Master Stucco, LLC v. Cleveland Construction, Inc., is an Ohio corporation

CourtDistrict Court, M.D. Tennessee
DecidedJanuary 31, 2022
Docket3:19-cv-01064
StatusUnknown

This text of Master Stucco, LLC v. Cleveland Construction, Inc., is an Ohio corporation (Master Stucco, LLC v. Cleveland Construction, Inc., is an Ohio corporation) is published on Counsel Stack Legal Research, covering District Court, M.D. Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Master Stucco, LLC v. Cleveland Construction, Inc., is an Ohio corporation, (M.D. Tenn. 2022).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE MIDDLE DISTRICT OF TENNESSEE NASHVILLE DIVISION

MASTER STUCCO, LLC, ) ) Plaintiff / Counter-Defendant, ) ) v. ) NO. 3:19-cv-01064 ) CLEVELAND CONSTRUCTION, INC., ) JUDGE CAMPBELL JOHN SLAPNICKER, and ELLIOT ) MAGISTRATE JUDGE HOLMES CHRISTIANSEN ) ) Defendants / Counter-Plaintiffs. )

MEMORANDUM

Pending before the Court are the Parties’ motions for partial summary judgment. Defendants Cleveland Construction, Inc., John Slapnicker, and Elliot Christiansen moved for judgment in their favor on the following claims asserted by Plaintiff Master Stucco, LLC: Count One (Declaratory Judgment), Count Eight (Fraud), Count Nine (Negligent Misrepresentation), and Count Ten (Promissory Fraud).1 (Doc. No. 38). Plaintiff responded to Defendants’ Motion (Doc. No. 51), and Defendants filed a reply (Doc. No. 56). Plaintiff filed a separate Motion to Partial Summary Judgment seeking judgment in its favor on Count One (Declaratory Judgment) of its complaint. (Doc. No. 47). Defendants responded to Plaintiff’s Motion (Doc. No. 58), and Plaintiff filed a reply (Doc. No. 60). In support of the Motions, the parties filed and responded to statements of undisputed material facts (Doc. Nos. 40, 49, 53, 59). Plaintiff filed Additional

1 Defendants’ counterclaim (Doc. No. 8) alleging a single claim for breach of contract is not the subject of the pending motions. Accordingly, all references to the Complaint are to Plaintiff’s Complaint (Doc. No. 1). For ease of reference, the Court refers to Master Stucco, LLC, as “Plaintiff,” and Cleveland Construction, Inc., John Slapnicker, and Elliot Christiansen as “Defendants.” Asserted Disputed Material Facts in Response to Defendants’ Motion for Summary Judgment. (Doc. No. 40). Defendants responded to Plaintiff’s additional statement of facts, agreeing that

those facts are in dispute. (Doc. No. 57). I. BACKGROUND In June 2018, Cleveland Construction, Inc. (“CCI”), a commercial general contractor, asked Master Stucco to bid on completing the stucco and exterior finish work on a hotel that was already under construction.2 (Doc. No. 59, ¶¶ 1, 4, 6). After receiving plans for the project, walking the construction site with CCI’s project manager, John Slapnicker, and “complet[ing] a takeoff measurement of the areas on the plans where stucco was to be applied,” Glen Cruzen, founder and president of Master Stucco, submitted a written proposal. (Id., ¶ 7; Doc. No. 48- 2).

The proposal stated, “Install EIFS stucco as per plans. Here is an initial budget breakdown and the costs per item. The costs increased based on the additional items we discussed at our meeting earlier this week. My initial budget was also a bit low.” (Doc. No. 48- 2). The proposal included a breakdown of the total square footage for different depths of foam and direct application, and line items for add-ons and other expenses such scaffolding setup. (Doc. No. 59, ¶ 8; Doc. No. 48-2). The total price given was $269,439.23. (Doc. No. 48-2). The proposal concluded, “I look forward to meeting with you on Tuesday to discuss the above work in more detail. I believe our numbers to be correct, but if this amount exceeds your budget, please check at our measurements.” (Id.).

2 The work to be performed by Master Stucco included stucco and EIFS (exterior insulation and finish systems). The Court has endeavored to accurately reflect that the project included both stucco and EIFS, however, no significance should be drawn from the Court’s use of use of “stucco” rather than “stucco/EIFS” on occasion in this Memorandum. Mr. Slapnicker responded that the price exceeded his budget. (Id., ¶ 9). He also told Mr. Cruzen that other contractors submitted lower bids and that CCI had calculated a lower square

footage as less than that calculated by Master Stucco. (Id.). Following these conversations, Mr. Cruzen recalculated the total square footage of stucco/EIFS application and concluded that the initial calculations were substantially correct. (Second Cruzen Decl., Doc. No. 52, ¶ 12; June 27, 2018 email, Doc. No. 51-2). On July 16, 2018, sent a revised proposal to CCI which reduced the price to $204,835.77. (Doc. No. 48-3). The revised proposed included “a few additional areas … that were not detailed in the last written proposal” and deducted the cost of existing materials located on the job site. (Doc. No. 51-2). This proposal did not provide itemized calculations, but stated that the total amount “to complete the installation as shown on the plans” was $204,835.77. (Doc. No. 48-3).

On July 18, 2018, Mr. Slapnicker emailed Master Stucco authorization to proceed. (Doc. No. 48-5). The email stated: Please consider this your authorization to proceed with Furnishing and Installing all EIFS, Direct Applied Stucco and Metal Flashings as related to this scope of work. This scope includes all work shown for the Hotel, Commercial Building, and Parking Garage for the Springhill Suites located in Brentwood, TN. Additionally, this includes the provided materials by CCI as indicated in the attached email correspondence, that additionally includes Break Metal Flashings and Fast Flash Joint Sealant. A formal subcontract agreement will be issued in the amount of $204,836.00 (Two Hundred Four Thousand, Eight Hundred and Thirty Six Dollars), all construction documents issued up thru post bid addendum 1, Exterior Elevation Drawing Revision dated 4/4/18 and enumerated in the attached documents, etc. Please procure all design documents, permits, submittals, shop drawings, and materials for the Work. Provide all applicable notices to the governing authorities. Applicable state and local tax to be paid by Subcontractor. A 100% Payment and Performance Bond is not included in this Agreement. Furthermore, this Authorization to Proceed is based upon the agreed upon durations that will be reflected in the next Construction Schedule update. The overall agreed upon duration is based upon the commencement of work on the East Elevation starting 7/23/18 and completing the project on the South Elevation of the Parking Garage on 10/12/18. … Last, attached is a blank sample copy of our subcontract agreement for your review. The formal subcontract agreement will be sent to you under separate cover and will include job specific information and work scope items … (Doc. No. 48-5). Master Stucco began work on the project on July 21, 2018. (Doc. No. 59, ¶ 14). In August 2018, the parties agreed that CCI would make progress payments based on a Schedule of Values prepared by Mr. Slapnicker. (Id.). Master Stucco submitted applications for payment at the end of July and August totaling over $30,000. (Id.). Between July 18, 2018 (the date of the emailed authorization to proceed) and September 2018, the parties continued to negotiate the terms of a written contract. (Doc. No. 59, ¶ 15). The parties agreed to a number of changes to CCI’s form contract, resulting in at least two draft versions of the contract. (Id., ¶¶ 17-20). By September 21, 2018, the parties had not reached agreement as to the terms and CCI, which had not paid Master Stucco for any of the work performed, refused to pay until Master Stucco signed a written contract. (Doc. No. 59, ¶ 23, 24). Mr. Cruzen was leaving for a three- week vacation on September 22, 2018, and wanted to ensure Master Stucco would be paid. (Doc. No. 59, ¶ 24). He emailed Elliot Christiansen, Mr. Slapnicker’s supervisor, a signed signature page of the most recent version (dated September 6, 2018) of the revised agreement.3

3 Master Stucco states that the signatures pages for the different versions of the agreement were the same, so it is not possible to determine whether the signature page he signed was that of an earlier version of the agreement. (Doc. No. 59, ¶ 24). (Doc. No. 58, ¶ 24). In the email Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Donald G. Wexler v. White's Fine Furniture, Inc.
317 F.3d 564 (Sixth Circuit, 2003)
Carolyn T. Rodgers v. Elizabeth Banks
344 F.3d 587 (Sixth Circuit, 2003)
Tina Marie Hodge v. Chadwick Craig
382 S.W.3d 325 (Tennessee Supreme Court, 2012)
Staubach Retail Services-Southeast, LLC v. H.G. Hill Realty Co.
160 S.W.3d 521 (Tennessee Supreme Court, 2005)
US Ex Rel. Marlar v. Bwxt Y-12, LLC
525 F.3d 439 (Sixth Circuit, 2008)
Homestead Group, LLC. v. Bank of Tennessee
307 S.W.3d 746 (Court of Appeals of Tennessee, 2009)
Stacks v. Saunders
812 S.W.2d 587 (Court of Appeals of Tennessee, 1990)
Roopchan v. Adt SEC. Sys., Inc.
781 F. Supp. 2d 636 (E.D. Tennessee, 2011)
Solomon v. First American National Bank of Nashville
774 S.W.2d 935 (Court of Appeals of Tennessee, 1989)
Cadence Bank, NA v. The Alpha Trust
473 S.W.3d 756 (Court of Appeals of Tennessee, 2015)
Bible Believers v. Wayne County
805 F.3d 228 (Sixth Circuit, 2015)
Peoples Bank of Elk Valley v. Conagra Poultry Co.
832 S.W.2d 550 (Court of Appeals of Tennessee, 1991)
Oliver v. Johanson
357 F. Supp. 3d 758 (S.D. New York, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
Master Stucco, LLC v. Cleveland Construction, Inc., is an Ohio corporation, Counsel Stack Legal Research, https://law.counselstack.com/opinion/master-stucco-llc-v-cleveland-construction-inc-is-an-ohio-corporation-tnmd-2022.