Mason v. Ashbritt, Inc.

CourtDistrict Court, N.D. California
DecidedJanuary 10, 2020
Docket4:19-cv-01062
StatusUnknown

This text of Mason v. Ashbritt, Inc. (Mason v. Ashbritt, Inc.) is published on Counsel Stack Legal Research, covering District Court, N.D. California primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mason v. Ashbritt, Inc., (N.D. Cal. 2020).

Opinion

1 2 3 4 5 6 UNITED STATES DISTRICT COURT 7 NORTHERN DISTRICT OF CALIFORNIA 8 9 CRAIG MASON, Case No. 19-cv-01062-DMR

10 Plaintiff, ORDER ON DEFENDANTS’ MOTIONS 11 v. TO DISMISS

12 ASHBRITT, INC., et al., Re: Dkt. Nos. 41, 42 13 Defendants.

14 This case relates to property damage caused by the Northern California wildfires of October 15 2017 and subsequent remediation efforts. Defendants AshBritt, Inc. (“AshBritt”) and Tetra Tech, 16 Inc. (“Tetra Tech”) contracted with the United States government to provide disaster relief services 17 following the fires. Plaintiff Craig Mason, a property owner in Sonoma County, filed this putative 18 class action on February 26, 2019, alleging that Defendants caused property damage and engaged 19 in fraudulent conduct during their remediation efforts. [Docket No. 1.] Mason brings claims for 20 relief under the Racketeering Influenced and Corrupt Organizations Act (“RICO”), as well as state 21 law claims for trespass, conversion, trespass to chattels, and violations of California’s Unfair Competition Law (“UCL”), California Business and Professions Code §§ 17200 et seq. [Docket 22 No. 35 (“SAC”).] 23 Defendants now move to dismiss Mason’s RICO claims pursuant to Federal Rules of Civil 24 Procedure 9(b) and 12(b)(6). [Docket Nos. 41 (“Tetra Mot.”), 42 (“AshBritt Mot.”), 53 (“Tetra 25 Reply”), 54 (“AshBritt Reply”).] Plaintiffs timely opposed. [Docket Nos. 47 (“Opp. to Tetra”), 48 26 (“Opp. to AshBritt”).] Having taken oral argument and after considering the parties’ submissions, 27 1 I. BACKGROUND 2 The following facts are alleged in the operative complaint. 3 A. October 2017 Wildfires 4 Mason, a California resident, owned real property in Sonoma County during the class period, 5 which is defined as October 2017 to the present. SAC ¶¶ 8, 11. In October 2017, a series of wildfires 6 caused extensive damage throughout the Northern California counties of Sonoma, Napa, 7 Mendocino, and Lake, among others. Id. ¶ 19. The fires burned over 245,000 acres of land and 8 destroyed over 14,700 homes. Id. On October 10, 2017, President Trump ordered federal aid to assist the recovery efforts in areas affected by the fires. Id. ¶ 20. The Federal Emergency 9 Management Agency (“FEMA”) coordinated those efforts. Id. The Army Corps of Engineers 10 (“ACE”), working under FEMA, “oversaw and coordinated contractors’ clean up and debris 11 removal work as part of the recovery efforts” (the “Project”). Id. ¶ 21. ACE contracted with 12 AshBritt, a Florida corporation, to manage the Project. Id. ¶ 22. 13 B. Scope of the Project 14 Under AshBritt’s contract with ACE, AshBritt was required to perform various services, 15 including: 16 Obtain, analyze and evaluate background soil samples to establish cleanup 17 goals for the project, including asbestos testing. Asbestos testing will not be required if the Contractor is assuming that all ash is toxic and disposing 18 of it at the proper landfill location. If this assumption is not made, tests will be required at a rate of one test per 5000 [cubic yards] of ash. 19 Collect, consolidate, and remove ash and debris for disposal. This material 20 typically requires special handling and disposal as “designated” or “special” 21 waste at a lined landfill.

22 Remove three to six inches of soil for reuse or disposal pending waste characterization. If soil is clean, a landfill may accept it as daily cover. 23 Upon removing all the debris and three to six inches of soil, sample and 24 analyze the remaining soil surface for the same constituents identified as 25 clean-up goals.

26 If results are higher than the threshold for clean-up goals . . . , the Contractor will remove another layer of soil (from 1/2[] inch to 3 inches) for disposal 27 and conduct re-sampling of the soil. The removal and re-sampling shall be 1 If results are less than the threshold clean-up goals, observe and verify the 2 site preparation for final erosion control and certification. SAC ¶ 23. In October 2017, AshBritt subcontracted with Tetra Tech to collect and test soil, among 3 other services, on all properties where AshBritt and its debris removal subcontractors performed 4 work. Id. ¶ 24; Tetra Mot. at 3. As the Project progressed, Defendants were awarded additional 5 contracts to continue performing work, and each additional contract “included the same terms and 6 requirements” as those listed above. SAC ¶ 25. 7 C. Allegations of Excessive Excavation and Removal 8 Mason claims that the ACE contract required Defendants to perform incremental soil 9 removal by removing small layers of soil and re-sampling the soil for additional contamination 10 before removing more. SAC ¶ 26. He alleges that Defendants “routinely removed excessive 11 amounts of soil, up to six feet in depth at a time far more than was necessary to dispose of 12 contaminants without performing sampling to determine whether the soil was contaminated.” Id. ¶ 13 27. He contends that Defendants “instructed or knowingly permitted” subcontractors to perform 14 excessive excavation, and that Tetra Tech on-site supervisors “monitored the workers and approved 15 the removal of excessive amounts of soil without performing sampling to determine whether the 16 soil was contaminated.” Id. ¶ 28. 17 Mason lists several examples of the conduct described above: 18 In one instance, workers for Ashbritt and its subcontractors took topsoil 19 from surrounding properties and used it to loosely fill an excavated hole to create the appearance that the land had not been overexcavated. The 20 property owner was forced to pay for the cost to compact and backfill the land. 21 22 In another instance, a property owner working to rebuild his house in Santa Rosa discovered that workers for a subcontractor contracted and supervised 23 by Ashbritt had overexcavated the land, removed pieces of the foundation, and loosely poured soil to cover it up. As a result, the owner was forced to 24 pay $55,000 for remediation. 25 In another instance, where 30 truckloads of overexcavated soil were 26 removed from a single individual’s land, a supervisor on-site admitted to the property owner that the Army Corps of Engineers had made a mistake 27 by paying the contractors by the ton. 1 provide dates and locations for when and where the conduct occurred. 2 Mason alleges that ACE paid AshBritt between $200 and $300 per ton of removed debris. 3 SAC ¶ 32. Mason claims that AshBritt over-excavated land, “with no consideration for 4 contamination levels or the need to remove material and debris,” in order to increase its profits. Id. 5 According to Mason, Defendants also routinely removed trees that did not meet the criteria for 6 removal under the ACE contract and left contaminated soil on the properties. Id. ¶¶ 32, 36. 7 On August 22, 2018, the Director of the California Governor’s Office of Emergency Services 8 (“OES”) sent a letter to ACE, informing them that OES had “discovered ‘unacceptable’ work performed as part of the cleanup effort, including over-excavation destruction of private property, 9 and false reports of uncontaminated soil.” SAC ¶ 31. This report issued “[a]fter extensive on-site 10 inspections,” and found that ACE’s contractors “caused substantial damage to many survivors’ 11 properties resulting in revictimization of the affected wildfire survivors.” Id. The letter speculated 12 that it was “probable this over-excavation was an intentional effort to capitalize on this tragedy by 13 defrauding the government,” since the subcontractors were paid by the weight of the soil they 14 removed. Id. 15 D. The Alleged Enterprise 16 Both AshBritt and Tetra Tech personnel were “personally involved in overseeing work 17 performed on each property involved in the [Project].” SAC ¶ 33. According to Mason, these 18 personnel “instructed subcontractors to over-excavate properties where proper testing had not been 19 conducted.” Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hemi Group, LLC v. City of New York
559 U.S. 1 (Supreme Court, 2010)
Papasan v. Allain
478 U.S. 265 (Supreme Court, 1986)
Anza v. Ideal Steel Supply Corp.
547 U.S. 451 (Supreme Court, 2006)
Erickson v. Pardus
551 U.S. 89 (Supreme Court, 2007)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Bridge v. Phoenix Bond & Indemnity Co.
553 U.S. 639 (Supreme Court, 2008)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Shroyer v. New Cingular Wireless Services, Inc.
622 F.3d 1035 (Ninth Circuit, 2010)
Sanford v. MemberWorks, Inc.
625 F.3d 550 (Ninth Circuit, 2010)
Rezner v. Bayerische Hypo-Und Vereinsbank AG
630 F.3d 866 (Ninth Circuit, 2010)
Campbell, Tom v. Clinton, William J.
203 F.3d 19 (D.C. Circuit, 2000)
Sybersound Records, Inc. v. UAV Corp.
517 F.3d 1137 (Ninth Circuit, 2008)
Harmoni Int'l Spice, Inc. v. Robert Hume
914 F.3d 648 (Ninth Circuit, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
Mason v. Ashbritt, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/mason-v-ashbritt-inc-cand-2020.