Mathis v. Public School District No. 103

264 P.2d 1082, 175 Kan. 453, 1953 Kan. LEXIS 456
Supreme Court of Kansas·Decided December 12, 1953·No. 39,127·Published·Cited by 13 cases

Opinion

The opinion of the court was delivered by

Parker, J.:

This is an action to recover the balance claimed to be due a contractor for the digging and construction of a water well for a school district. Plaintiff recovered and the defendant appeals.

A preliminary review of the events giving rise to the lawsuit is necessary in order to insure a proper understanding of the issues involved on appellate review. This, based on facts about which *454 there can be no dispute, will be made in the form of a summarized statement without attempting to include everything disclosed by a long and tedious record.

On July 17,1950, the parties entered into a written contract by the terms of which plaintiff agreed to dig defendant a water well, 10 feet in diameter and thirty-five feet deep, for an agreed price of $3,260. The agreement referred to contract documents designated as “general conditions,” “specifications” and “drawing.” In addition it contained provisions to the effect that the contractor was to secure and the owner to pay for the necessary materials; that the owner was to make progress payments on the 1st and 15th of each month in an amount equal to eighty-five percent of the work completed, payment for materials paid for by defendant to be deducted from the contract sum; that a schedule of prices upon which progress payments were to be based were to be set up before the work was started.

The specifications referred to in the contract provided, among other things, that the intent of the agreement was to provide a complete piece of work, notwithstanding every miscellaneous item necessarily involved, if not particularly mentioned; that the contractor should provide and pay for all materials, labor, water tools, equipment, power and transportation, and other facilities necessary for completion of the work; that the owner, without invalidating the contract, might order extra work or make changes by altering, adding to or deducting from the work, the value of which extra work or changes should be determined by estimates and acceptances in a lump sum before such work was started; that there should be no variations from the regular prices in the proposal; and that payments would be made on the basis of units set forth therein.

Subsequent to the execution of the contract and before the work was started a certain schedule of prices was set up as contemplated by both the master agreement and the specifications and, at least until sometime in October, 1950, progress payments were made to the contractor on the basis of unit prices therein set forth.

On October 26, 1950, when the well had been excavated to something under nineteen feet with a considerable showing of water, plaintiff and the duly elected officials of defendant’s governing body met for the purpose of considering conditions existing with respect to the well and at that time, without discussing any change in the contract price, entered into a mutual oral understanding and *455 agreement, whereby the parties agreed it was not going to be necessary to dig the well to the depth specified in the original contract and that instead such well was to be completed at a less depth, to be later ascertained, with an increase in the diameter. Thereafter without any determination by estimates and acceptances, as contemplated by the contract, plaintiff proceeded with the construction of the well and subsequently with the consent and approval of the governing body of the district completed and turned it over to the defendant with dimensions of twenty feet in depth and twelve feet four inches in diameter.

Following the completion of the work the parties, who as we have heretofore indicated had not complied with the terms of the contract by reaching an understanding or agreement as to the lump sum to be paid for completion of the well in its changed form, disagreed as to the amount due and payable the contractor for performing that work. Plaintiff then brought this action to recover the sum of $1,239.97, which is conceded to be the amount that would have been due him, under the terms of the original contract, after deducting all progress payments theretofore made by defendant.

Extended reference to the pleadings would merely encumber and be of no value to this opinion. Highly summarized, it suffices to say that under their allegations issues were joined on the question whether, by reason of the parties’ subsequent agreement, the original contract was modified as to dimensions only or was modified as to dimensions and contract; price for completion of the well.

With issues joined as just indicated the cause came on for trial by jury in district court for the second time. After plaintiff had adduced his evidence defendant demurred thereto. When this demurrer was overruled defendant adduced its evidence. Thereupon, after denying defendant’s request for a directed verdict, the court instructed the jury as to the law. Included in these instructions was instruction No. 5, which we pause to note was not objected to in the court below and is not now complained of, wherein the sole factual issue requiring decision by the jury was clearly outlined and defined. It reads:

“It is admitted by the parties that a written contract for the digging of the water well 10 feet in diameter and 35 feet deep and the installation of certain equipment for $3,260.00 was entered into by the parties, and that the parties verbally agreed to a modification of said contract and that the sole matter for your determination is whether plaintiff was to receive $3,260.00 under tire contract as modified, or whether he was to receive $2,020.03.
*456 “It is agreed by both parties that plaintiff has been paid $2,020.03, by the defendant paying him $1,221.37 and defendant paying $798.69 for materials used by plaintiff.
“If you find from a preponderance of the evidence that plaintiff was to receive $3,260.00 under the contract as modified then your verdict should be for plaintiff for the amount prayed for. However, if you do not so find then your verdict should be for the defendant.”

After receiving instructions the jury retired to the jury room for deliberation. Eventually it determined the factual issue submitted against defendant, returning a verdict in favor of plaintiff for the full amount sued for, and was discharged. Defendant then filed its motion for new trial wherein it moved the court “to set aside the verdict rendered and the judgment entered thereon” on divers grounds not now important. When this motion was overruled it perfected the instant appeal by giving notice that it appealed from “the verdict and judgment of the court made and entered on December 10, 1952”; the order denying its motion for new trial; the order overruling its demurrer to plaintiff’s evidence; and all other adverse orders and rulings.

At the outset, both in his brief and oral argument, appellee raises an issue which must be given first consideration. He points out, as it may be said our independent examination of the record discloses, that appellant has failed to assign or specify the overruling of his motion for new trial as error and insists that under such circumstances no question involved in that ruling is subject to appellate review. We are constrained to agree.

Free access — add to your briefcase to read the full text and ask questions with AI

Mathis v. Public School District No. 103, 264 P.2d 1082, 175 Kan. 453, 1953 Kan. LEXIS 456 (kan 1953).

264 P.2d 1082 (Mathis v. Public School District No. 103) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Rentfro v. Wheelock Bros., Inc.
364 S.W.2d 55 (Missouri Court of Appeals, 1962)
Albin v. Munsell
369 P.2d 323 (Supreme Court of Kansas, 1962)
Ford v. Sewell
366 P.2d 285 (Supreme Court of Kansas, 1961)
Weber v. Wilson
356 P.2d 659 (Supreme Court of Kansas, 1960)
Green v. State Highway Commission
337 P.2d 657 (Supreme Court of Kansas, 1959)
Rule v. Cheeseman
317 P.2d 472 (Supreme Court of Kansas, 1957)
McIntyre v. Dickinson
307 P.2d 1068 (Supreme Court of Kansas, 1957)
Drennan v. Chalfant
282 P.2d 442 (Supreme Court of Kansas, 1955)
Bishop v. Huffman
278 P.2d 588 (Supreme Court of Kansas, 1955)
Emporia Plumbing & Heating Co. v. Noland
276 P.2d 296 (Supreme Court of Kansas, 1954)
McCarty v. Kansas-Nebraska Natural Gas Co.
271 P.2d 264 (Supreme Court of Kansas, 1954)