Matheson Tri-Gas, Inc. v. Maxim Integrated Products, Inc.

444 S.W.3d 283, 2014 Tex. App. LEXIS 9562, 2014 WL 4216202
CourtCourt of Appeals of Texas
DecidedAugust 27, 2014
Docket05-13-00929-CV
StatusPublished
Cited by2 cases

This text of 444 S.W.3d 283 (Matheson Tri-Gas, Inc. v. Maxim Integrated Products, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Matheson Tri-Gas, Inc. v. Maxim Integrated Products, Inc., 444 S.W.3d 283, 2014 Tex. App. LEXIS 9562, 2014 WL 4216202 (Tex. Ct. App. 2014).

Opinions

MAJORITY OPINION

Opinion by

Justice LANG-MIERS.

Appellant Matheson Tri-Gas, Inc. sued appellee Maxim Integrated Products, Inc. alleging claims for breach of contract and fraud. Maxim counterclaimed seeking a declaratory judgment that the parties’ contract never commenced. The trial court granted summary judgment in favor of Maxim. On appeal, Matheson argues that the trial court erred by granting summary judgment in favor of Maxim. We affirm.

BACKGROUND

This is the second case involving a nitrogen gas pipeline that runs from Mathe-son’s facility to a semi-conductor facility located in Irving, Texas (the Facility). The Facility was previously owned by At-mel Corporation, and most of the events leading up to this second case are explained in detail in our opinion in Matheson Tri-Gas, Inc. v. Atmel Corp., 347 S.W.3d 339 (Tex.App.-Dallas 2011, no pet.) (Atmel). After Maxim bought the Facility and after our decision in Atmel, Matheson sought payment from Maxim for amounts Matheson alleged were due and owing under the Nitrogen Purchase and Sale Agreement between Matheson and Maxim (the Agreement). Maxim took the position that the Agreement did not commence and refused to pay Matheson.

Matheson sued Maxim for breach of contract and fraud. In response, Maxim filed an answer generally denying Matheson’s allegations and asserting various affirmative defenses. Maxim also asserted a counterclaim for declaratory judgment asking the trial court to declare that the Agreement never commenced because the parties never agreed on a commencement date as required under the terms of the Agreement. Maxim moved for summary judgment on Matheson’s claims. Mathe-son moved for partial summary judgment on certain elements of its contract claim: breach and damages. Matheson also moved for summary judgment on Maxim’s affirmative defenses and counterclaim for declaratory judgment. The trial court granted summary judgment in favor of Maxim, declared that “no enforceable agreement exists — only an unenforceable agreement to agree exists,” and dismissed Matheson’s claims. Matheson filed a motion for new trial, which the trial court denied after a hearing. Matheson timely filed its notice of appeal.

Issues on Appeal

In its “Issues Presented,” Matheson states that the central question in this appeal is whether the trial court erred by granting summary judgment in favor of [285]*285Maxim. Matheson then breaks that question down into these five issues:

(1) Did the district court misconstrue the agreement and thereby err in granting Maxim’s summary judgment motion, denying Matheson’s summary judgment motions, and ruling that Matheson take nothing on its breach of contract claim?
(2) Should the court have granted Matheson a partial summary judgment on its breach of contract claim and denied Maxim any relief on its counterclaim?
(3) Did the court err in denying Mathe-son’s motion for summary judgment on Maxim’s affirmative defenses?
(4) Should the court have granted Matheson’s motion regarding the proper measure of damages?
(5) Did the court err in granting Maxim a summary judgment on Matheson’s fraud claim as well?

Matheson’s Contract Claim

Matheson’s first four issues on appeal relate to Matheson’s contract claim. We address that claim first.

Undisputed Facts

The Agreement at issue in this case was signed by Matheson and Maxim in February 2007. At the time, Maxim was also negotiating for the purchase of the Facility from Atmel, and all three parties were negotiating the termination of Atmel’s gas supply agreement with Matheson. At the heart of this dispute is section 3(a) of the Agreement, the provision titled “TERM AND TERMINATION.” Section 3(a) states as follows:

This Agreement shall be effective as of the date hereof. The sale and purchase of Nitrogen hereunder shall be for an initial term of fifteen (15) years (“Initial Term”), which term shall commence on or about March 15, 2007 or as otherwise agreed upon by the parties in writing. The commencement date shall be memorialized in writing between the parties and is incorporated herein by reference and made a part hereof.

The final sentence of the Agreement is also relevant. It states, “This whole agreement is conditioned on [Maximj’s purchase of the [Facility].” The purchase closed, and Maxim acquired the Facility, on May 1, 2007. The parties did not enter into any other written agreements concerning the commencement date.

Each side argued that section 3(a) is unambiguous and should be construed in its favor. In its motion for summary judgment Maxim cited section 3(a) and argued that it did not breach the Agreement. More specifically, Maxim focused on the last sentence in section 3(a) and argued that its payment obligations never commenced because the parties never agreed to a commencement date in writing. In response, Matheson argued that Maxim breached the Agreement as a matter of law. Focusing on the second sentence of section 3(a), Matheson argued that the contract commenced on March 15, 2007 because the parties never agreed on a different commencement date.

The trial court agreed with Maxim. In its final summary judgment order the trial court noted that the Agreement contains a condition precedent: “This whole agreement is conditioned on [MaximJ’s purchase of the [Facility].” It also, noted that Maxim purchased the Facility on May 1, 2007. Based on those undisputed facts, the trial court explained that it granted summary judgment in favor of Maxim because the Agreement left open an essential term:

The Court finds that the commencement date of the “term” was subject to the condition precedent of Maxim’s purchase of the [Facility]. Maxim’s agreement to [286]*286purchase all of Maxim’s present and future nitrogen requirements from Mathe-son could not have commenced prior to Maxim’s purchase of the [Facility] on May 1, 2007....
The Court finds that Maxim and Mathe-son never agreed upon a commencement date of the “term” in writing and never memorialized an agreed date of commencement of the “term” of the “agreement” in writing between the parties.
[[Image here]]
The Court finds that Maxim and Mathe- ' son left such an essential and material term for later determination, which they never determined; therefore, no enforceable agreement exists — only an unenforceable agreement to agree exists.

Standard of Review

When both sides move for summary judgment, and the trial court grants one and denies the other, we consider the summary-judgment evidence, determine all questions presented, and render the judgment the trial court should have rendered. Gilbert Tex. Constr., L.P. v. Underwriters at Lloyd’s London, 327 S.W.3d 118, 124 (Tex.2010).

Analysis

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
444 S.W.3d 283, 2014 Tex. App. LEXIS 9562, 2014 WL 4216202, Counsel Stack Legal Research, https://law.counselstack.com/opinion/matheson-tri-gas-inc-v-maxim-integrated-products-inc-texapp-2014.