Martone Const. v. Bridges at Lake Whitney, No. Cv00-0441010s (Mar. 15, 2002)

2002 Conn. Super. Ct. 2913
CourtConnecticut Superior Court
DecidedMarch 15, 2002
DocketNo. CV00-0441010S
StatusUnpublished

This text of 2002 Conn. Super. Ct. 2913 (Martone Const. v. Bridges at Lake Whitney, No. Cv00-0441010s (Mar. 15, 2002)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Martone Const. v. Bridges at Lake Whitney, No. Cv00-0441010s (Mar. 15, 2002), 2002 Conn. Super. Ct. 2913 (Colo. Ct. App. 2002).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]

MEMORANDUM OF DECISION
STATEMENT OF TILE CASE
The plaintiff was a subcontractor for the defendant, Can-Do Construction Company, which company was the general contractor of the defendant Bridges at Lake Whitney, LLC, the owner and developer of an assisted living project located on Lake Whitney in Hamden.

The plaintiff seeks to recover in a four count complaint for a balance allegedly due for work it performed on work change orders in 1999. The amount in dispute is $41,795.45, all of which the defendants deny owing. CT Page 2914

The first count seeks foreclosure of a mechanic's lien filed against the owner-developer (Bridges) while the fourth count sounds in unjust enrichment as to this defendant. The third count is also directed at Bridges, but is premised on the hiring of the plaintiff by the contractor, in its capacity of agent for Bridges.

The second count is directed against the contractor and is based on the agreement between the plaintiff and Can-Do.

The defendants deny the plaintiff performed the work in question, while Bridges attacks the validity of the mechanic's lien for failure to comply with § 49-35 of the General Statutes.

A portion of the plaintiffs total claim, about $15,000, is alleged to be due from the retainage clause of the contract. There was some sparring over this amount in the cross examination of the plaintiffs principal, but the defense seemed to concede that at least $9000 was due.

After a trial in which only two witnesses were heard, two complete rounds of briefs were permitted by the court.

The court will address first what it perceives as the two basic issues, after which the relative positions of the three parties can be more easily identified. These issues are: (1) Did the plaintiff establish his right to a recovery? and, (2) If it did, is the mechanic's lien valid?

DISCUSSION
I
Frank Martone testified in support of the claim of the plaintiff company. He described the work done and offered two proposals for "change orders" his company submitted, covering this work. These Exhibits, A B, total $25,600. An additional $1180 was billed without a covering change order. Mr. Martone stated this was done "in a hurry" as a courtesy to Can-Do, hence no paper work was prepared. This work involved masonry work around the elevator cylinder.

The defendants presented the testimony of William White, managing member of the defendant Bridges. Addressing the elevator work, he was certain that no work was done on the elevator after March of 1999. The plaintiff claims to have performed his work in July of 1999.

The $3600 charge for brick work on the porte cohere was also addressed CT Page 2915 by White. He stated someone else was hired "to finish it up." It was partially done, and we had to bring people in to complete it" (Tr. p. 93). This "partially done" would appear to be the plaintiffs portion of the project, the change order for $3600.

Turning to the major item in dispute, the $22,000 item for re-pointing and cleaning, the contradictions multiply. The photographs presented by Mr. White appear to refute Mr. Martone's testimony that he cleaned and re-pointed the brick wall as needed. The court's examination of photos show areas that appear "fresher" or cleaner than surrounding areas, indicative of re-pointing. There are large sections which do not appear to have been cleaned at all, with graffiti, staining and paint splatters clearly visible.

In light of these conflicting claims, the court concludes that the plaintiff has not met his burden on this change order, though some work has been done. In view of the admission by Mr. White that 20 percent of the necessary work was done, the plaintiff is entitled to recover the sum of $4400.

On the three items comprising the change orders and invoice, the court finds the plaintiff is entitled to $8000.

II
The court finds no merit to the defendant Can-Do's contention that the plaintiff cannot recover the retainage because of a clause in its subcontract with Martone. That clause, paragraph 2(i) reads:

i. Final payment shall be made after Subcontractors' work has been accepted by Owner, satisfactory proof of payment of all amounts owed by Subcontractor in connection with this Subcontract has been provided, the entire Project is complete, and Contractor has been paid in full for the entire Project.

This imposes conditions on Martone over which he has no control and enables the owner and the contractor to profit if the project fails — even if they were the cause of the failure.

Further, there is no evidence that the owner was unhappy with the plaintiffs work until these disputed change orders surfaced.

The court concludes that the plaintiff is entitled to recover the retainage in the amount of $15,015.45. CT Page 2916

III
Having concluded that the plaintiff is entitled to recover $23,015.45, the court next addresses the validity of the mechanic's lien.

Bridges argues that the lien is invalid because the plaintiff did not give notice to Bridges within 90 days of the last work done as required by § 49-35. The complaint alleges it gave the notice on or about November 24, 1999. According to the defendants no work was done after the execution of the settlement agreement on June 16, 1999. If this were true the notice would have been tardy. If the court accepts the plaintiffs testimony that the last day worked was August 18, 1999, then the notice was still tardy, with 98 days having elapsed between August 18 and November 24. The notice being late, the lien is invalid.

The plaintiff has presented a "fall-back" position, arguing that the notice failure is not fatal because the notice was not required by §49-35 (a). The plaintiff relies on language which states there is an exception to the notice requirement where the subcontractor's written contract "has been assented to in writing by the other party to the original contract."

While Bridges assented to the plaintiffs contract with Can-Do, there is no evidence, and the plaintiff does not argue, that the assent was in writing, The plaintiff has cited Connecticut cases which he claims stand for the proposition that our Supreme Court does not compel a strict construction of the mechanic's lien statutes. This liberality is deemed applicable to claimed inadequacies in certificates. First ConstitutionBank v. Harbor Village Ltd. Partnership, 230 Conn. 807, 816 (1994). The plaintiff cites no case where acts required by the statute may be excused. The court finds the absence of the assent in writing to be fatal.

"The right to fix a lien for materials furnished or services rendered on buildings and land is created by statute, and the acts required by the statute must be done to entitle a party to the benefits of the lien."Lampson Lumber Co. v. Rosadino, 141 Conn. 193, 196 (1952). See Bridges' brief of January 8, 2002, p. 8.

The court concludes that the plaintiffs mechanic's lien is invalid.

IV

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lampson Lumber Co. v. Rosadino
141 Conn. 193 (Supreme Court of Connecticut, 1954)
First Constitution Bank v. Harbor Village Ltd. Partnership
646 A.2d 812 (Supreme Court of Connecticut, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
2002 Conn. Super. Ct. 2913, Counsel Stack Legal Research, https://law.counselstack.com/opinion/martone-const-v-bridges-at-lake-whitney-no-cv00-0441010s-mar-15-connsuperct-2002.