Mary John Family, L.L.C. Versus Stevens Construction & Design, LLC and Adam Stevens

Louisiana Court of Appeal·Decided October 30, 2024·No. 24-CA-132·Unknown

Opinion

MARY JOHN FAMILY, L.L.C. NO. 24-CA-132 VERSUS FIFTH CIRCUIT

STEVENS CONSTRUCTION & DESIGN, LLC COURT OF APPEAL AND ADAM STEVENS STATE OF LOUISIANA

ON APPEAL FROM THE TWENTY-FOURTH JUDICIAL DISTRICT COURT PARISH OF JEFFERSON, STATE OF LOUISIANA NO. 835-204, DIVISION "A"

HONORABLE RAYMOND S. STEIB, JR., JUDGE PRESIDING

October 30, 2024

TIMOTHY S. MARCEL

JUDGE

Panel composed of Judges Fredericka Homberg Wicker, John J. Molaison, Jr., and Timothy S. Marcel

REVERSED IN PART; AFFIRMED IN PART TSM FHW JJM

COUNSEL FOR PLAINTIFF/APPELLANT, MARY JOHN FAMILY, L.L.C.

Albert J. Nicaud Jeffrey M. Siemssen Bret D. Guepet, Jr.

Ramsey T. Marcello

COUNSEL FOR DEFENDANT/APPELLEE, STEVENS CONSTRUCTION & DESIGN, L.L.C. AND ADAM STEVENS Charles K. Chauvin

MARCEL, J.

In this case arising from purportedly defective renovation of a gas service station, plaintiff Mary John Family, L.L.C., (“MJF”) appeals a January 17, 2024 district court judgment granting a motion to confirm arbitration award filed by defendants Stevens Construction & Design, L.L.C. (“SC&D”) and Adam Stevens and dismissing with prejudice the claims brought against them by MJF. For the following reasons, we reverse in part and affirm in part the judgment of the trial court.

BACKGROUND

MJF is the owner of a Chevron gas station located at 3120 Clearview Pkwy., Metairie, Louisiana. On May 4, 2020, MJF contracted with SC&D for the renovation of the gas station. The parties utilized industry standard AIA contract forms for their agreement. Following the commencement of construction, billing disputes arose between the parties. MJF alleges that SC&D double-billed MJF and also failed to pay its subcontractors and suppliers. MJF also alleges SC&D caused project delays, failed to properly supervise the project, failed to obtain the necessary inspections and permits, and negligently allowed work to be done in a manner not in accordance to plans and specifications. MJF claims that it terminated its contract with SC&D “for cause” prior to the completion of the project and later hired a third party to complete the project. On November 18, 2022, MJF filed a petition for damages against SC&D and its owner, Adam Stevens, alleging breach of contract, negligence, and violations of the Louisiana Unfair Trade Practices Act.

In response to the petition, SC&D filed a dilatory exception of prematurity in which it argued that, on February 1, 2023, MJF engaged the initial claim resolution process pursuant to the terms of their construction contract. The contractual dispute resolution procedure provided for a first step of submitting

claims to an Initial Decision Maker before being mediated. In this case, the project architect was selected as the Initial Decision Maker. SC&D argued that because MJF’s claims were still under review by the project architect at the time of the filing of the petition, MJF’s action was premature. MJF opposed the dilatory exception, arguing that it was not bound by the terms of the construction contract requiring an initial review process, because the parties, by their oral statements and actions, had modified the written terms of the agreement.

The matter was set for hearing on April 11, 2023, at which time the trial court orally granted the exception of prematurity and ordered the parties to participate in the Initial Decision Maker’s review process. The project architect issued his Initial Decision Maker report on April 20, 2023. On June 27, 2023, the trial court issued its written judgment granting the exception of prematurity and stayed the litigation on MJF’s petition during the pendency of the Initial Decision Maker review process and any subsequent mediation invoked by the parties as provided for by the construction contract.

Days later, on June 30, 2023, MJF filed a motion to lift the stay of the proceedings. Its motion noted that the Initial Decision Maker report had been issued and SC&D, in response to MJF’s written demand, had elected not to initiate mediation proceedings in accordance with the terms of the construction contract. Following a September 12, 2023 hearing, the trial court issued a judgment on September 26th denying the motion to lift the stay on the proceedings.

Prior to the hearing on the motion to lift the stay, on September 4, 2023, SC&D filed a “motion to confirm arbitration award” wherein it asked the court to confirm the initial decision of the project architect as final. SC&D’s motion averred that MJF had waived its rights to pursue litigation in a court of competent jurisdiction because MJF failed to file for mediation. In particular, SC&D pointed to the provisions of the construction contract that require mediation as a condition

precedent for binding dispute resolution. SC&D attached copies of the construction contract and the initial decision maker’s report in support of its motion.

Following a December 6, 2023 hearing on the matter, the trial court issued a judgment on January 17, 2024 in which it confirmed the initial decision of the architect as final and binding, dismissed with prejudice all claims brought by MJF arising from the contract, and ordered MJF to pay SC&D multiple sums (as stated in the initial decision) totaling $174,077.61.

On appeal, MJF raises multiple assignments of error: 1) the trial court erred in its interpretation of the terms of the construction contract; 2) the trial court erred in finding the appellant waived its right to litigate its claims; 3) the trial court erred in finding the decision of the Initial Decision Maker was an arbitration award; 4) the trial court erred in failing to compel the parties to mediation; 5) the district court erred in confirming an arbitration award despite SC&D’s failure to introduce a valid arbitration agreement; 6) the trial court erred in dismissing all of the claims against SC&D and Adam Stevens. We address these assignments of error en globo in our discussion below, beginning with whether the trial court erred in granting the motion to confirm the arbitration award before proceeding to discussion of whether the trial court properly dismissed MJF’s claims pursuant to waivers contained in the contract.1

1 As part of its arguments relating to the alleged arbitration proceedings, though not as a specific assignment of error, MJF has claimed that the initial decision process violated MJF's due process rights. This claim was not argued before the trial court. In light of the longstanding rules that litigants must raise constitutional attacks in the trial court, not the appellate courts, and that the constitutional challenge must be specifically pleaded and the grounds for the claim particularized, we pretermit any discussion of MJF's due process claims. FMT Shipyard & Repair, LLC v. Normand, 18-292 (La. App. 5 Cir. 5/30/19), 274 So.3d 868, 871.

DISCUSSION

Motion to Confirm Arbitration Under Louisiana Binding Arbitration Law, a provision in any written contract to settle by arbitration a controversy arising out of the contract must be construed as valid, irrevocable, and enforceable. La. R.S. 9:4201. However, before a judgment may be entered on a motion to confirm an arbitration award, the court must first determine whether there is a valid agreement to arbitrate. FIA Card Servs., N.A. v. Weaver, 10-1372 (La. 3/15/11), 62 So.3d 709, 713. It is the burden of the party seeking to enforce a contract to show the contract exists. Id. at 719; La. C.C. art. 1831. Whether a valid agreement to arbitrate exists is decided by application of principals that govern the formation of contracts. NCO Portfolio Mgmt. v. Gougisha, 07-604 (La. App. 5 Cir. 04/29/08), 985 So.2d 731, 735.

Free access — add to your briefcase to read the full text and ask questions with AI

Mary John Family, L.L.C. Versus Stevens Construction & Design, LLC and Adam Stevens, (La. Ct. App. 2024).

Mary John Family, L.L.C. Versus Stevens Construction & Design, LLC and Adam Stevens (Mary John Family, L.L.C. Versus Stevens Construction & Design, LLC and Adam Stevens) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

New Orleans v. Texas & Pacific Railway Co.
171 U.S. 312 (Supreme Court, 1898)
Southern St. Masonry v. JA Jones Const.
507 So. 2d 198 (Supreme Court of Louisiana, 1987)
NCO Portfolio Management Inc. v. Gougisha
985 So. 2d 731 (Louisiana Court of Appeal, 2008)
Atchley v. Atchley
788 So. 2d 690 (Louisiana Court of Appeal, 2001)
FIA Card Services, N.A. v. Weaver
62 So. 3d 709 (Supreme Court of Louisiana, 2011)
Khoobehi Properties, LLC v. Baronne Development No. 2, L.L.C.
216 So. 3d 287 (Louisiana Court of Appeal, 2017)
Aucoin-Hart Jewelers, Inc. v. Metairie Shopping Ctr., L.L.C.
249 So. 3d 1011 (Louisiana Court of Appeal, 2018)