Martin v. Northern States Power Co.

72 N.W.2d 867, 245 Minn. 454, 1955 Minn. LEXIS 666
CourtSupreme Court of Minnesota
DecidedNovember 4, 1955
Docket36,601
StatusPublished
Cited by3 cases

This text of 72 N.W.2d 867 (Martin v. Northern States Power Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Martin v. Northern States Power Co., 72 N.W.2d 867, 245 Minn. 454, 1955 Minn. LEXIS 666 (Mich. 1955).

Opinion

*455 Nelson, Justice.

Suit was commenced to recover damages to home and contents caused by fire due to overheating of electrical wire and equipment. Plaintiffs, husband and wife, were the owners of a lot in joint tenancy upon which there was a partially constructed house. It was located at 8356 Wentworth Avenue in the city of Minneapolis. The plaintiff Earl Martin, who was a carpenter, installed an electrical system leading into the basement of the house, and this was done with the help of his brother-in-law, an electrician. They set up a pole consisting of a 4 x 6 timber about 11-12 feet in length approximately 8 to 10 inches from the foundation wall on the west side of the house and about 2y2 feet from the door leading into the basement. They attached a meter connection box to the pole. Thereafter the Northern States Power Company, the defendant herein, installed its meter and lead-in wires from one of its poles in the alley, and when the job was completed, sealed the box as is its custom. The defendant company attached its lead-in wires to two meter sockets fastened on the pole. From these meter sockets wires lead to the inside of plaintiffs’ basement apartment. The wires from the pole in the alley to the top of this temporary pole were strung by the defendant. From there on, all the installation was done by the plaintiff Earl Martin with the assistance of his brother-in-law, who was the electrician. The meter sockets were owned and furnished by the defendant, but it had no part in fastening them to the temporary pole or connecting them with the lead-in wires and the wires running out of the socket into the basement. The larger of the two meters was for heating and power and the other one was for lighting purposes. We will only be concerned here with the smaller of the two meters, which was located below the larger one.

This installation had been working properly for about two years prior to the evening of June 23, 1952, when around 6 p. m. there was a severe electrical windstorm which interrupted the electric current and caused the power to go off in the entire block. During the full period which the plaintiffs had lived in their basement-apartment, no criticism whatever had been directed at plaintiffs’ installation. *456 The entire installation had been done properly, and the defendant offered no testimony in contradiction. The power was in fact cut off from some 2,000 other homes in the area by the storm. The plaintiffs did not personally call the defendant to notify them of the interruption of the current for the reason that they had talked to their neighbors after the storm and were told that they had already notified the company and that the company had notice.

Earl Martin found the pole with the meter installation leaning over at a 45-degree angle away from the house shortly after the storm. A wire was holding it up, and the wires at the top of the pole were obviously slacker than they had been. He put a prop under it so that it would not fall on the children but otherwise did nothing further about it. He said he saw nothing wrong with the meters or the pole, except the leaning of it caused by the storm. Martin’s wife, June, together with a neighbor Phyllis Dyck and a Mr. Ambrose Klotz, a master electrician who repaired the electrical work at the house a week later, corroborated the testimony regarding the leaning of the pole.

The next morning, after Earl Martin had left for his work, the defendant’s crew arrived in the area to restore the electrical current. Almost immediately after they re-fused the transformer, fire broke out in the Martin house. Mrs. Martin noticed the smoke and shortly thereafter went into the basement where she saw red-hot wires by the water heater and the fuse box. There is no dispute but that the fire was started by the overheating of the electrical system in the basement of the Martin house.

Defendant’s employee, Louis Thompson, with his assistant, had parked his truck in the driveway at 8346 Wentworth Avenue. They looked over the various lead-in wires in the block to see if there was any noticeable damage done but did not go to the Martin house to make a close-up inspection. It was all done by standing in the alley near the truck and looking around the area from that point; that constituted their inspection prior to their re-energizing the line, which energized the lead-in wires running into the Martin house.

*457 Shortly thereafter someone called Thompson’s attention to the fact that smoke was coming out of the Martin basement. He then went over and, according to his testimony, placed his ladder against the temporary pole and climbed up it and cut off the lead-in wires. There is some dispute as to whether it was necessary to use a ladder in order to reach the wires because of the leaning of the pole. Thompson and his helper denied that the pole was leaning at a 45-degree angle but admitted that it might have been leaning slightly.

Due to some confusion as to which village fire department had jurisdiction, there was some delay in the arrival of the fire department, so that the fire was not put out as soon as it might have been. Several days after the fire Mr. Ambrose Klotz was engaged to restore the electrical installation. When taking off the meter, he discovered that one of the porcelain terminal blocks was broken, causing a short, so that when the transformer was re-fused, the live wires became crossed with a ground wire leading into the house, thus causing the ground wire to heat up to such an extent that it started the fire resulting in the damage complained of. Plaintiffs’ electrical expert, John H. Williams, stated that, when the temporary pole was blown or pulled away from the house, it caused such a strain on the wires running from the meter socket to the house that it resulted in the breaking of the porcelain terminal block, which in turn caused the crossing of the live and ground wires resulting in the transformer fuse blowing out. He stated that from an electrical standpoint, if the fuse had not blown out at the time it did, the fire would have occurred then and not when the transformer was re-fused the next morning.

This damage admittedly could not be seen from the outside. Since the meter assembly had been sealed by the defendant company, the plaintiffs could not inspect the interior of defendant’s meter assembly without breaking defendant’s seal, thus violating its rules and regulations. The meter was held in the socket by means of friction between the posts and it is held to the socket by a band and a seal affixed by defendant, which seal must not be broken except by an electrician. In addition to the broken porcelain block and the fusing *458 “short” defendant’s distribution superintendent found that the terminal legs for the plug-in lugs were bent, which establishes mechanical force of the breaking pole and the consequent strain through “storm damage” which caused the initial interruption of the-service. That the defendant owned the installations commencing at the housing of the meter socket and extending from that point through the porcelain base and the terminals affixed thereto through the lead-ins to the line to the transformer, and thereon to the source of power is not disputed. All of this material was part of the defendant’s own system and under its exclusive control.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Marshall v. Dawson County Public Power District
578 N.W.2d 428 (Nebraska Supreme Court, 1998)
Bringle v. Lloyd
537 P.2d 1060 (Court of Appeals of Washington, 1975)
Russell v. City of Idaho Falls
305 P.2d 740 (Idaho Supreme Court, 1956)

Cite This Page — Counsel Stack

Bluebook (online)
72 N.W.2d 867, 245 Minn. 454, 1955 Minn. LEXIS 666, Counsel Stack Legal Research, https://law.counselstack.com/opinion/martin-v-northern-states-power-co-minn-1955.