Mathis v. Velsicol Chemical Corp.

786 F. Supp. 971, 1991 U.S. Dist. LEXIS 19794, 1991 WL 325927
CourtDistrict Court, N.D. Georgia
DecidedDecember 30, 1991
Docket1:91-cr-00024
StatusPublished
Cited by12 cases

This text of 786 F. Supp. 971 (Mathis v. Velsicol Chemical Corp.) is published on Counsel Stack Legal Research, covering District Court, N.D. Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mathis v. Velsicol Chemical Corp., 786 F. Supp. 971, 1991 U.S. Dist. LEXIS 19794, 1991 WL 325927 (N.D. Ga. 1991).

Opinion

ORDER

HAROLD L. MURPHY, District Judge.

This case is before the Court on counter-claimant’s Motion for Partial Judgment on the Pleadings and Motion to Strike. Counter-claimant (“Velsicol”) has filed this combined Motion under Federal Rule of Civil Procedure 12(c), 12(f) and 12(h). Velsicol *973 wants this Court to determine, as a matter of law, that Plaintiffs are “liable” persons under the Comprehensive Environmental Response, Compensation and Liability Act of 1980 (CERCLA) § 107(a), 42 U.S.C. § 9607(a). Velsicol also moves this Court under Rule 12(f) to strike some of Plaintiffs’ affirmative defenses.

FACTS

Plaintiffs are joint owners of land in Walker County, Georgia, and Velsicol is a chemical manufacturer located in Chattanooga, Tennessee. Between 1973 and 1984 Plaintiffs contracted with Velsicol to dispose of thousands of drums of industrial waste. Plaintiffs claim that they were under the impression that the drums were to be non-hazardous waste only, while Velsicol claims that Plaintiffs knew that some of the waste contained hazardous materials. Regardless of the parties initial understanding, Plaintiffs have subsequently learned that the drums which are buried on their land, “Marble Top Landfill”, actually contain hazardous material, not non-hazardous material. Consequently, after Plaintiffs discovered the contents of the drums, they filed this lawsuit against Velsicol, sounding in nuisance and trespass to land, seeking $500,000 compensatory and $2,000,000 punitive damages.

Velsicol has counterclaimed under three separate theories: (1) CERCLA contribution; (2) contractual indemnification; and, (3) breach of contract. Velsicol asserts that Plaintiffs are “liable” parties as that term is defined in CERCLA and as such Velsicol is entitled to contribution from Plaintiffs for all the response costs incurred by Velsicol. The second and third counterclaims arise from Velsicol’s assertions that Plaintiffs are contractually bound for either contribution or indemnification concerning the costs incurred in connection with the waste disposed of and the environmental liabilities which have subsequently arisen. At the time of filing of the counterclaim those costs totaled over $1.2 million.

Plaintiffs answered Velsicol’s counterclaims and raised numerous affirmative defenses. These defenses and Velsicol’s request to have Plaintiffs defined as liable parties under CERCLA are the subject of Velsicol’s current motion.

I. MOTION FOR JUDGMENT ON THE PLEADINGS

Velsicol has moved this Court for a Judgment on the Pleadings, under Federal Rule of Civil Procedure 12(c). Velsicol wants the Court to determine that Plaintiffs are liable parties under CERCLA. Plaintiffs claim, however, that even though they might be liable parties under CERCLA, they are covered by one of CERCLA’s statutory defenses, 42 U.S.C. § 9607(b)(3), and, therefore, the Court cannot declare them a liable party under CERCLA.

Under Rule 12(c), a party may move for judgment on the pleadings after “the pleadings are closed but within such time as not to delay the trial.” FED.R.CIV.P. 12(c). For purposes of the motion, all of the factual allegations in the adversary’s pleadings are assumed to be true and all contravening assertions in the movant’s pleadings are to be taken as false. See Parker v. DeKalb Chrysler Plymouth, 459 F.Supp. 184, 187 (N.D.Ga.1978) (Murphy, J.), aff'd, 673 F.2d 1178 (11th Cir.1982). These motions have their most utility when “all material allegations of fact are admitted in the pleadings and only questions of law remain.” 5A CHARLES A. WRIGHT & ARTHUR R. MILLER, FEDERAL PRACTICE AND PROCEDURE § 1367 at 510 (1990). Such is the situation with the Motion currently before the Court.

1. CERCLA LIABILITY AND “LIABLE” PARTIES

To establish that Plaintiffs are liable persons under CERCLA, Velsicol must prove that Plaintiffs: (1) are or were at the time of disposal owners or operators; (2) of a facility; (3) at which there was a release or threatened release of hazardous substance; and, (4) which caused another person to incur response costs consistent with the national contingency plan. 42 U.S.C. § 9607(a). See United States v. Fleet Factors Corp., 901 F.2d 1550, 1553-54 (11th Cir.1990), cert. denied, — U.S.-, *974 111 S.Ct. 752, 112 L.Ed.2d 772 (1991); Kelley v. Thomas Solvent Co., 790 F.Supp. 710 (W.D.Mich.1990); United States v. Parsons, 723 F.Supp. 757, 760 (N.D.Ga.1989) (Murphy, J.).

CERCLA liability is strict liability regardless of a person’s knowledge or intent. Parsons, 723 F.Supp. at 760. The only way to avoid liability once a party has been declared liable under CERCLA is to prove that “the release or threat of release of a hazardous substance and the damages resulting therefrom were caused solely by: (1) an act of God; (2) an act of war; (3) an act or omission of a third party other than ... one whose act or omission occurs in connection with a contractual relationship, existing directly or indirectly, with the defendant ... if the defendant established by a preponderance of the evidence that (a) he exercised due care with respect to the hazardous substance ... and (b) he took precautions against the foreseeable acts or omissions of any such third party____; or, (4) any combination of the forgoing paragraphs.” 42 U.S.C. § 9607(b) (emphasis added).

Plaintiffs have admitted that they were owners of the facility at the time the hazardous material was transported there; that they are the current owners of the facility; that the Marble Top Landfill is a facility under CERCLA; that the EPA has determined that a release or threatened release has occurred at the facility; and, that Velsicol has incurred “response costs.” Reply ofMose and Sidney Mathis at ¶ VI, VII, IX, X & XI. Instead of admitting that the response costs are consistent with the National Contingency Plan, however, Plaintiffs have stated that they do not know if the costs are consistent. Therefore, under the Federal Rules their answer is considered as a denial regarding whether the costs are consistent with the Plan. See FED.R.CIV.P. 8(b). This denial, however, does not affect whether Plaintiffs are liable parties under CERCLA, it only affects what expenses Velsicol can collect in this private action under CERCLA. See United States v. Western Processing Co., Inc., 734 F.Supp. 930, 942 (W.D.Wash.1990).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Moore v. McCalla Raymer, LLC
916 F. Supp. 2d 1332 (N.D. Georgia, 2013)
Bank of the Ozarks v. Khan
903 F. Supp. 2d 1370 (N.D. Georgia, 2012)
Niagara Mohawk Power Corp. v. Consolidated Rail Corp.
291 F. Supp. 2d 105 (N.D. New York, 2003)
Aviall Services Inc v. Cooper Indust Inc
312 F.3d 677 (Fifth Circuit, 2001)
Aviall Services, Inc. v. Cooper Industries, Inc.
263 F.3d 134 (Fifth Circuit, 2001)
Johnson County Airport Commission v. Parsonitt Co.
916 F. Supp. 1090 (D. Kansas, 1996)
Mullins v. M.G.D. Graphics System Group
867 F. Supp. 1578 (N.D. Georgia, 1994)
Pine Ridge Recycling, Inc. v. Butts County, Ga.
855 F. Supp. 1264 (M.D. Georgia, 1994)
Thaler v. PRB Metal Products, Inc.
815 F. Supp. 99 (E.D. New York, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
786 F. Supp. 971, 1991 U.S. Dist. LEXIS 19794, 1991 WL 325927, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mathis-v-velsicol-chemical-corp-gand-1991.