MASSEY CONSTRUCTION GROUP, INC. A/A/O ARTHUR CARLSON and CAROL CARLSON v. ALEX FINCH, P.A. D/B/A FINCH LAW FIRM and FROMANG & FINCH P.A.

CourtDistrict Court of Appeal of Florida
DecidedNovember 14, 2025
Docket6D2024-1029
StatusPublished

This text of MASSEY CONSTRUCTION GROUP, INC. A/A/O ARTHUR CARLSON and CAROL CARLSON v. ALEX FINCH, P.A. D/B/A FINCH LAW FIRM and FROMANG & FINCH P.A. (MASSEY CONSTRUCTION GROUP, INC. A/A/O ARTHUR CARLSON and CAROL CARLSON v. ALEX FINCH, P.A. D/B/A FINCH LAW FIRM and FROMANG & FINCH P.A.) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
MASSEY CONSTRUCTION GROUP, INC. A/A/O ARTHUR CARLSON and CAROL CARLSON v. ALEX FINCH, P.A. D/B/A FINCH LAW FIRM and FROMANG & FINCH P.A., (Fla. Ct. App. 2025).

Opinion

SIXTH DISTRICT COURT OF APPEAL STATE OF FLORIDA _____________________________

Case No. 6D2024-1029 Lower Tribunal No. 20-CA-002296 _____________________________

MASSEY CONSTRUCTION GROUP, INC. a/a/o ARTHUR CARLSON and CAROL CARLSON,

Appellant, v.

ALEX FINCH, P.A. d/b/a FINCH LAW FIRM and FROMANG & FINCH P.A.,

Appellees. _____________________________

Appeal from the Circuit Court for Lee County. Michael T. McHugh, Judge.

November 14, 2025

TRAVER, C.J.

Massey Construction Group, Inc., a/a/o Arthur Carlson and Carol Carlson

(“Massey Construction”) appeals the trial court’s denial of two motions for

attorney’s fees and costs under section 768.79, Florida Statutes (2021). We have

jurisdiction. See Fla. R. App. P. 9.030(b)(1)(A). Because section 768.79 does not

apply to a non-party’s action to enforce an equitable charging lien, we affirm.

While this proceeding involves a dispute between Massey Construction and

its former counsel, it began as an unremarkable first-party insurance claim. Massey Construction hired Alex Finch d/b/a Finch Law Firm and Fromang & Finch, P.A.

(collectively, “Former Counsel”) to sue an insurer for damages. The relationship

between Massey Construction and Former Counsel soured, though, and Former

Counsel withdrew. Former Counsel then filed a notice of imposition of attorney

charging lien against Massey Construction.

When Massey Construction and the insurer settled the case, Former Counsel

moved to enforce their lien. Massey Construction moved to strike this motion or

discharge the lien. It also served Former Counsel with two nearly identical offers of

judgment under section 768.79 and Florida Rule of Civil Procedure 1.442. Former

Counsel did not respond. Following an evidentiary hearing, the trial court granted

Massey Construction’s motion to strike or discharge and denied Former Counsel’s

motion to enforce. We affirmed this decision without opinion. See Finch Law Firm

v. Massey Constr. Grp., 370 So. 3d 658 (Fla. 6th DCA 2023).

Massey Construction then filed two analogous motions against Former

Counsel seeking attorney’s fees. It observed that it had prevailed in the ancillary

charging lien proceeding. Therefore, Massey Construction argued that it was

entitled to recover from Former Counsel the attorney’s fees it had incurred from the

date it made its offers of judgment.

Focusing its analysis on the statute’s and rule’s plain language, the trial court

denied Massey Construction’s motions. It observed that section 768.79 applied to

2 “civil action[s] for damages,” and Former Counsel’s efforts to enforce an equitable

lien did not meet this requirement. It also reasoned that the statute and rule applied

to “parties,” and Former Counsel were not parties to the action between Massey

Construction and the insurer. It finally noted that to garner relief under section

768.79, a “plaintiff” had to obtain a judgment at least 25% percent more than its

offer. The trial court identified Massey Construction as the “plaintiff” in the case

and explained that it neither sought nor obtained a judgment in the ancillary lien

proceeding. Massey Construction challenges this ruling.

We review de novo Massey Construction’s eligibility to recover its fees and

costs under section 768.79 and rule 1.442. See Kuhajda v. Borden Dairy Co. of Ala.,

LLC, 202 So. 3d 391, 393–94 (Fla. 2016) (citing Pratt v. Weiss, 161 So. 3d 1268,

1271 (Fla. 2015)). The Florida Supreme Court directs us to “strictly” construe the

terms of this statute and rule “because they are in derogation of the common law rule

that each party should pay its own fees.” See id. at 394 (collecting cases).

Our interpretation of section 768.79 and rule 1.442 focuses on their plain

language. See Ham v. Portfolio Recovery Assocs., 308 So. 3d 942, 946 (Fla. 2020)

(articulating supremacy-of-the-text principle). Three phrases or terms are at issue.

First, the statute generally applies to “any civil action for damages filed in the courts

of this state.” § 768.79(1). Second, the statute refers to a “party” or “parties” in

multiple instances, including provisions about the required contents for an offer of

3 judgment or demand for judgment, service requirements, and determination of

whether someone made an offer or demand in good faith. See § 768.79(2), (3), (7).

Third, the statute describes the person filing an offer of judgment as a “defendant”

and the person filing a demand for judgment as a “plaintiff.” See § 768.79(1), (6).

The rule likewise refers to a “party” or “parties” in multiple contexts. See Fla. R.

Civ. P. 1.442(c)(2)–(4), (d), (g), (h)(1)–(2), (j). And it mirrors the statute’s

references to a “plaintiff” and a “defendant” as persons or entities who make

proposals for settlement.1 See id. 1.442(a).

Massey Construction argues that the trial court erred when it interpreted the

statute and rule as excluding ancillary attorney charging lien litigation. Relying

almost exclusively on a federal district court decision, it contends that the “case

within a case” nature of charging lien litigation compels a different result. See

Elessar v. Verizon Wireless Pers. Commc’ns, LLP, No. 18-80025-CV, 2020 WL

6156498, at *1 (S.D. Fla. Aug. 26, 2020). Massey Construction argues that Former

Counsel were “parties” to this ancillary proceeding, and that the proceeding’s nature

changed its role from “plaintiff” to “de facto defendant.” See id. at *5 (finding

official party assignment irrelevant in “case within a case” scenarios). Massey

Construction concedes that this case sought to enforce an equitable right, but it

1 Rule 1.442 applies to all proposals for settlement, even if section 768.79 refers to them as offers or demands. See Fla. R. Civ. P. 1.442(a). 4 argues that we should look to the monetary relief Former Counsel sought, and not

the remedy they employed to gain that relief. See id. at *4 (“[Attorney] made an

equitable claim in this case (enforcement of the attorney charging lien), but the

remedy it sought was not a remedy in equity. The only remedy [Attorney] sought

was monetary damages.”). But neither Massey Construction nor Elessar analyzed

section 768.79’s or rule 1.442’s plain language. This critical step forecloses Massey

Construction’s arguments and illustrates why we respectfully disagree with Elessar.

First, Former Counsel did not pursue “a civil action for damages.” See §

768.79(1), Fla. Stat. The operative statute does not apply to actions in equity.

Diamond Aircraft Indus., Inc. v. Horowitch, 107 So. 3d 362, 375 (Fla. 2013).2 A

charging lien is a judicially created, “equitable right to have costs and fees due an

attorney for services in the suit secured to him in the judgment or recovery in that

particular suit.” Sinclair, Louis, Siegel, Heath, Nussbaum & Zavertnik, P.A. v.

Baucom, 428 So. 2d 1383, 1384 (Fla. 1983). Thus, a charging lien proceeding is not

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Seagrave v. State
802 So. 2d 281 (Supreme Court of Florida, 2001)
Cheek v. McGowan Elec. Supply Co.
511 So. 2d 977 (Supreme Court of Florida, 1987)
Exposito v. State
891 So. 2d 525 (Supreme Court of Florida, 2004)
Sinclair, Etc. & Zavertnik, PA v. Baucom
428 So. 2d 1383 (Supreme Court of Florida, 1983)
Hayes v. State
750 So. 2d 1 (Supreme Court of Florida, 1999)
Ancel Pratt, Jr. v. Michael C. Weiss, D.O.
161 So. 3d 1268 (Supreme Court of Florida, 2015)
Susanne L. Kuhajda v. Borden Dairy Company of Alabama, LLC.
202 So. 3d 391 (Supreme Court of Florida, 2016)
Polk County v. Highlands-In-The-Woods, L.L.C.
227 So. 3d 161 (District Court of Appeal of Florida, 2017)
Tower Hill Signature Ins. Co. v. Javellana
238 So. 3d 372 (District Court of Appeal of Florida, 2017)
Diamond Aircraft Industries, Inc. v. Horowitch
107 So. 3d 362 (Supreme Court of Florida, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
MASSEY CONSTRUCTION GROUP, INC. A/A/O ARTHUR CARLSON and CAROL CARLSON v. ALEX FINCH, P.A. D/B/A FINCH LAW FIRM and FROMANG & FINCH P.A., Counsel Stack Legal Research, https://law.counselstack.com/opinion/massey-construction-group-inc-aao-arthur-carlson-and-carol-carlson-v-fladistctapp-2025.