Marx v. Oliver

92 N.E. 864, 246 Ill. 316
CourtIllinois Supreme Court
DecidedOctober 28, 1910
StatusPublished
Cited by8 cases

This text of 92 N.E. 864 (Marx v. Oliver) is published on Counsel Stack Legal Research, covering Illinois Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Marx v. Oliver, 92 N.E. 864, 246 Ill. 316 (Ill. 1910).

Opinion

Mr. Chiee Justice

Vickers delivered the opinion of the court:

This is an appeal from a decree for the specific performance of a contract for the sale of real estate, rendered by the circuit court of Cook county.

On July 9, 1907, William H. Oliver, being the owner of lot 3 in block 30, in School Section addition to Chicago, entered into a contract with the firm.of Morrice & Barron for the construction of a four-story and basement building thereon, according to certain plans and specifications. The contractors proceeded to erect the building, and on September 19 the building was enclosed, the walls up, the roof on and the floors all laid, and the plumbing was all roughed in and the cement floor in the basement was - being put in, and they were getting ready to put the elevators in place. The building was substantially four-fifths completed on that day. On said day appellant, Oliver, entered into a written contract of sale with Walter Z. Marx, appellee, by which Oliver agreed to complete said building according to the plans and specifications (which were made a part of the contract) within sixty days, and in addition to the requirements of the plans and specifications he also agreed to install in said building an electric freight elevator of approved design and a triplex pump and water tank in the basement of said premises. Appellant agreed to make and deliver a good and sufficient warranty deed conveying said property to appellee free and clear of all liens and encumbrances and to clear said building of all mechanics’ liens. The consideration for the sale was $50,000, $2000 of which was paid in cash as earnest money when the contract was executed and $18,000 more was to be paid upon delivery of the deed, and the balance was divided into two payments of $15,000 each, one to be made in two years and the other in five years, bearing interest at the rate of five and one-half per cent and secured by a trust deed on the property sold. The $2000 cash was paid to appellant at the time the contract was executed.

When the plans and specifications as originally made were submitted to contractors for bids, appellant was unable to secure a bid under $33,000 for the erection of the building, which was more money than he desired to put into the building. He had the architect go over the plans and specifications and make a number of material changes, which were noted in addenda to the plans and specifications. As thus modified appellant was able to contract for the erection of the building for $29,000. The plans and specifications contained a provision by which the “owner reserved the right, after conferring with the architect, to alter or modify the design and to add to or diminish from the contract price for such alterations, the architect being at liberty to make any such alterations in the plans, form, construction, detail or execution described by the drawings and specifications without invalidating or rendering void the contract.” After the contract for the erection of the building had been let, and while the work was in progress, other changes were made in the building by consent of the contractors and the architect in charge of the work. Some 'of these changes had been actually made, and others had been determined upon but had not been made owing to the incomplete condition of the building. At the time the contract which is the basis of the bill filed in this case was entered into, appellee had not made a careful examination of the building. In fact, the only examination that had been made was simply looking at the building on the outside. Appellee entered into the contract relying upon the plans arid specifications as to the character of the building that was to be constructed. These plans and specifications did not show any of the changes except those noted in the addenda at the time the appellee’s architect examined them. After the contract of sale was entered into, appellee employed Mr. Hansen, an architect, to watch after the progress of the building and see that it was finished in accordance with the plans and specifications. Mr. Hansen made his first careful examination of the building on the 26th and 27th of September, after the contract of sale had been executed. He did not at that time point out any objections to the building or find any fault with the manner in which the work was being done. Mr. Hansen was in the building two or three times each week until it was finally completed. Some important changes were made after the execution of the contract, in accordance with Mr. Hansen’s directions.

On November 11, 1907, appellant notified appellee that the building was complete according to the plans and1 specifications and that he desired to close the matter up and make a final settlement according to the terms of the contract. He also informed appellee that he would expect $18,000 in cash on the day that the transaction was closed. In reply to this, Mr. Hansen, the architect, wrote appellant that he could not accept the building as complete under the plans and specifications until he saw the electric elevator tested and also the water pump and steam apparatus, and he requested appellant to put it all into business and notify him and he would call and see it work. In this letter Mr. Hansen said: “If satisfactoiy and with contractor’s usual guarantee to rectify possible defects promptly,- I will accept and issue certificate promptly.” Koester & Zander, real estate agents, who represented appellee in this transaction, also wrote appellant a letter in answer to his of November n, in which they say that appellee’s attorney had advised that it was appellant’s duty to put in such electric connections as were necessary to malee the elevator and pump operate. On November 12 it was agreed between the appellant and Mr. Hansen that the final test of the heating plant would be made on the following Monday. Some attempt was made at a test on the day fixed but the parties disagreed as to the result, Mr. Hansen claiming that the test was unsatisfactory while appellant claimed that it showed the heating plant to be all right.

On the 18th of November the parties met for the purpose of trying to close up the transaction. They failed to agree, and. other meetings were had with like result. On November 21 appellee wrote appellant, stating in detail the particulars in which he claimed the appellant had failed to comply with his contract. In his letter appellee notified appellant to procure from the city authorities certificates of approval of the electric elevator, doors in shaft, tank and motor pump; also a like certificate of approval of the steam boiler, fire escape, plumbing and sewerage and the window cleaning device, and also a certificate of acceptance from the board of underwriters accepting the metal windows. He also pointed out a number of changes in the building which he insisted should be made to make it conform to the plans and specifications referred to in the contract. At a conference held between the parties on the day this letter was delivered to appellant it was agreed that the time for fulfilling the contract should be extended to four o’clock in the afternoon of November 25, and an endorsement to that effect was made on the contract and signed by the parties. On November 23 appellant replied to appellee’s letter of the 21 st, in which he repeated his claim that the building was substantially completed in accordance with the plans and specifications.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Douglas Theater Corp. v. Chicago Title & Trust Co.
641 N.E.2d 584 (Appellate Court of Illinois, 1994)
Yonan v. OAK PARK FED. S. & L. ASS'N
326 N.E.2d 773 (Appellate Court of Illinois, 1975)
Yonan v. Oak Park Federal Savings & Loan Ass'n
326 N.E.2d 773 (Appellate Court of Illinois, 1975)
Fleming v. O'Donohue
138 N.E. 183 (Illinois Supreme Court, 1923)
Sweeney v. Brow
100 A. 593 (Supreme Court of Rhode Island, 1917)
Wald v. Bien
14 Ohio N.P. (n.s.) 145 (Ohio Superior Court, Cincinnati, 1913)
Bateman v. Hopkins
160 N.C. 59 (Supreme Court of North Carolina, 1912)
Bear v. Fletcher
96 N.E. 997 (Illinois Supreme Court, 1911)

Cite This Page — Counsel Stack

Bluebook (online)
92 N.E. 864, 246 Ill. 316, Counsel Stack Legal Research, https://law.counselstack.com/opinion/marx-v-oliver-ill-1910.