Mary John Family, L.L.C. Versus Stevens Construction & Design, LLC and Adam Stevens

CourtLouisiana Court of Appeal
DecidedOctober 30, 2024
Docket24-CA-132
StatusUnknown

This text of Mary John Family, L.L.C. Versus Stevens Construction & Design, LLC and Adam Stevens (Mary John Family, L.L.C. Versus Stevens Construction & Design, LLC and Adam Stevens) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mary John Family, L.L.C. Versus Stevens Construction & Design, LLC and Adam Stevens, (La. Ct. App. 2024).

Opinion

MARY JOHN FAMILY, L.L.C. NO. 24-CA-132

VERSUS FIFTH CIRCUIT

STEVENS CONSTRUCTION & DESIGN, LLC COURT OF APPEAL AND ADAM STEVENS STATE OF LOUISIANA

ON APPEAL FROM THE TWENTY-FOURTH JUDICIAL DISTRICT COURT PARISH OF JEFFERSON, STATE OF LOUISIANA NO. 835-204, DIVISION "A" HONORABLE RAYMOND S. STEIB, JR., JUDGE PRESIDING

October 30, 2024

TIMOTHY S. MARCEL JUDGE

Panel composed of Judges Fredericka Homberg Wicker, John J. Molaison, Jr., and Timothy S. Marcel

REVERSED IN PART; AFFIRMED IN PART TSM FHW JJM COUNSEL FOR PLAINTIFF/APPELLANT, MARY JOHN FAMILY, L.L.C. Albert J. Nicaud Jeffrey M. Siemssen Bret D. Guepet, Jr. Ramsey T. Marcello

COUNSEL FOR DEFENDANT/APPELLEE, STEVENS CONSTRUCTION & DESIGN, L.L.C. AND ADAM STEVENS Charles K. Chauvin MARCEL, J.

In this case arising from purportedly defective renovation of a gas service

station, plaintiff Mary John Family, L.L.C., (“MJF”) appeals a January 17, 2024

district court judgment granting a motion to confirm arbitration award filed by

defendants Stevens Construction & Design, L.L.C. (“SC&D”) and Adam Stevens

and dismissing with prejudice the claims brought against them by MJF. For the

following reasons, we reverse in part and affirm in part the judgment of the trial

court.

BACKGROUND

MJF is the owner of a Chevron gas station located at 3120 Clearview Pkwy.,

Metairie, Louisiana. On May 4, 2020, MJF contracted with SC&D for the

renovation of the gas station. The parties utilized industry standard AIA contract

forms for their agreement. Following the commencement of construction, billing

disputes arose between the parties. MJF alleges that SC&D double-billed MJF and

also failed to pay its subcontractors and suppliers. MJF also alleges SC&D caused

project delays, failed to properly supervise the project, failed to obtain the

necessary inspections and permits, and negligently allowed work to be done in a

manner not in accordance to plans and specifications. MJF claims that it

terminated its contract with SC&D “for cause” prior to the completion of the

project and later hired a third party to complete the project. On November 18,

2022, MJF filed a petition for damages against SC&D and its owner, Adam

Stevens, alleging breach of contract, negligence, and violations of the Louisiana

Unfair Trade Practices Act.

In response to the petition, SC&D filed a dilatory exception of prematurity

in which it argued that, on February 1, 2023, MJF engaged the initial claim

resolution process pursuant to the terms of their construction contract. The

contractual dispute resolution procedure provided for a first step of submitting

24-CA-132 1 claims to an Initial Decision Maker before being mediated. In this case, the project

architect was selected as the Initial Decision Maker. SC&D argued that because

MJF’s claims were still under review by the project architect at the time of the

filing of the petition, MJF’s action was premature. MJF opposed the dilatory

exception, arguing that it was not bound by the terms of the construction contract

requiring an initial review process, because the parties, by their oral statements and

actions, had modified the written terms of the agreement.

The matter was set for hearing on April 11, 2023, at which time the trial

court orally granted the exception of prematurity and ordered the parties to

participate in the Initial Decision Maker’s review process. The project architect

issued his Initial Decision Maker report on April 20, 2023. On June 27, 2023, the

trial court issued its written judgment granting the exception of prematurity and

stayed the litigation on MJF’s petition during the pendency of the Initial Decision

Maker review process and any subsequent mediation invoked by the parties as

provided for by the construction contract.

Days later, on June 30, 2023, MJF filed a motion to lift the stay of the

proceedings. Its motion noted that the Initial Decision Maker report had been

issued and SC&D, in response to MJF’s written demand, had elected not to initiate

mediation proceedings in accordance with the terms of the construction contract.

Following a September 12, 2023 hearing, the trial court issued a judgment on

September 26th denying the motion to lift the stay on the proceedings.

Prior to the hearing on the motion to lift the stay, on September 4, 2023,

SC&D filed a “motion to confirm arbitration award” wherein it asked the court to

confirm the initial decision of the project architect as final. SC&D’s motion

averred that MJF had waived its rights to pursue litigation in a court of competent

jurisdiction because MJF failed to file for mediation. In particular, SC&D pointed

to the provisions of the construction contract that require mediation as a condition

24-CA-132 2 precedent for binding dispute resolution. SC&D attached copies of the

construction contract and the initial decision maker’s report in support of its

motion.

Following a December 6, 2023 hearing on the matter, the trial court issued a

judgment on January 17, 2024 in which it confirmed the initial decision of the

architect as final and binding, dismissed with prejudice all claims brought by MJF

arising from the contract, and ordered MJF to pay SC&D multiple sums (as stated

in the initial decision) totaling $174,077.61.

On appeal, MJF raises multiple assignments of error: 1) the trial court erred

in its interpretation of the terms of the construction contract; 2) the trial court erred

in finding the appellant waived its right to litigate its claims; 3) the trial court erred

in finding the decision of the Initial Decision Maker was an arbitration award; 4)

the trial court erred in failing to compel the parties to mediation; 5) the district

court erred in confirming an arbitration award despite SC&D’s failure to introduce

a valid arbitration agreement; 6) the trial court erred in dismissing all of the claims

against SC&D and Adam Stevens. We address these assignments of error en globo

in our discussion below, beginning with whether the trial court erred in granting

the motion to confirm the arbitration award before proceeding to discussion of

whether the trial court properly dismissed MJF’s claims pursuant to waivers

contained in the contract.1

1 As part of its arguments relating to the alleged arbitration proceedings, though not as a specific assignment of error, MJF has claimed that the initial decision process violated MJF's due process rights. This claim was not argued before the trial court. In light of the longstanding rules that litigants must raise constitutional attacks in the trial court, not the appellate courts, and that the constitutional challenge must be specifically pleaded and the grounds for the claim particularized, we pretermit any discussion of MJF's due process claims. FMT Shipyard & Repair, LLC v. Normand, 18-292 (La. App. 5 Cir. 5/30/19), 274 So.3d 868, 871.

24-CA-132 3 DISCUSSION

Motion to Confirm Arbitration

Under Louisiana Binding Arbitration Law, a provision in any written

contract to settle by arbitration a controversy arising out of the contract must be

construed as valid, irrevocable, and enforceable. La. R.S. 9:4201. However, before

a judgment may be entered on a motion to confirm an arbitration award, the court

must first determine whether there is a valid agreement to arbitrate. FIA Card

Servs., N.A. v. Weaver, 10-1372 (La. 3/15/11), 62 So.3d 709, 713.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

New Orleans v. Texas & Pacific Railway Co.
171 U.S. 312 (Supreme Court, 1898)
Southern St. Masonry v. JA Jones Const.
507 So. 2d 198 (Supreme Court of Louisiana, 1987)
NCO Portfolio Management Inc. v. Gougisha
985 So. 2d 731 (Louisiana Court of Appeal, 2008)
Atchley v. Atchley
788 So. 2d 690 (Louisiana Court of Appeal, 2001)
FIA Card Services, N.A. v. Weaver
62 So. 3d 709 (Supreme Court of Louisiana, 2011)
Khoobehi Properties, LLC v. Baronne Development No. 2, L.L.C.
216 So. 3d 287 (Louisiana Court of Appeal, 2017)
Aucoin-Hart Jewelers, Inc. v. Metairie Shopping Ctr., L.L.C.
249 So. 3d 1011 (Louisiana Court of Appeal, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
Mary John Family, L.L.C. Versus Stevens Construction & Design, LLC and Adam Stevens, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mary-john-family-llc-versus-stevens-construction-design-llc-and-adam-lactapp-2024.