MASSEY v. DUKE BUILDERS, INC

849 S.E.2d 186, 310 Ga. 153
CourtSupreme Court of Georgia
DecidedSeptember 28, 2020
DocketS20G0018
StatusPublished

This text of 849 S.E.2d 186 (MASSEY v. DUKE BUILDERS, INC) is published on Counsel Stack Legal Research, covering Supreme Court of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
MASSEY v. DUKE BUILDERS, INC, 849 S.E.2d 186, 310 Ga. 153 (Ga. 2020).

Opinion

310 Ga. 153 FINAL COPY

S20G0018. MASSEY et al. v. DUKE BUILDERS, INC.

NAHMIAS, Presiding Justice.

In this dispute between property owners and the contractor

they hired to build a house, we granted the property owners’ petition

for certiorari to consider two questions: (1) whether anticipated

profits can be included in a materialmen’s lien and (2) if so, whether

the improper inclusion of such profits renders the entire lien void.

As explained below, because the Court of Appeals correctly held that

anticipated profits may not be included in a lien and that their

inclusion does not invalidate the entire lien, see Duke Builders, Inc.

v. Massey, 351 Ga. App. 535, 537-539 (831 SE2d 172) (2019), we

affirm.

1. In June 2013, John and Stephanie Massey’s home was

destroyed by a fire. They hired Duke Builders, Inc., as the contractor

to build a new house. The Masseys pre-approved and then paid Duke Builders for completed work on a project-by-project basis. The

payments for these projects included the actual cost of the work and

materials as well as a contractor’s fee for Duke Builders, which

varied from project to project. After a series of disagreements

between the parties, Duke Builders stopped work on the Masseys’

property by April 2015, and the Masseys hired a new contractor. In

May 2015, Duke Builders filed a materialmen’s lien in the amount

of $197,107.13 against the Masseys’ property. This amount included

$145,694.20 for work that had been completed but not paid for

(including Duke Builders’ profits on those completed projects) and

$51,412.93 as the profit Duke Builders anticipated based on its

estimated cost to finish the house.

In November 2015, the Masseys filed a lawsuit against Duke

Builders for, among other things, breach of contract. Duke Builders

filed an answer and counterclaims, including one for breach of

contract. In December 2016, the Masseys filed a motion for partial

summary judgment on several claims as well as the lien, arguing

that the lien should not include Duke Builders’ anticipated profits.

2 In April 2017, the trial court summarily denied the Masseys’ motion

without specifically addressing the lien issue. In March 2018, the

Masseys filed a renewed motion for summary judgment raising only

the lien issue, and this time the trial court granted the motion. The

court ruled that the lien amount was illegal because it included

Duke Builders’ anticipated profits and that the entire lien was

therefore void; the court ordered that the lien be marked as

cancelled.

Duke Builders appealed the cancellation of its lien.1 The Court

of Appeals affirmed the trial court’s holding that anticipated profits

could not be included in the lien, but reversed the trial court’s

holding that the entire lien was void. See Duke Builders, 351 Ga.

1 In March 2017, a month before their initial motion for summary judgment was denied, the Masseys filed a bond for the lien, allowing the property to be released from the lien. See OCGA § 44-14-364 (a) (“Upon the approval by the clerk [of the superior court] of the bond provided for in this Code section, the real estate shall be discharged from the lien.”). In the order granting summary judgment to the Masseys, the trial court directed that the funds held in the court’s registry as the bond be disbursed to the Masseys. Duke Builders filed its notice of appeal 12 days after the trial court entered the order. During oral argument, the Masseys’ attorney indicated that the funds had already been disbursed, but Duke Builders’ counsel disputed that, and there is no evidence of disbursement in the record.

3 App. at 537-539. The Court of Appeals was correct on both issues.2

2. On the first question — whether a materialmen’s lien can

include anticipated but not yet earned profits — the Court of

Appeals looked to the plain text of OCGA §§ 44-14-361 and 44-14-

361.1 (e) to conclude that the lien cannot include anticipated profits.

See Duke Builders, 351 Ga. App. at 537. Subsection (a) (2) of OCGA

§ 44-14-361 authorizes contractors to file “a special lien on the real

estate . . . or other property for which they furnish labor, services, or

materials[.]” Subsection (b) says that the lien “may attach to the real

estate of the owner for which the labor, services, or materials are

furnished if they are furnished at the instance of the owner,

contractor, or some other person acting for the owner or

contractor[.]” Subsection (c) says that this lien “shall include the

amount due and owing the lien claimant under the terms of its

2 Duke Builders had filed a cross-motion for partial summary judgment

to establish the terms of its alleged contract with the Masseys, which the trial court denied. The Court of Appeals affirmed the trial court’s denial of summary judgment on this issue. See Duke Builders, 351 Ga. App. at 539. Duke Builders did not file a petition for certiorari asking us to review this issue, and we did not ask a question about it when we granted the Masseys’ petition for certiorari. We express no opinion on that issue. See Doctors Hosp. of Augusta v. Alicea, 299 Ga. 315, 321-322 n.7 (788 SE2d 392) (2016). 4 express or implied contract, subcontract, or purchase order subject

to subsection (e) of Code Section 44-14-361.1.”

Under subsection (c), which was added to OCGA § 44-14-361 in

2013, the lien claimant can file a lien “based on the contracted price

of the work, which includes overhead costs and profit, rather than

just on the value of the materials and labor that directly improved

the property.” Stock Bldg. Supply v. Platte River Ins. Co., 336 Ga.

App. 113, 118-119 (783 SE2d 708) (2016). Duke Builders argues that

subsection (c)’s reference to the contract means that a lien claimant

can include even unearned profits that were anticipated based on

the contract. That statutory provision, however, restricts the lien to

the “amount due and owing” under the contract. Thus, the lien is

limited to amounts actually due to the claimant based on the work

completed at the time the lien is filed, not amounts that the claimant

was expecting to receive for future work under the contract. OCGA

§ 44-14-361.1 (e) also mentions the contract price but again limits

the lien to the contract price of work already done by referring to the

work in the past tense: “In no event shall the aggregate amount of

5 liens set up by Code Section 44-14-361 exceed the contract price of

the improvements made or services performed.” (Emphasis

supplied.)

The Court of Appeals was correct to hold that a materialmen’s

lien may not include anticipated profits, and we affirm that holding.3

3. On the second question — the effect of the inclusion of

nonlienable amounts in a materialmen’s lien — the Court of Appeals

held that the trial court erred by ruling that the entire lien was void,

reversed that portion of the trial court’s summary judgment order,

and remanded the case for a determination of the lienable amount.

See Duke Builders, 351 Ga. App. at 538-539.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

M. Shapiro & Sons, Inc. v. Yates Construction Co.
231 S.E.2d 497 (Court of Appeals of Georgia, 1976)
Summit-Top Development, Inc. v. Williamson Construction, Inc.
416 S.E.2d 889 (Court of Appeals of Georgia, 1992)
Taverrite v. Lowe's of Franklin, Inc.
304 S.E.2d 78 (Court of Appeals of Georgia, 1983)
Dill v. Chastain
507 S.E.2d 872 (Court of Appeals of Georgia, 1998)
Roofing Supply of Atlanta, Inc. v. Forrest Homes, Inc.
632 S.E.2d 161 (Court of Appeals of Georgia, 2006)
Sears, Roebuck & Co. v. Superior Rigging & Erecting Co.
170 S.E.2d 721 (Court of Appeals of Georgia, 1969)
Seaboard Construction Company v. Kent Realty Brunswick, LLC
771 S.E.2d 429 (Court of Appeals of Georgia, 2015)
Doctors Hospital of Augusta v. Alicea, Admrx.
788 S.E.2d 392 (Supreme Court of Georgia, 2016)
Hillburn v. O'Barr
19 Ga. 591 (Supreme Court of Georgia, 1856)
Pace v. Shields-Geise Lumber Co.
92 S.E. 755 (Supreme Court of Georgia, 1917)
Duke Builders, Inc. v. Massey
831 S.E.2d 172 (Court of Appeals of Georgia, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
849 S.E.2d 186, 310 Ga. 153, Counsel Stack Legal Research, https://law.counselstack.com/opinion/massey-v-duke-builders-inc-ga-2020.