Mason Coal, Inc. v. Tennessee Valley Authority

532 F. Supp. 16, 1981 U.S. Dist. LEXIS 10072
CourtDistrict Court, E.D. Tennessee
DecidedOctober 21, 1981
DocketCiv. No. 3-81-324
StatusPublished
Cited by1 cases

This text of 532 F. Supp. 16 (Mason Coal, Inc. v. Tennessee Valley Authority) is published on Counsel Stack Legal Research, covering District Court, E.D. Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mason Coal, Inc. v. Tennessee Valley Authority, 532 F. Supp. 16, 1981 U.S. Dist. LEXIS 10072 (E.D. Tenn. 1981).

Opinion

MEMORANDUM

ROBERT L. TAYLOR, District Judge.

Mason Coal, Inc. (Mason) brought this action in the United States District Court for the Western District of Virginia, Big Stone Gap Division, against the Tennessee Valley Authority (TVA) seeking to set aside or amend a Hearing Officer’s final administrative decision rendered pursuant to the Disputes provision of a contract between the parties. Chief Judge James C. Turk transferred the action to this Court because the “Eastern District of Tennessee has already become familiar with the complex details of this case through prior litigation . ..,” and because the operative facts arose in this District.

This Court’s familiarity with this litigation began in 1974 when we ordered specific performance of a coal supply contract between Mason and TVA. Tennessee Valley Authority v. Mason Coal, Inc., 384 F.Supp. 1107, aff’d 513 F.2d 632 (6th Cir. 1975). The contract provided that Mason would sell and TVA would buy 75,300 tons of coal of a guaranteed quality to be delivered at the rate of approximately 1,500 tons per week. By Supplement 1 to the contract the parties scheduled deliveries to begin October 29, 1973 and to conclude October 28, 1974. (Vol. V, Ex. 14).

Most of the facts surrounding this protracted litigation are not in dispute. The facts as they had developed through June, 1974 appear in this Court’s prior decision granting specific performance. We noted then that

The inherent nature of the coal industry requires that such long-term supply contracts include various price adjust[18]*18ments for cost increases during the term of the contract. Accordingly, all TVA contracts, including the contract in this case, contain price escalators for such things as changes in mining costs and welfare payments, changes in costs of supplies and materials, changes in applicable state and federal laws or regulations, and costs incurred by the coal company in complying with the Federal Black Lung Benefits Act of 1972.
The contract provides an administrative procedure by which the coal company may recover these increased costs. In the event the parties cannot agree upon the amount of the price increase, a disputes procedure is provided to settle these differences administratively. Although contending that its costs have increased, Mason Coal has filed no such claim with TVA.

384 F.Supp. at 1113. Mason filed a claim for a price increase (a gross inequity claim) on June 20, 1974 pursuant to section 8 of the contract. That section provides in pertinent part that

any gross inequity that may result from unusual economic conditions not contemplated by the parties at the time of execution of the contract may be corrected by mutual agreement. In case of a claim of gross inequity each party shall furnish the other with any pertinent information requested. The existence of a claim of inequity or failure of the parties to reach an agreement with respect thereto shall not relieve contractor from the obligation to continue delivery of coal hereunder. ...

The claim covered the period March 5 through May, 1974 during which Mason had been delivering coal pursuant to this Court’s preliminary injunction issued March 5,1974. (Vol. VII, Ex. 60). In March, 1975 a price adjustment was granted, but in an amount smaller than Mason had requested. (Vol. VII, Ex. 61). Mason reserved its position that no valid contract existed and/or that the contract had expired on October 29, 1974. The parties agreed to hold all administrative remedies in abeyance pending the outcome of Mason’s appeal. (Vol. V, Ex. 21, 22). The United States Court of Appeals for the Sixth Circuit affirmed this Court’s injunction on April 22, 1975 and on July 25, 1975 TVA requested that Mason submit rescheduled deliveries. (Vol. V, Ex. 20). Mason did not and again asserted that the contract had expired by its own terms in October, 1974. It also argued that TVA’s claim was not timely and that any obligation that it might have had was terminated by the parties’ failure to resolve the gross inequity claim. Mason also claimed that performance was impossible because the mine had been closed due to adverse conditions. (Vol. V, Ex. 23). Consequently, on September 12,1975, pursuant to section 5 of the contract’s Terms and Conditions, TVA found Mason in breach of the contract and terminated its right to make further deliveries. TVA also informed Mason that it would procure the undelivered coal for Mason’s account. (Vol. V, Ex. 24).

Mason requested a Contracting Officer’s decision. The Contracting Officer upheld TVA’s termination of Mason’s right to make further deliveries and the settlement of Mason’s gross inequity claim. He found that Mason owed TVA the net amount of $153,127.72 because of the reprocurement of coal to replace that which Mason failed to deliver. (Vol. V, Ex. 19).

Mason appealed the decision of the Contracting Officer to TVA’s General Manager who appointed Professor Richard S. Wirtz of the University of Tennessee College of Law to decide the appeal. Professor Wirtz held a four-day evidentiary hearing on March 21-24, 1977. (Vol. II, III). On June 7, 1978 he filed his decision holding that Mason was entitled to a price increase of $7,191.23 on its gross inequity claim instead of the $3,273.84 which TVA had allowed in Supplement 9 to the contract. (Vol. V, Ex. 14). He determined that Mason had an unexcused deficiency of 24,757 tons of coal and awarded TVA $165,129.19 as its excess cost of reprocuring coal to fill the contract. [19]*19After adjustments, TVA was awarded $158,592.83.1

Our scope of review in this case is governed by the Disputes clause found at section lib of the Terms and Conditions of the Contract:

The decision of the General Manager or his representative or representatives shall be final and conclusive upon the parties except on questions of law or unless determined by a court of competent jurisdiction to have been fraudulent or capricious or arbitrary or so grossly erroneous as necessarily to imply bad faith, or not supported by substantial evidence.. ..

Thus, our review is limited to the questions of law presented and to whether the Hearing Officer’s decision was capricious, arbitrary, grossly erroneous or not supported by substantial evidence. Crass v. Tennessee Valley Authority, 460 F.Supp. 941 (E.D.Tenn.1978), aff’d 627 F.2d 1089 (6th Cir. 1980).

Mason challenges the decision of the Hearing Officer on six grounds, only one of which has been briefed. First, Mason contends that TVA lacked the right and power to make a deficiency assessment and reprocurement more than nine months after expiration of the contract. There is no merit in this contention. That the matter was not referred to the Contracting Officer until after the original time set for the required deliveries is not significant. The matter was nevertheless to be resolved according to the Disputes clause of the contract. Tennessee Valley Authority v. U. S. Carbon Products, Inc., 427 F.Supp. 474 (E.D.Ill.1976). Moreover, all administrative remedies available to both parties were stayed until the appeal was decided. (Vol. V, Ex. 21, 22).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bobbitt v. Milberg, LLP
D. Arizona, 2021

Cite This Page — Counsel Stack

Bluebook (online)
532 F. Supp. 16, 1981 U.S. Dist. LEXIS 10072, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mason-coal-inc-v-tennessee-valley-authority-tned-1981.