Martin v. Seaboard Air Line Ry.

48 S.E. 616, 70 S.C. 8, 1904 S.C. LEXIS 155
CourtSupreme Court of South Carolina
DecidedSeptember 29, 1904
StatusPublished
Cited by30 cases

This text of 48 S.E. 616 (Martin v. Seaboard Air Line Ry.) is published on Counsel Stack Legal Research, covering Supreme Court of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Martin v. Seaboard Air Line Ry., 48 S.E. 616, 70 S.C. 8, 1904 S.C. LEXIS 155 (S.C. 1904).

Opinion

The opinion of the Court was delivered by

Mr. Justice; Woods.

This is an action to' recover damages for breach of contract. The plaintiff was the owner of a brick mill at Arthur’s Lake, in Lexington County, about one mile from Dixiana, a station on defendant’s railroad. Wishing to move his mill to the railroad in order to save the expense of hauling brick, plaintiff contracted with the de *10 fendant railway company for a spur track at a point on the railroad about three-fourths of a mile from Dixiana. The contract provided as a condition precedent to the construction of the spur that plaintiff should furnish the switch ties, grade the road-bed and pay $60 in cash. On the faith of the contract the plaintiff moved his plant to the new location at considerable expense. The spur was not built, and after waiting some time plaintiff moved his mill back to Arthur’s Lake, and sued for damages. The defendant admitted the $60 had been paid and not returned, but attempted to justify its failure to build the spur track by proving plaintiff had not furnished cross-ties suitable for the work or made an adequate road-bed.

The complaint sets up these items of damage:

Expense of moving brick plant from Arthur’s Lake and back........................... $550 00

Cross-ties, grading and $60 cash, as required by contract....................... 100 00

Loss on kiln of brick for lack of spur track — difference between $350, value on railroad and $97.50, price received................153 50

Rental value of plant while idle for six weeks, based on anticipated profits................ 3,400 00

Total ......................................$3,303 50

1 Undoubtedly the allegations as to several of these items would have been stricken out of the complaint if a motion to that end had been made. But as no such motion was made, the defendant’s first exception, charging reversible error in the admission of testimony concerning them, cannot be sustained. Ragsdale v. Railway Co., 60 S. C., 381, 38 S. E., 609; Dent v. R. R., 61 S. C., 339, 39 S. E., 527. The Code of Procedure provides opportunity for the parties to a suit to have the real issues presented in distinct and clear-cut form by a motion to strike out irrelevant matter. If they choose not to* use this means, complaint that the Circuit Judge failed, in the hearing of the *11 testimony, to disentangle the confusion of relevant and irrelevant matter, will not be heeded. Justice does not in such circumstances require that litigation should be prolonged by new trials. On the other hand, due administration of the law and dispatch of public business are promoted by encouraging the use of the proper means to eliminate all irrelevant matter before the trial begins. It is upon these reasons that the cases above cited rest. It may be important to remark in this connection, however, that while a party cannot complain of the admission of testimony as to irrelevant allegations he has allowed to remain in the complaint, this Court has never held that the Circuit Court has not the right to exclude such testimony. In all the cases on the subject, the refusal to grant a new trial was placed on the ground that the appellant having failed to move to strike out irrelevant allegations, had no right to have the testimony as to such allegations excluded. The proposition that a court is obliged to receive evidence which does not tend to establish any fact from which, under the pleadings, a legal conclusion would result, merely because the immediate litigants are not in a position to complain, cannot for a moment be entertained. The Court is vested with power to exclude such evidence in the interests of other litigants and of the public. Those who have a cause on trial are entitled to time and opportunity to present the evidence and argument which bear upon the real issue, but when either party attempts to go beyond this, it is within the power of the trial Judge, and a duty he owes to others having business in the Court and to the public, either upon the objections of the other party, or of his own motion, to require adherence to the true controversy.

2 The failure of the Circuit Judge to~ instruct the jury not to consider the objectionable items of damage cannot avail the defendant, because no specific request upon the subject was submitted and refused. The first exception is overruled.

At the close of plaintiff’s testimony, the defendant requested the Court to instruct the jury to find a verdict for *12 the plaintiff for $16 only, the cost of hauling to> Dixiana all the brick plaintiff actually shipped. In his second exception, defendant submits this request was erroneously refused. Appellant’s argument is that the sole advantage plaintiff would have derived from the spur track was the saving of the cost of hauling the brick to> the railroad, and hence his damage was limited to the cost of hauling actually paid. Even if the business at the new location had been abandoned for some reason not connected with defendant’s breach of contract, such, for example, as the destruction of the machinery by explosion, this argument still would not be conclusive; for the advantage plaintiff would have derived from the performance of the contract would have been the saving of the cost of hauling to the railroad all the brick manufactured for market at the new location, and not merely of those actually hauled. In that event, the verdict should have been for $50, the cost of hauling the 50,000 brick actually manufactured, and not $16, the cost of hauling those actually shipped. But this was not the case; the plaintiff treated the breach as final and conclusive, and on account of the breach, as he testified, moved his mill away from the location at which he would have been benefited by the building of the spur track. . It is always a question of fact for the jury to decide whether, in view of the circumstances of the particular case, the breach should be regarded final and conclusive, justifying the injured party in treating the contract at an end, or only a temporary delay in performance, or other default not vital to the interests involved. Remelee v. Hell, 76 Am. Dec., 140 (Vt.)

If the plaintiff had continued business at the new location, notwithstanding defendant’s alleged default, and the evidence had led the jury to conclude there was not a final and complete breach, but only'a postponement of performance resulting in no' permanent and continuing- loss, then the recovery should have been for only $16, the cost of hauling the brick actually shipped. But if in that case the evidence had led to the conclusion that the breach was final and com *13 píete, the proper verdict would have been not only for hauling up to the time of the trial, but for the prospective future expense which would have been incurred on that account. 3 Parsons on Contracts, 200; 7 A. & E. Ency. Law, 133.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lundy v. Lititz Mutual Insurance
100 S.E.2d 544 (Supreme Court of South Carolina, 1957)
Shea v. Glens Falls Indemnity Co.
89 S.E.2d 221 (Supreme Court of South Carolina, 1955)
Arkwright Mills v. Clearwater Mfg. Co.
61 S.E.2d 165 (Supreme Court of South Carolina, 1950)
Southern Iron & Equipment Co. v. Bamberg, E. & W. Ry. Co.
149 S.E. 271 (Supreme Court of South Carolina, 1929)
Furst & Thomas v. Davis
147 S.E. 654 (Supreme Court of South Carolina, 1929)
Swift & Co. v. Sullivan
147 S.E. 315 (Supreme Court of South Carolina, 1929)
Calhoun v. Anderson
146 S.E. 245 (Supreme Court of South Carolina, 1929)
W.T. Rawleigh Company v. Wilson
139 S.E. 395 (Supreme Court of South Carolina, 1927)
James v. Western Union Tel. Co.
126 S.E. 653 (Supreme Court of South Carolina, 1925)
National Tire & Rubber Co. v. Hoover
122 S.E. 858 (Supreme Court of South Carolina, 1924)
McFadden v. Anderson Motor Co.
114 S.E. 402 (Supreme Court of South Carolina, 1922)
Thornhill v. Davis, Director General
113 S.E. 370 (Supreme Court of South Carolina, 1922)
Sanders v. Boynton
98 S.E. 854 (Supreme Court of South Carolina, 1919)
Salley v. Cox
77 S.E. 933 (Supreme Court of South Carolina, 1913)
Henry v. Southern Ry.
75 S.E. 1018 (Supreme Court of South Carolina, 1912)
Givens v. North Augusta Electric & Improvement Co.
74 S.E. 1067 (Supreme Court of South Carolina, 1912)
Mills v. Southern Ry.
73 S.E. 772 (Supreme Court of South Carolina, 1912)
Godfrey v. E. P. Burton Lumber Co.
70 S.E. 396 (Supreme Court of South Carolina, 1911)
Building Supply Co. v. Jones
69 S.E. 881 (Supreme Court of South Carolina, 1911)
Anderson v. Western Union Tel. Co.
67 S.E. 232 (Supreme Court of South Carolina, 1910)

Cite This Page — Counsel Stack

Bluebook (online)
48 S.E. 616, 70 S.C. 8, 1904 S.C. LEXIS 155, Counsel Stack Legal Research, https://law.counselstack.com/opinion/martin-v-seaboard-air-line-ry-sc-1904.