Maryland Casualty Co. v. Ballard County

289 S.W. 316, 217 Ky. 343, 1926 Ky. LEXIS 92
CourtCourt of Appeals of Kentucky (pre-1976)
DecidedDecember 17, 1926
StatusPublished
Cited by9 cases

This text of 289 S.W. 316 (Maryland Casualty Co. v. Ballard County) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky (pre-1976) primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Maryland Casualty Co. v. Ballard County, 289 S.W. 316, 217 Ky. 343, 1926 Ky. LEXIS 92 (Ky. 1926).

Opinion

Opinion of the Court by

Judge Sampson —

Affirming.

The Maryland Casualty Company in 1916' became surety upon the bond of Gene Seamahorn, a highway contractor, whereby it undertook, in the penal sum of $19,530.56, to indemnify the county of Ballard against loss and damage in consequence of the failure of Scamahorn to perform the terms and conditions of a contract by which he undertook to build and construct a certain highway in that county between the towns of Oscar and Barlow according to plans and specifications made a part of the contract. The contract is on a .regularly printed form then employed by the state road department, and to it is attached a printed notice to road con • tractors, also instructions to bidders, specifications, methods of construction, and several other pages on related subjects, concluding with a clause reading: “The county court clerk will furnish, to prospective bidders, data as to supplies of gravel which will be furnished free Of Cost at'the pit by the county, all other material to.be furnished by the contractor,” all on the regular forms employed by the. state road department. The proposal of Seamahorn, a contractor, is attached to and made a part- of the contract. The contract, which bears, date of July 21, 1916, provides that the contractor shall b.egiii work within twenty days after the signing of the contract, and complete the work in all parts and requirements on o.r before June 1, 1917, with the provision that the fiscal *346 court had the power at its discretion to extend the time for such completion of the work or to stop the work if weather conditions were unsuitable for carrying it on. It also had a subhead under a black letter caption, “Forfeiture for Delay,” which reads:

‘ ‘ The said contractor hereby agrees, in the event of the failure to complete the work within the time agreed that the fiscal court of Ballard county may deduct and retain from any money which may become due under this contract the whole cost of engineering, superintendence and inspection which the county and state may suffer by reason of any failure to complete the work within the time herein specified; provided, however, that said deduction shall not exceed the sum of ten ($10.00) dollars for each and every day the time employed in completing the work exceeds the time herein specified.
“And it is further agreed that in addition to the above that, should said contractor fail to complete the work by the date agreed on herein, to-wit, June 1, 1917, that the county of Ballard will be damaged; but the amount thereof is uncertain and hard to ascertain, and it is therefore agreed by the parties to this contract that upon such failure of the contractor to complete said work by said date, said contractor agrees to pay Ballard county, Kentucky, the sum of ten (10) dollars per day, which amount to be paid as liquidated damages agreed on by the parties hereto as the damage done to Ballard county, Kentucky, by failure of contractor to complete said work as above set out, and which damages are addition to the above clause of ten (10) dollars per day as provided for herein. ’ ’

Under the heading, “General 'Clauses,” in the specification is a paragraph with a subhead “Forfeiture of Contract, ’ ’ which reads:

“If at any time the commissioner of public roads is of the opinion that the work is unnecessarily delayed, and will not be finished within the prescribed time, and shall so certify in writing to the fiscal court, then the said court shall notify the contractor and his bondsmen, in writing, to that effect. And if the said contractor or his bondsmen shall not, *347 within ten (10) days thereafter, take such measures as will, in the judgment of the commissioner of public roads, insure the satisfactory completion of the work, the fiscal court may then notify the said contractor to discontinue all work under this contract for this improvement; and the said contractor shall immediately respect such notice and discontinue all work or any part thereof as the fiscal court may designate, and the said fiscal court shall thereupon have the right at their discretion, to contract with other parties for the delivery of any material, for the completion of any part of the work; and in case the expense so incurred by the fiscal court is less than the sum which is or would have been payable under the contract, if same had been completed by said contractor, then the said contractor shall be entitled to receive the difference; and in case the expense shall exceed the last named sum, then the contractor shall, on demand, pay the amount of such excess to said county.”

Scamahorn failed to complete the work by June 1, 1917, but was permitted by the county and state highway department to continue thereat until the 30th day of October, and the contract at that time was incomplete owing, as it is charged by the county, to want of diligence on the part of Scamahorn in the prosecution of the work. On that date the county gave notice to the contractor, in pursuance to the terms of the contract, to suspend work and to surrender the contract for cancellation, and the county immediately assumed charge of the work and re-let it to another contractor for completion, Scamahorn retiring from the job. In completing the work the county was required to and did expend $5,534.38 more than the original contract provided. In March, 1922, the county filed this action in the Ballard circuit court against Maryland Casualty Company, surety on Scamahorn’s bond, to recover $5,534.38, alleged to be the difference between the contract price of Scamahorn and the price at which the county was able to get the work done, and for $1,535.00 as liquidated damages under the contract, a total of $7,064.38. Later the county filed another suit against Scamahorn and the Maryland Casualty Company to recover $'3,000.00 loaned in June, 1917, by the county of Ballard to Scamahorn and the casualty company at 4% per cent interest but which had not been re *348 paid. In this latter suit the defendants filed answer and counterclaim and succeeded in recovering on their counterclaim a goodly sum, and the county’s petition was dismissed. The casualty company- also filed answer and counterclaim in the original action upon the bond by which it 'clái'med that the work would have been completed by the contractor before June 1, 1917, in accord anee with the terms of the contract, but for the failure of .Ballard county and the fiscal court of Ballard county to keep and perform its part of the contract, in that the county and its fiscal court had failed to locate the road which was to be constructed under the contract and had failed to.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Patel v. Tuttle Properties, LLC
392 S.W.3d 384 (Kentucky Supreme Court, 2013)
Uncle George Orphans Home, Inc. v. Landrum
551 S.W.2d 582 (Court of Appeals of Kentucky, 1977)
Pipelines, Inc. v. Muhlenberg County Water District
465 S.W.2d 927 (Court of Appeals of Kentucky, 1971)
Coca-Cola Bottling Works (Thomas) Inc. v. Hazard Coca-Cola Bottling Works, Inc.
450 S.W.2d 515 (Court of Appeals of Kentucky (pre-1976), 1970)
Western Casualty & Surety Co. v. Meyer
192 S.W.2d 388 (Court of Appeals of Kentucky (pre-1976), 1946)
United States Fidelity & Guaranty Co. v. Mayo Arcade Corp.
70 S.W.2d 531 (Court of Appeals of Kentucky (pre-1976), 1934)
American Surety Co. of N.Y. v. Noe
53 S.W.2d 178 (Court of Appeals of Kentucky (pre-1976), 1932)
Young Men's Christian Association's Assignee v. Indemnity Insurance Co. of North America
51 S.W.2d 463 (Court of Appeals of Kentucky (pre-1976), 1932)

Cite This Page — Counsel Stack

Bluebook (online)
289 S.W. 316, 217 Ky. 343, 1926 Ky. LEXIS 92, Counsel Stack Legal Research, https://law.counselstack.com/opinion/maryland-casualty-co-v-ballard-county-kyctapphigh-1926.