Matson, Inc. v. Lamb & Associates Packaging, Inc.

947 S.W.2d 324, 328 Ark. 705, 1997 Ark. LEXIS 353
CourtSupreme Court of Arkansas
DecidedJune 2, 1997
Docket96-606
StatusPublished
Cited by11 cases

This text of 947 S.W.2d 324 (Matson, Inc. v. Lamb & Associates Packaging, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Matson, Inc. v. Lamb & Associates Packaging, Inc., 947 S.W.2d 324, 328 Ark. 705, 1997 Ark. LEXIS 353 (Ark. 1997).

Opinion

David Newbern, Justice.

Lamb & Associates Packaging, Inc., and Jerry Don Lamb (referred to collectively as Lamb) entered an agreement with Matson, Inc. (Matson), pursuant to which Matson constructed a commercial building for Lamb in exchange for $789,543. The construction contract contained a clause requiring arbitration of disputes relating to performance or breach of the contract. Matson purchased a performance bond from United States Fidelity and Guarantee Co. (USF&G). The bond agreement incorporated the construction contract by reference. Lamb sued USF&G on the bond, alleging defects in the building and thus breach of the contract. Matson sought to intervene to protect its interests, including enforcement of the arbitration clause.

The Trial Court allowed Matson to intervene, but only to the extent of protecting its rights in the event a judgment were entered against USF&G which might then claim against Matson. Matson appeals from the order and claims that intervention should have been allowed for the purpose of protecting all its interests in the contract, including its right to arbitration. An order denying intervention is appealable. Ark. R. App. P. 2(a); Cupples Farms Partnership v. Forrest City Prod. Credit Ass’n, 310 Ark. 597, 839 S.W.2d 187 (1992). We reverse and remand because intervention should have been allowed without the limitation imposed by the Trial Court.

Matson asserts its right to unlimited intervention pursuant to Ark. R. Civ. P. 24(a) and its right to arbitration on the ground that Lamb agreed to binding arbitration in the construction contract which was incorporated in the bond upon which Lamb has brought suit. Matson also argues it is entitled to arbitration in accordance with the Federal Arbitration Act, 9 U.S.C. §§ 1 through 307 (1994). Lamb asserts that the bond is a separate agreement giving rise to a separate obligation on the part of USF&G. Lamb argues it is entitled to a jury trial of its claim against USF&G and contends that the bond is an insurance agreement which, according to Ark. Code Ann. § 16-108-201 (b) (Supp. 1995), is not subject to arbitration.

As we hold that Matson is entitled to unlimited intervention in accordance with Rule 24(a), and that § 16-108-201 (b) does not apply to prevent arbitration, we need not address the federal law.

i. Intervention

In his letter opinion the Trial Court wrote the following:

It is true that the Matson [construction] contract was referred to and incorporated by reference into the performance bond, but the incorporation was not for the purpose of pulling in the arbitration clause found in the Matson contract. To find that the arbitration clause was incorporated would render the performance bond meaningless. Rather, the incorporation of the Matson contract was for the purpose of defining the terms of USF&G’s obligations under the performance bond. * * * This Court believes that to allow Matson to intervene for the purpose of demanding arbitration would deny Plaintiff the benefits of the performance bond and would allow USF&G to simply sit by and refuse to perform one of its two obligations that it signed its name to perform.

Ark. R. Civ. P. 24(a) states:

Upon timely application anyone shall be permitted to intervene in an action: ... (2) when the applicant claims an interest relating to the property or transaction which is the subject of the action and he is so situated that the disposition of the action may as a practical matter impair or impede his ability to protect that interest, unless the applicant’s interest is adequately represented by existing parties.

Thus, three requirements must be met for intervention as a matter of right: (1) a recognized interest in the subject matter of the primary litigation; (2) an interest that might be impaired by the disposition of the suit; and (3) an interest not adequately represented by existing parties. Pearson v. First Nat’l Bank, 325 Ark. 127, 924 S.W.2d 460 (1996); Billabong Prods., Inc. v. Orange City Bank, 278 Ark. 206, 644 S.W.2d 594 (1983).

Lamb does not dispute the existence of Matson’s interest in the subject matter or the possibility that Matson’s interest might be impaired. Lamb contends, however, that Matson’s interest is adequately represented. The burden of persuasion to demonstrate adequacy of representation falls on the party opposing intervention. SEC v. Dresser Indus., Inc., 628 F.2d 1368 (C.A.D.C. 1980), cert. denied, 449 U.S. 993 (1980). Liz Claiborne, Inc. v. Mademoiselle Knitware, Inc., 1996 WL 346352 (S.D.N.Y.); CBS, Inc. v. Snyder, 136 F.R.D. 364 (S.D.N.Y. 1991). See also Wright, Miller, and Kane, Federal Practice and Procedure, Civil 2d § 1909 (1986).

An interest of a litigant is adequately represented when it is identical to, or not significantly different from, that of the proposed intervenor. National Enterprises, Inc. v. Union Planters Nat’l Bank, 322 Ark. 590, 910 S.W.2d 691 (1995). A party’s interest in enforcing arbitration rights has been held to be a significant factor in determining whether to allow intervention as of right pursuant to the federal rule, which is identical to our Rule 24(a). See CBS, Inc. v. Snyder, supra.

Even though USF&G and Matson are presently represented in this case by one attorney, Lamb has failed to show that USF&G’s interest is identical to or not significantly different from Matson’s. Although USF&G and Matson may have the same interest in disputing Lamb’s claim of breach of contract at this stage of the proceedings, it is apparent that their interests would diverge if Lamb were able to demonstrate that Matson breached the construction contract. To recover under the bond, Lamb must show that Matson has not performed or has not properly performed. It is ultimately the conduct of Matson in performance or failure to perform the construction contract which is at issue, and that is a matter Lamb agreed to arbitrate. As USF&G has a right to indemnity from Matson in the event Lamb recovers against USF&G, it is clear that USF&G may not have the same interest in arbitration that Matson does at this stage of the proceeding. Mat-son should have been allowed to intervene to protect its right to arbitration.

2. Arbitration

a. Contract interpretation

The performance bond states, “Contractor [Matson] has by written agreement dated October 31, 1991, entered into a contract with Owner [Lamb] for a new manufacturing building . . . which contract is by reference made a part hereof, and is hereinafter referred to as the Contract.” The bond then provides that “Any suit under this bond must be instituted before the expiration of two (2) years from the date on which final payment under the Contract falls due.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
947 S.W.2d 324, 328 Ark. 705, 1997 Ark. LEXIS 353, Counsel Stack Legal Research, https://law.counselstack.com/opinion/matson-inc-v-lamb-associates-packaging-inc-ark-1997.