MASSEY v. DUKE BUILDERS, INC
Opinion
310 Ga. 153 FINAL COPY
S20G0018. MASSEY et al. v. DUKE BUILDERS, INC.
NAHMIAS, Presiding Justice.
In this dispute between property owners and the contractor they hired to build a house, we granted the property owners’ petition for certiorari to consider two questions: (1) whether anticipated profits can be included in a materialmen’s lien and (2) if so, whether the improper inclusion of such profits renders the entire lien void. As explained below, because the Court of Appeals correctly held that anticipated profits may not be included in a lien and that their inclusion does not invalidate the entire lien, see Duke Builders, Inc. v. Massey, 351 Ga. App. 535, 537-539 (831 SE2d 172) (2019), we affirm.
1. In June 2013, John and Stephanie Massey’s home was destroyed by a fire. They hired Duke Builders, Inc., as the contractor to build a new house. The Masseys pre-approved and then paid Duke
Builders for completed work on a project-by-project basis. The payments for these projects included the actual cost of the work and materials as well as a contractor’s fee for Duke Builders, which varied from project to project. After a series of disagreements between the parties, Duke Builders stopped work on the Masseys’ property by April 2015, and the Masseys hired a new contractor. In May 2015, Duke Builders filed a materialmen’s lien in the amount of $197,107.13 against the Masseys’ property. This amount included $145,694.20 for work that had been completed but not paid for (including Duke Builders’ profits on those completed projects) and $51,412.93 as the profit Duke Builders anticipated based on its estimated cost to finish the house.
In November 2015, the Masseys filed a lawsuit against Duke Builders for, among other things, breach of contract. Duke Builders filed an answer and counterclaims, including one for breach of contract. In December 2016, the Masseys filed a motion for partial summary judgment on several claims as well as the lien, arguing that the lien should not include Duke Builders’ anticipated profits.
In April 2017, the trial court summarily denied the Masseys’ motion without specifically addressing the lien issue. In March 2018, the Masseys filed a renewed motion for summary judgment raising only the lien issue, and this time the trial court granted the motion. The court ruled that the lien amount was illegal because it included Duke Builders’ anticipated profits and that the entire lien was therefore void; the court ordered that the lien be marked as cancelled.
Duke Builders appealed the cancellation of its lien.1 The Court of Appeals affirmed the trial court’s holding that anticipated profits could not be included in the lien, but reversed the trial court’s holding that the entire lien was void. See Duke Builders, 351 Ga.
1 In March 2017, a month before their initial motion for summary judgment was denied, the Masseys filed a bond for the lien, allowing the property to be released from the lien. See OCGA § 44-14-364 (a) (“Upon the approval by the clerk [of the superior court] of the bond provided for in this Code section, the real estate shall be discharged from the lien.”). In the order granting summary judgment to the Masseys, the trial court directed that the funds held in the court’s registry as the bond be disbursed to the Masseys. Duke Builders filed its notice of appeal 12 days after the trial court entered the order. During oral argument, the Masseys’ attorney indicated that the funds had already been disbursed, but Duke Builders’ counsel disputed that, and there is no evidence of disbursement in the record.
App. at 537-539. The Court of Appeals was correct on both issues.2 2. On the first question — whether a materialmen’s lien can include anticipated but not yet earned profits — the Court of Appeals looked to the plain text of OCGA §§ 44-14-361 and 44-14- 361.1 (e) to conclude that the lien cannot include anticipated profits. See Duke Builders, 351 Ga. App. at 537. Subsection (a) (2) of OCGA § 44-14-361 authorizes contractors to file “a special lien on the real estate . . . or other property for which they furnish labor, services, or materials[.]” Subsection (b) says that the lien “may attach to the real estate of the owner for which the labor, services, or materials are furnished if they are furnished at the instance of the owner, contractor, or some other person acting for the owner or contractor[.]” Subsection (c) says that this lien “shall include the amount due and owing the lien claimant under the terms of its
2 Duke Builders had filed a cross-motion for partial summary judgment
to establish the terms of its alleged contract with the Masseys, which the trial court denied. The Court of Appeals affirmed the trial court’s denial of summary judgment on this issue. See Duke Builders, 351 Ga. App. at 539. Duke Builders did not file a petition for certiorari asking us to review this issue, and we did not ask a question about it when we granted the Masseys’ petition for certiorari. We express no opinion on that issue. See Doctors Hosp. of Augusta v. Alicea, 299 Ga. 315, 321-322 n.7 (788 SE2d 392) (2016).
express or implied contract, subcontract, or purchase order subject to subsection (e) of Code Section 44-14-361.1.”
Under subsection (c), which was added to OCGA § 44-14-361 in 2013, the lien claimant can file a lien “based on the contracted price of the work, which includes overhead costs and profit, rather than just on the value of the materials and labor that directly improved the property.” Stock Bldg. Supply v. Platte River Ins. Co., 336 Ga. App. 113, 118-119 (783 SE2d 708) (2016). Duke Builders argues that subsection (c)’s reference to the contract means that a lien claimant can include even unearned profits that were anticipated based on the contract. That statutory provision, however, restricts the lien to the “amount due and owing” under the contract. Thus, the lien is limited to amounts actually due to the claimant based on the work completed at the time the lien is filed, not amounts that the claimant was expecting to receive for future work under the contract. OCGA § 44-14-361.1 (e) also mentions the contract price but again limits the lien to the contract price of work already done by referring to the work in the past tense: “In no event shall the aggregate amount of
liens set up by Code Section 44-14-361 exceed the contract price of the improvements made or services performed.” (Emphasis supplied.)
The Court of Appeals was correct to hold that a materialmen’s lien may not include anticipated profits, and we affirm that holding.3 3. On the second question — the effect of the inclusion of nonlienable amounts in a materialmen’s lien — the Court of Appeals held that the trial court erred by ruling that the entire lien was void, reversed that portion of the trial court’s summary judgment order, and remanded the case for a determination of the lienable amount. See Duke Builders, 351 Ga. App. at 538-539. The Court of Appeals did not err.
(a) In support of its holding, the Court of Appeals looked to the
3 Duke Builders argues that it could recover its anticipated profits as
damages for breach of contract. See Dill v. Chastain, 234 Ga. App. 770, 771 (507 SE2d 872) (1998) (“When a construction contract is wrongfully breached, the basic component of damages is the net profit the contractor would have received had full performance been permitted.”). The parties appear to agree on that point of law, although their dispute as to whether Duke Builders actually had a contract to finish the Masseys’ house is a question to be resolved when this case returns to the trial court. In any event, what is lienable is a different question than what is recoverable as damages in a breach of contract action.
Free access — add to your briefcase to read the full text and ask questions with AI
849 S.E.2d 186 (MASSEY v. DUKE BUILDERS, INC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.