercial development in the Town of Haverstraw (hereinafter the Haverstraw commercial phase) and a mix of residential and commercial uses, including “a deli/coffee shop” in the Town of Ramapo (hereinafter, respectively, the Ramapo residential phase and the Ramapo commercial phase).

In January 2012, the property’s new owner, Mt. Ivy Partners, LLC (hereinafter Mt. Ivy), applied to the Planning Board for preliminary and final site plan approval for the Haverstraw and Ramapo commercial phases of the project. However, Mt. Ivy’s proposed Ramapo commercial phase was changed to include a deli/coffee shop with gas pumps in the Town of Ramapo, and the site plan depicted a 7,000-square-foot convenience store with 16 gas pumps. After soliciting comments from the public, consultants, and other agencies, the Planning Board issued a resolution dated November 28, 2012, determining that a second SEIS was not required. The Planning Board granted the requested preliminary and final site plan approval subject to certain conditions, requiring Mt. Ivy, among other things, to obtain all required approvals from the Town of Ramapo and the Rockland County Department of Health. The resolution did not mention the proposed gas station.

The petitioners, most of whom are owners of properties near the site of the supplemental proposed development plan, commenced this proceeding pursuant to CPLR article 78 against the Planning Board, Mt. Ivy, and the Town of Haverstraw Building Department (hereinafter the Building Department). The petition sought review of the Planning Board’s determination finding that the preparation of a second SEIS was not warranted and granting the application for site plan approval. In the judgment appealed from, the Supreme Court determined that all the petitioners had standing under SEQRA to challenge the Planning Board’s determination. Further, the court determined that the Planning Board failed to take the requisite “hard look” at the change in the proposed development from a deli/coffee shop to a large convenience store with 16 gas pumps. Accordingly, the court granted the petition, in effect, annulled the SEQRA determination, annulled the site plan approval, and remitted the matter to the Planning Board for the preparation of a second SEIS, in effect, limited to examining whether there were significant adverse environmental impacts arising from the proposed construction of the gas station. Mt. Ivy, the Planning Board, and the Building Department appeal.

As an initial matter, in the judgment appealed from, the Supreme Court, in effect, dismissed the petition insofar as asserted against the Building Department. Accordingly, the *826 Building Department is not aggrieved by the judgment, and the appeal by the Building Department must be dismissed.

Free access — add to your briefcase to read the full text and ask questions with AI

Matter of Green Earth Farms Rockland, LLC v. Town of Haverstraw Planning Bd., 2017 NY Slip Op 6273, 153 A.D.3d 823, 60 N.Y.S.3d 381 (N.Y. Ct. App. 2017).

2017 NY Slip Op 6273 (Matter of Green Earth Farms Rockland, LLC v. Town of Haverstraw Planning Bd.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Acker v. Village of Head of the Harbor
2025 NY Slip Op 50418(U) (New York Supreme Court, Suffolk County, 2025)
Preserve Pine Plains v. Town of Pine Plains Planning Bd.
2024 NY Slip Op 50696(U) (New York Supreme Court, Putnam County, 2024)
Matter of Nunnally v. Zoning Bd. of Appeals of the Town of New Windsor
193 N.Y.S.3d 43 (Appellate Division of the Supreme Court of New York, 2023)
Matter of Veteri v. Zoning Bd. of Appeals of the Town of Kent
163 N.Y.S.3d 231 (Appellate Division of the Supreme Court of New York, 2022)