Massachusetts Institute of Technology v. Department of Public Utilities

684 N.E.2d 585, 425 Mass. 856, 1997 Mass. LEXIS 370
CourtMassachusetts Supreme Judicial Court
DecidedSeptember 18, 1997
StatusPublished
Cited by38 cases

This text of 684 N.E.2d 585 (Massachusetts Institute of Technology v. Department of Public Utilities) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Massachusetts Institute of Technology v. Department of Public Utilities, 684 N.E.2d 585, 425 Mass. 856, 1997 Mass. LEXIS 370 (Mass. 1997).

Opinion

Marshall, J.

The Massachusetts Institute of Technology (MIT) appealed to a single justice, pursuant to G. L. c. 25, § 5, from an order of the Department of Public Utilities (department) that authorizes the Cambridge Electric Light Company (company) to impose a monthly customer transition charge (CTC) on MIT, following MIT’s construction of its own cogeneration facility and its departure as a full-service customer from the company.2 The single justice reserved and reported the case to the full court.3

The CTC was authorized by the department to permit [858]*858recovery of the company’s so-called “stranded costs”4 from MIT because of MIT’s size in relation to the company, and its decision to self-generate.5 According to MIT, the CTC authorized by the department in this case is the first such tariff imposed on a cogeneration facility anywhere in the country; the CTC would require MIT to pay an additional monthly charge exceeding $110,000, resulting in an annual charge of $1.3 million to MIT.6

On appeal, MIT argues that in approving the CTC, the department failed to apply its own PURPA regulations, 220 Code Mass. Regs. §§ 8.00-8.07 (1993). MIT next claims that the department failed to make the necessary subsidiary findings in support of its calculation of the stranded costs that formed the basis of the CTC. Third, MIT asserts that the department’s allocation of 75% of the company’s stranded costs allegedly attributable to MIT is arbitrary and capricious. Finally, MIT argues that this court must reverse the department’s order because imposing the CTC on MIT results in the inequitable retroactive application of new decisional law.

We conclude that, contrary to the claim of MIT, the imposition of a customer transition charge, as such, does not violate State PURPA regulations, 220 Code Mass. Regs. §§ 8.00-8.07. However, because the department’s subsidiary findings, see [859]*859G. L. c. 30A, § 11 (8),7 are insufficient for us to give any meaningful review to the calculation of the stranded costs that formed the basis of the CTC, and are similarly insufficient for us to determine whether its decision to permit the company to recover 75% of the costs attributable to MIT is arbitrary, we decline to affirm the department’s order, and remand for further proceedings. See G. L. c. 30A, § 14 (7). We are also unable to conclude on the basis of the department’s inadequate decision whether the imposition of the approved CTC on MIT violates principles prohibiting the inequitable retroactive application of new decisional law.

I

In 1985, MIT began investigating the option of constructing its own electricity-generating, cogeneration facility.8 In an attempt to keep MIT as a customer of the company, in 1992 the company proposed several options to MIT, including a buy-sell agreement, discounted rates, cogeneration deferral payments, and other potential ratemaking concessions.9 After MIT and the company failed to reach any agreement with respect to MIT remaining as an all-requirements customer, MIT began construction of its multimillion dollar, twenty-megawatt cogeneration facility in 1993.10 Operations commenced on September 16, [860]*8601995. The cogeneration facility satisfied all of the criteria for, and was designated, a qualifying cogeneration facility (qualifying facility or QF) under the Public Utility Regulatory Policies Act of 1978 (PURPA), 16 U.S.C. § 824-824k (1994).11 Although MIT’s cogeneration facility can generate enough power to meet MIT’s normal electricity requirements, MIT still must purchase auxiliary services from the company to meet its needs when the facility experiences an outage, and to cover peak periods of usage.12

In May, 1994, prior to the completion of the construction of its facility, MIT filed a petition with the department to establish “just and reasonable” rates for three types of auxiliary services MIT would require from the company after completion of its cogeneration facility: standby service, maintenance service, and supplemental service.13 In response, on March 15, 1995, the company filed for approval its proposed rates for these services; [861]*861it also proposed an additional monthly customer transition charge (CTC) of $7.49 per kilovolt amperes (kVa) to be assessed on all applicable14 customers on a monthly basis. The department consolidated MIT’s request and the company’s proposed CTC and its proposed auxiliary rates into a single case, D.P.U. 94-101/95-36.

The CTC proposed by the company was intended to recover what it claimed were the stranded costs that would result from MIT’s departure as a major customer of the company.15 The company claimed that, absent approval of the CTC, there was a likelihood of substantial cost shifting to residential and other small customers because of the loss of a customer the size of MIT relative to the company’s system. Although the CTC for which the company sought approval was designed to apply to any of its departing customers with demands above a specific level, to date MIT is the only customer to which the CTC is applicable; the remaining applicable customers have not indicated that they would or might depart as customers of the company.

In the proceedings before the department, the company explained the basis on which it had calculated the monthly CTC charge for which it sought authorization. It began by defining a load at-risk class, the class of customers whose departure from [862]*862its system the company claimed would result in a significant loss of revenue to it. (The company determined that this class consisted of seven customers with an average monthly demand level of 2,000 kVa or greater.)16 Next, the company calculated the total net stranded cost that it claimed it would incur if every member of the load at-risk class were to depart as a full-service customer from the company. To calculate this cost, it first calculated the gross annual revenue associated with the class (nearly $21 million).17 From this amount the company subtracted an amount equal to the “avoidable variable expenses” that would not be incurred if all of the load at-risk customers left the system (almost $6 million). The company claimed that this resulted in an annual revenue requirement figure of approximately $15 million.

Next, the company mitigated what it claimed was the “gross amount of stranded costs” for the load at-risk class by the amount of (1) expected revenues from continued services provided to the customers should they depart (approximately $ 4.5 million); (2) potential revenues from reselling the generating capacity available to be marketed as a result of the custom[863]*863ers’ departure (approximately $3 million); and (3) the revenues associated with anticipated load growth on the company’s system (approximately $1.6 million). Subtracting these mitigating factors, the company claimed “net stranded cost” of approximately $6 million.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stoneham Retirement Board v. Contributory Retirement Appeal Board
32 Mass. L. Rptr. 607 (Massachusetts Superior Court, 2015)
Hougie v. Board of Registration in Medicine
32 Mass. L. Rptr. 494 (Massachusetts Superior Court, 2015)
City of Brockton v. Energy Facilities Siting Board (No. 1)
14 N.E.3d 167 (Massachusetts Supreme Judicial Court, 2014)
McGuiness v. Department of Correction
465 Mass. 660 (Massachusetts Supreme Judicial Court, 2013)
NSTAR Electric Co. v. Department of Public Utilities
968 N.E.2d 895 (Massachusetts Supreme Judicial Court, 2012)
Crossen v. Board of Registration of Home Inspectors
29 Mass. L. Rptr. 627 (Massachusetts Superior Court, 2012)
Alliance to Protect Nantucket Sound, Inc. v. Department of Public Utilities
461 Mass. 166 (Massachusetts Supreme Judicial Court, 2011)
Fitchburg Gas & Electric Light Co. v. Department of Public Utilities
460 Mass. 800 (Massachusetts Supreme Judicial Court, 2011)
Bay State Gas Co. v. Department of Public Utilities
947 N.E.2d 1077 (Massachusetts Supreme Judicial Court, 2011)
Southern Union Co. v. Department of Public Utilities
458 Mass. 812 (Massachusetts Supreme Judicial Court, 2011)
City of Springfield v. DEPARTMENT OF TELECOMMUNICATIONS AND CABLE
931 N.E.2d 942 (Massachusetts Supreme Judicial Court, 2010)
Zoning Board of Appeals v. Housing Appeals Committee
923 N.E.2d 114 (Massachusetts Appeals Court, 2010)
Attorney General v. Department of Public Utilities
900 N.E.2d 862 (Massachusetts Supreme Judicial Court, 2009)
City of Cambridge v. Department of Telecommunications & Energy
874 N.E.2d 1110 (Massachusetts Supreme Judicial Court, 2007)
Oyster Creek Preservation, Inc. v. Conservation Commission
449 Mass. 859 (Massachusetts Supreme Judicial Court, 2007)
Ritchie v. Massachusetts Department of Environmental Protection
24 Mass. L. Rptr. 353 (Massachusetts Superior Court, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
684 N.E.2d 585, 425 Mass. 856, 1997 Mass. LEXIS 370, Counsel Stack Legal Research, https://law.counselstack.com/opinion/massachusetts-institute-of-technology-v-department-of-public-utilities-mass-1997.