Mary K. Miller v. Hiawassee Allen Family, LLC

CourtCourt of Appeals of Georgia
DecidedOctober 21, 2020
DocketA20A0849
StatusPublished

This text of Mary K. Miller v. Hiawassee Allen Family, LLC (Mary K. Miller v. Hiawassee Allen Family, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mary K. Miller v. Hiawassee Allen Family, LLC, (Ga. Ct. App. 2020).

Opinion

FIRST DIVISION BARNES, P. J., GOBEIL and PIPKIN, JJ.

NOTICE: Motions for reconsideration must be physically received in our clerk’s office within ten days of the date of decision to be deemed timely filed. https://www.gaappeals.us/rules

DEADLINES ARE NO LONGER TOLLED IN THIS COURT. ALL FILINGS MUST BE SUBMITTED WITHIN THE TIMES SET BY OUR COURT RULES.

October 5, 2020

In the Court of Appeals of Georgia A20A0849. MILLER v. HIAWASSEE ALLEN FAMILY, LLC. et al.

PIPKIN, Judge.

The parties to this case, appellant Mary Miller and appellee Jacques Elfersy,

entered into a contract for the purchase of real estate. Elfersy was unable to obtain

financing for the loan and the loan did not close as scheduled. A dispute arose over

who was entitled to the earnest money, and an interpleader action was filed. The trial

court granted summary judgment to Elfersy and held that he was entitled to the return

of the earnest money. Miller then filed this appeal. As more fully set forth below, we

now reverse.

The record shows the following facts relevant to this appeal. On June 17, 2017,

the parties entered into a pre-printed Purchase and Sale Agreement (“Agreement”) pursuant to which Elfersy would purchase property Miller owned in Hiawasee,

Georgia. The Agreement specified a closing date of August 30, 2017, but closing was

dependent upon Elfersy obtaining financing, as was more particularly set out in a pre-

printed “Conventional Loan Contingency” (“financing contingency”), which was

made a part of the Agreement. The financing contingency gave Elfersy 35 days from

the date that the Agreement became binding to obtain a loan under the terms

contained therein. The financing contingency also set out the loan amount – 80

percent of the purchase price – and the term of the loan – 30 years – at a fixed rate of

interest, but the line where the interest rate should have been filled in was left blank.

The Agreement also provided that Elfersy would pay earnest money in the amount of

$10,000, to be held by Hiawassee Allen Family, LLC, d/b/a Mountain Realty

(“Mountain Realty”), and the conditions governing the entitlement and disbursement

of the earnest money were further set out in the Agreement.

Elfersy encountered difficulty securing a loan, and on July 24, 2017, he

executed an amendment to the Agreement purporting to extend the financing

contingency until August 20, 2017; however, it does not appear that Miller ever

agreed to this extension. A separate amendment to change the closing date to

September 26, 2017, was signed by Elfersy on September 5, 2017, and by Miller on

2 September, 11, 2017; however, it is unclear whether this amendment became effective

because Miller made a change to the document and Elfersy did not resign it.

On September 29, 2017, Miller gave Elfersy notice that she was relisting the

property, and on November 13, 2017, Elfersy signed a notice of termination of the

Agreement based on the “failure” of the financing contingency; he also sought return

of the earnest money. Miller countered that Elfersy had breached the Agreement and

that the earnest money should be disbursed to her instead. On August 16, 2018,

Mountain Realty filed a petition for interpleader and paid the earnest money into the

registry of the trial court. Elfersy filed a response and cross-claim to the interpleader

petition, asserting that the Agreement was void and unenforceable due to vagueness.

Miller also answered and cross-claimed, as amended, contending that Elfersy had

breached the Agreement by failing to close by the closing date and by failing to

comply with the terms of the financing contingency.

Elfersy filed a motion for summary judgment, contending among other things

that the Agreement was unenforceable due to the omission of the interest rate in the

financing contingency. Miller filed a response and “alternative” summary judgment

motion, contending that a jury should decide whether Elfersy had waived the alleged

defect in the financing contingency by failing to raise it prior to terminating the

3 Agreement. The trial court subsequently ruled in Elfersy’s favor, finding that Miller

had failed to present evidence supporting a waiver and that, therefore, the Agreement

was void and unenforceable and Elfersy was entitled to return of the earnest money.

The appellate courts of Georgia have consistently held that a contract that

contains a financing contingency but fails to specify an interest rate for the loan is too

vague and indefinite to be enforced. Parks v. Thompson Builders, Inc., 296 Ga. App.

704, 705-706 (1) (675 SE2d 583) (2009); Homler v. Malas, 229 Ga. App. 390, 391

(494 SE2d 18) (1997). However, it is equally well-established that a purchaser may

waive a financing condition that is for his benefit, including defects or omissions that

would otherwise render the contract unenforceable. Brack v. Brownlee, 246 Ga. 818,

820 (273 SE2d 390) (1980).

[A]ny such waiver may be accomplished expressly or implicitly through a party’s conduct. But the law will not infer the waiver of an important contract right unless the waiver is clear and unmistakable. And because waiver is not favored under the law, the evidence relied upon to prove waiver must be so clearly indicative of an intent to relinquish a then known particular right or benefit as to exclude any other reasonable explanation. Indeed, all the attendant facts, taken together, must amount to an intentional relinquishment of a known right, in order that a waiver may exist. The burden of proof lies with the party asserting waiver and, although generally a jury question, when the facts and circumstances

4 essential to the waiver issue are clearly established, waiver becomes a question of law.

(Punctuation omitted; emphasis in original.) Vratsinas Constr. Co. v. Triad Drywall,

LLC, 321 Ga. App. 451, 453-454 (1) (739 SE2d 493) (2013).

Here, we cannot say that the “facts and circumstances essential to the waiver

issue are clearly established.” Id. Miller states in her brief on appeal that Elfersy did

not raise the issue of the missing interest rate “at any time prior to litigation” and

argues that his “protracted silence” constitutes evidence of waiver. See Greenberg

Farrow Architecture, Inc. v. JMLS 1422, LLC, 339 Ga. App. 325, 332 (2) (791 SE2d

635) (2016) (“In particular, a party’s protracted silence, or unreasonable delay in

making protest, can raise a fact issue as to whether [that party] has waived a

contractual right.”) (citation and punctuation omitted). But the interpleader petition,

which was filed by a disinterested party as the holder of the earnest money, recites

that Elfersy had made a demand for the return of the earnest money on the grounds

the Agreement was unenforceable. This clearly indicates that this issue was not just

raised “prior to litigation,” but that it was one of the factors precipitating the filing of

the interpleader petition. On the other hand, while Elfersy states in his brief on appeal

that his attorney raised the issue of the unenforceability of the Agreement in

5 correspondence with Miller’s attorney “[l]ong before the interpleader was filed,” he

does not say when this occurred. More importantly, Elfersy does not provide a

citation to the record where this correspondence may be found and, although it is not

our duty to search the record on the parties’ behalf, we have been unable to locate this

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Koets, Inc. v. Benveniste
312 S.E.2d 846 (Court of Appeals of Georgia, 1983)
Parks v. Thompson Builders, Inc.
675 S.E.2d 583 (Court of Appeals of Georgia, 2009)
Homler v. Malas
494 S.E.2d 18 (Court of Appeals of Georgia, 1997)
Brack v. Brownlee
273 S.E.2d 390 (Supreme Court of Georgia, 1981)
Greenberg Farrow Architecture, Inc. v. Jmls 1422, LLC
791 S.E.2d 635 (Court of Appeals of Georgia, 2016)
Vratsinas Construction Co. v. Triad Drywall, LLC
739 S.E.2d 493 (Court of Appeals of Georgia, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
Mary K. Miller v. Hiawassee Allen Family, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mary-k-miller-v-hiawassee-allen-family-llc-gactapp-2020.