Martin v. Martin

326 S.W.3d 741, 2010 WL 4321628
CourtCourt of Appeals of Texas
DecidedDecember 14, 2010
Docket06-09-00069-CV
StatusPublished
Cited by30 cases

This text of 326 S.W.3d 741 (Martin v. Martin) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Martin v. Martin, 326 S.W.3d 741, 2010 WL 4321628 (Tex. Ct. App. 2010).

Opinion

OPINION

Opinion by

Justice MOSELEY.

I. FACTS AND PROCEDURAL POSTURE

In the intervening years since R.S. Martin, Jr., founded the company which eventually became Martin Resource Management Company (MRMC) in 1951, it experienced substantial growth. In its current situation, MRMC is a privately held company, which is also general partner of Martin Midstream Limited Partners, a publicly-traded company, valued in the hundreds of millions of dollars. It had been successfully jointly managed for some twenty years by Ruben S. Martin, III, and Scott D. Martin, sons of the founders (who owned or controlled all of the voting shares and both of whom were on the five-member board of directors) in an informal, collaborative relationship. 1 Formal shareholder and board meetings were infrequent and they regularly conducted votes through unanimous written consents.

Basically, an internecine power struggle over the control of MRMC arose between the brothers. Although the nature of the brothers’ dispute is complicated, essentially Ruben contended that Scott was trying to take control of the company, while Scott took the position that it was Ruben’s goal to “freeze” Scott out from corporate management. Beginning in 2006, the brothers’ relationship began to deteriorate regarding the general direction of the company and their collegial relationship was finally fractured in 2007 when Ruben decided that MRMC should seek to acquire a California refinery, while Scott opposed the move. This course of events led Scott to attempt to stop the purchase by formalizing MRMC’s corporate decision-making process, which would impose checks on any type of unilateral control of the company by Ruben. Meanwhile, control of the board of directors remained in flux.

In an effort to settle their dispute over corporate control, Ruben and Scott met together and hammered out an agreement, which was monumentalized in a nineteen-paragraph document captioned “Settlement Agreement” drafted by Scott’s attorney and signed on January 29, 2008. 2 *744 Among other things, the agreement required the brothers to negotiate a shareholder agreement in good faith for sixty days (later extended by agreement to ninety days) and that upon completion of “all of the obligations under this Settlement Agreement” (defined as the “Completion Date”), certain other obligations would arise. Although the parties negotiated, they were unable to agree on the terms of a shareholder agreement and none of the remaining terms have been fulfilled.

Although he acknowledged the failure to arrive at an agreement concerning the content of a shareholders’ agreement, Scott characterized Ruben’s failure to perform the other obligations set forth in the agreement as a breach of contract. Scott brought suit to enforce the agreement, seeking specific performance and damages. 3 After a ten-day trial, the trial court submitted the case to the jury on the issues of breach and damages. 4 In doing so, the trial court impliedly found the *745 agreement was an enforceable contract. Holt Atherton Indus., Inc. v. Heine, 885 S.W.2d 80, 88 (Tex.1992); Burnett v. Mo-tyka, 610 S.W.2d 735, 736 (Tex.1980) (per curiam) (conclusions of law that are necessary, but not made, are deemed in support of judgment). The jury found Ruben breached the agreement and awarded Scott $3.2 million in damages and attorney’s fees of $1.5 million. The judgment awarded Scott $3.2 million in accord with the jury verdict, included provisions requiring specific performance by Ruben of certain portions of the settlement agreement, and awarded $13,533.85 in costs to Scott. Ruben filed a motion for judgment notwithstanding the verdict and alternatively a motion for new trial, contending Scott was not entitled to judgment because the settlement agreement was unenforceable as a matter of law. That motion was overruled by operation of law.

In the race to appeal, Scott prevailed. In his sole point of error, Scott claims that he was entitled to recover $16,028.15 in costs, rather than the $13,533.85 awarded in the judgment, alleging that the trial court had acted arbitrarily, picking a number between the cost figure proved up by Scott and the number argued for by Ruben. Ruben filed a cross-appeal. In his reply brief, Ruben streamlined his issues and argument. 5 While his principal brief presented four issues, Ruben’s basic issues, as joined by Scott on cross-appeal, are whether the January 29, 2008, settlement agreement is legally enforceable, and if so, whether Scott was entitled to an award of both money damages and specific performance for breach of the agreement. Because the settlement agreement is not enforceable as a matter of law, we reverse the judgment of the trial court- and render judgment for Ruben.

II. ANALYSIS

Because resolution of Ruben’s issues is determinative of Scott’s point of error regarding the award of court costs, the issues raised by Ruben will be considered first.

In his first issue on cross-appeal, Ruben contends the settlement agreement is an unenforceable agreement to agree. Scott contends that this issue (not having been submitted to the jury) was abandoned and, thus, waived on appeal. We first address the issue of whether the agreement’s enforceability was properly preserved and then discuss the merits of the issue.

A. The Enforceability Issue Was Preserved

The central issue raised in this appeal is whether the parties’ January 29, 2008, settlement agreement is an unenforceable agreement to agree. Scott contends that Ruben abandoned the contract formation issue by not submitting a question to the jury on this issue and in failing to object to the absence of such a question. This contention is based on Ruben’s concession that he assented to the settlement agreement individually, but his assent to its terms was not in a representative ea- *746 parity. On appeal, Ruben places more emphasis on the enforceability of the settlement agreement than at the trial level and relies less on the issue of the capacity under which he was operating at the time he signed the settlement agreement. Because he raised this issue in his motion for directed verdict and in his motion for judgment notwithstanding the verdict, or in the alternative, motion for new trial, Ruben contends that the issue of the contract’s legal enforceability has successfully been preserved. We agree.

Black’s Law Dictionary defines a “contract” as “[a]n agreement between two or more parties creating obligations that are enforceable or otherwise recognizable at law.” Black’s Law Dictionary 365 (9th ed. 2009).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mosler v. Gerace
Supreme Court of The Virgin Islands, 2024
Young v. Ershick
E.D. Texas, 2022
John Magness v. Sheppard Baker
Court of Appeals of Texas, 2019
MKM Engineers, Inc. v. Guzder
476 S.W.3d 770 (Court of Appeals of Texas, 2015)
Robert Marx and Debbie Marx v. Fdp, Lp
Court of Appeals of Texas, 2015
Lincoln Farm, L.L.C. v. Oppliger
2013 OK 85 (Supreme Court of Oklahoma, 2013)
Mailing & Shipping Systems, Inc. v. Neopost USA, Inc.
937 F. Supp. 2d 879 (W.D. Texas, 2013)
Tekelec, Incorporated v. Verint Systems, Incorpora
708 F.3d 658 (Fifth Circuit, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
326 S.W.3d 741, 2010 WL 4321628, Counsel Stack Legal Research, https://law.counselstack.com/opinion/martin-v-martin-texapp-2010.