Maryland Casualty Co. v. Des Moines City Evangelization Union

184 Iowa 246
CourtSupreme Court of Iowa
DecidedMay 20, 1918
StatusPublished
Cited by7 cases

This text of 184 Iowa 246 (Maryland Casualty Co. v. Des Moines City Evangelization Union) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Maryland Casualty Co. v. Des Moines City Evangelization Union, 184 Iowa 246 (iowa 1918).

Opinion

Weaver, J.

On April 30, 1914, Arthur Errington, a builder, entered into a written contract with the defendant to provide the necessary materials and labor and to construct a certain church building in the city o-f Des Moines, and to complete the same on or before September 1, 1914. The contract price of the building was fixed at $9,880. Payments in installments not to exceed 85% of-the material and labor actually furnished by the contractor were to be made from time to time as the building progressed, — not oftener than once each week, — and the re[248]*248mainder of the contract. p-rice within 30 days after the completion of the building and its acceptance by the owner and the performance of certain conditions by the contractor, as expressed in' the following paragraphs, which we quote from the written agreement:

“If, at any time,, there shall be evidence of any lien or claim for which, if established, the owner of said premises might become liable, and which is chargeable to the contractor, the owner shall have the right to retain out of any payment then due or thereafter to become due, an amount sufficient to completely indemnify the owner against such lien or claim. Should there prove to be any such claim or lien after all payments are made, the contractor shall refund to the owner all moneys that the owner may be compelled to pay in discharging any lien on said premises made obligatory in consequence to the contractor’s default. Prior to the making of the final payment, and as a condition precedent thereto, the contractor agrees to furnish and deliver to the owner receipts in full for all materials and labor furnished and used in said church building. The contract- or further agrees to indemnify against any and all mechanic liens that may be placed against said church building.”

The building was not completed within the contract period; and, in January, 1915, the work being still unfinished, the contractor abandoned it; and, on February 18, 1915, instituted suit to recover an alleged remainder due him of $2,735, and for the enforcement of a mechanics’ lien to that amount upon the property. On March 6, 1915, the defendant appeared in said suit and filed its answer, denying any indebtedness to plaintiff, and alleging, in substance, that he had failed to perform his contract or perform the conditions upon which the contract price was made payable. There was also a plea of payment. In May, 1915, the Maryland Casualty Company gave a written notice to the defendant that it had received from Errington an assignment [249]*249of Ms account and claim against defendant; but said company did not become a party to the suit, and was not substituted as plaintiff, until December 80, 1915, and the issues were not finally settled until December 4, 1916. During the period beginning May 4, 1915, and ending March 23, 1916, the Randall Lumber Company and nine others, who had furnished Errington labor and materials in the construction of the building, and whose claims and accounts so arising had not been paid by Errington, severally intervened in this suit, setting up their said claims, and asserted a lien therefor, which they asked the court to confirm and enforce. With perhaps one or two exceptions, none of these subcontractors had filed any previous itemized account of their several claims, under the provisions of Code Section 3092; but each, in his petition of intervention, set out the alleged facts in general terms, and each asserted a lien for the amount of his claim, and prayed a foreclosure thereof. Upon each of these petitions, the plaintiff joined issue, and pleaded the failure of the intervenors to file verified statements of their several claims, in the manner or within the time provided by the statute.

The issues having been settled, they were referred to W. G. Harvison, Esq., to hear, try, and report thereon, with findings of fact and conclusions of law. Trial was had to the referee, who made and filed his report in due form. For the purposes of this appeal, it is unnecessary to set out the report in full. Briefly stated, the referee found that, as between the plaintiff and its assignor, Errington, on the one hand, and the defendant Evangelistical Union on the other, there was a remainder due the plaintiff to the amount of $1,362.43, for which sum it was entitled to have its claim for a mechanics’ lien established. This relief, was, however, made subject to the claims of the intervenors, to whom it was found Errington was indebted in the aggregate sum- of $1,009.21, for labor and materials furnished [250]*250him. in the construction of the building. In other words, the referee, having found the remainder due to Errington and assigned to plaintiff, further found that this sum, when collected or paid, should be first applied to the payment of the intervening subcontractors’ claims, as adjudicated; and that the remainder, if any, should then be paid over to the plaintiff. The plaintiff’s objections to the report of the referee were overruled, and a decr'ee entered in accordance therewith. Plaintiff appeals.

1. Mechanics' lien: perfecting lien: non-necessity for itemized statements and notice. I. The appellant makes no complaint, in argument, that the amount found due from the defendant to plaintiff is less than it should have been, nor is it contended that, as between Errington and the intervenors, the latter ivere not entitled to r'ecover the several sums reported by the referee in their favor. The proposition relied upon for a reversal or modification of the decree below is that the intervenors failed to observe the provisions of Code Sections 3092 and 3094, in that they did not, within 30 days from the date when the materials were furnished or labor was performed by them for Errington, file with the clerk of the district court verified statements of their several accounts or demands, nor did they, or either of them, intervene in this action or file petitions asserting their alleged right to a lien or liens until long after said period of 30 days had expired, and after the plaintiff had served notice upon defendant of Errington’s assignment to the plaintiff; and that, by reason of this alleged failure of the intervenors, their alleged liens and right to preference in the distribution and application of the moneys earned by Errington and remaining unpaid, cannot noiv be asserted, or given preference against the plaintiff, as Errington’s assignee. This objection, variously stated, presents the only question we have to consider upon the merits of this litigation. So far [251]*251as is material in this case, the statute under consideration is as follows:

“Sec. 3089. Every person who shall do any labor upon, or furnish any materials * * * for, any building, * * * by virtue of any contract with the owner, * * * contractor or subcontractor, * * ' shall have for his labor done, or material * * * furnished, a lien upon such building erection or improvement * * to secure payment for such labor done or material, machinery or fixtures furnished.”
“Sec. 3092.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Schnittjer v. Pippert (Carney)
396 B.R. 22 (N.D. Iowa, 2008)
In Re Carney
396 B.R. 22 (N.D. Iowa, 2008)
Rohlin Const. Co., Inc. v. Lakes, Inc.
252 N.W.2d 403 (Supreme Court of Iowa, 1977)
Cities Service Oil Co. v. Longerbone
6 N.W.2d 325 (Supreme Court of Iowa, 1942)
Hunt Hardware Co. v. Herzoff
196 Iowa 715 (Supreme Court of Iowa, 1923)
Reynolds v. City of Onawa
192 Iowa 398 (Supreme Court of Iowa, 1921)
City National Bank v. Independent School District
190 Iowa 25 (Supreme Court of Iowa, 1920)

Cite This Page — Counsel Stack

Bluebook (online)
184 Iowa 246, Counsel Stack Legal Research, https://law.counselstack.com/opinion/maryland-casualty-co-v-des-moines-city-evangelization-union-iowa-1918.