Martin v. A. L. Scott Lumber Co.

273 P. 411, 127 Kan. 391, 1929 Kan. LEXIS 132
CourtSupreme Court of Kansas
DecidedJanuary 12, 1929
DocketNo. 28,441
StatusPublished
Cited by6 cases

This text of 273 P. 411 (Martin v. A. L. Scott Lumber Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Martin v. A. L. Scott Lumber Co., 273 P. 411, 127 Kan. 391, 1929 Kan. LEXIS 132 (kan 1929).

Opinion

The opinion of the court was delivered by

Burch, J.:

The action was one by the buyer of lumber to recover from the manufacturing seller damages occasioned by defective performance by the seller. The district court stated findings of fact and conclusions of law, on which judgment was rendered for defendant. Plaintiff appeals.

The findings of fact and conclusions of law follow:

“Findings of Fact.
“1. The plaintiff is a resident of Ottawa, Kan., where he has a plant or factory and is engaged in the business of manufacturing and setting up road signs.
“2. The defendant has its principal office in Topeka, Kan., is engaged in the lumber business, and at all times hereinafter mentioned operated a branch lumber yard in Ottawa, Kan., which was in charge of a local manager.
“3. Sometime in December, 1925, the plaintiff ordered from the defendant, through its local manager at Ottawa, a carload of lumber. The lumber in question was to be manufactured into given widths and lengths, and the defendant knew at the time the order was given and received the purpose for which the lumber was to be used, and that exactitude in dimension was essential. In order that the lumber could be used to the best advantage, it was necessary that it should be manufactured with exactness. The order above referred to was for 40,009 pieces, divided into the number and sizes as shown by the first four items on exhibit No. 2. About March 13, 1926, the lumber was delivered at the plaintiff’s warehouse and factory in Ottawa, in bundles, tied with twine or wire, and was corded up by him in his factory. He made some examination of the outside pieces on some of the bundles, but did not discover any inaccuracy in the manner in which the lumber was manufactured. So far as the lumber itself is concerned, outside of its manu[393]*393facture, it is admitted to be first class, and the plaintiff makes no complaint in regard thereto. At the time the lumber was delivered the plaintiff appears to have had a fair stock of material on hand proper for the purpose of manufacturing frames similar to the ones which he would make out of the lumber he purchased from the defendant. Some time between April and the latter part of October, 1926, some 4,500 frames were made up from the lumber purchased from the defendant. Some time in late October, 1926, the plaintiff got in touch with the defendant’s manager at Ottawa, who went to the plaintiff’s factory, where he was advised by the plaintiff that his production in the manufacture of his frames had been considerably slowed down because of the inaccuracies in the manufacture of the lumber delivered to him by the defendant. The defendant’s manager listened to the plaintiff’s complaint, watched a workman assemble a few of the frames, and advised the plaintiff that he would take the matter of the complaint 'up with his superiors, with a view to a possible adjustment. No further interview appears to have been had between the parties. After this conversation the plaintiff continued to use lumber which he had bought from the defendant. No adjustment was ever arrived at between the parties, and this action was begun on August 10, 1927. Before the action was begun probably between 6,500 and 7,000 frames had been cgnstrueted from the lumber supplied by the defendant. In January, 1928, after this action was begun, plaintiff used the balance of the lumber on hand, and made about 1,000 frames.
“4. A mechanic in the employ of the plaintiff, who appears to have been a reasonably efficient workman, put together from 145 to 165 frames a day from the lumber which was manufactured accurately. The same workman put together only about 90 of the frames with the lumber supplied by the defendant, until a simple contrivance costing about $3 was put into use, and after that the same workman put together about 125 per day. The frames thus made were not all of the exact size desired by the plaintiff, but were reasonably adapted for and used in his business, although many of them were of inferior quality because of inaccuracy in the manufacture of the lumber used. The employee was what might be called an all-round workman, worked at various jobs around the plant, and received $25 per week.
“5. The plaintiff did not receive at any time any direction from the defendant or its manager to proceed to use the lumber in question to best advantage, and there was no promise at any time made to the plaintiff on behalf of the defendant that it would pay for or adjust any damage which might be sustained by the plaintiff.
“6. Knowledge of the inaccuracy in the manufacture of the lumber in question came to the attention of the plaintiff's manager and workman at least two months before any complaint was made to the defendant thereof. While the testimony in regard to the matter is somewhat hazy, it is safe to say that the inaccuracy in manufacture was discovered after comparatively little of the lumber had been used. So far as the testimony shows, the defendant was not hindered or impeded in any way in properly preparing his defense to the plaintiff’s claim by reason of the time at which the plaintiff made his complaint of the inaccuracy in the manufacture of the lumber.
[394]*394“Conclusions op Law.
“1. Tbe continued use of the lumber under the facts in this case after discovery of the inaccuracy in manufacture, constitutes an acceptance thereof in the condition in which it was received, and forecloses the right to recover damages sustained because of such inaccuracy in manufacture.
“2. The plaintiff has failed to establish the proper measure of damage, and is not entitled to recover.
“3. If the plaintiff has a right to recover under the facts in this case and his damages have been correctly ascertained, then the plaintiff should recover from the defendant $147.92 and costs.”

It will be observed the court did not find as a fact, from continued use of the lumber after discovery of inaccurate manufacture, and the circumstances, that plaintiff assented to take the lumber as it was in satisfaction of the seller’s obligation to manufacture with exactitude. The first conclusion of law forbade recovery because of application of a rule of law to stated facts, and not because of a finding that the buyer did in fact assent to release the seller from liability. For purpose of review the findings of fact embrace all the facts established by the evidence. (Shuler v. Lashhorn, 67 Kan. 694, 74 Pac. 264; Snodgrass v. Carlson, 117 Kan. 353, 354, 232 Pac. 241.)

The word “acceptance” properly relates to the subject of passing of title.

“The proper meaning of ‘acceptance’ in the law of sales is an assent to become owner of specified goods offered by the seller.” (2 Williston on Sales, § 482.)

In this instance the lumber was ordered, was manufactured, and was delivered to the buyer, who took possession of it, stored it in his warehouse, and paid the price. Of course the buyer accepted the lumber, whether or not it fulfilled the implied warranty of precision in dimensions. Title passed to the buyer, and if, before he commenced to use the lumber, or discovered its defective quality, it had been destroyed by fire, he would have been the loser.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brunner v. Jensen
524 P.2d 1175 (Supreme Court of Kansas, 1974)
Naaf v. Griffitts
439 P.2d 83 (Supreme Court of Kansas, 1968)
Travis v. Glick
91 P.2d 41 (Supreme Court of Kansas, 1939)
Hart v. Wiley
285 P. 548 (Supreme Court of Kansas, 1930)
Carlgren v. Saindon
283 P. 620 (Supreme Court of Kansas, 1930)
Empire Commission Co. v. Carlson
274 P. 1116 (Supreme Court of Kansas, 1929)

Cite This Page — Counsel Stack

Bluebook (online)
273 P. 411, 127 Kan. 391, 1929 Kan. LEXIS 132, Counsel Stack Legal Research, https://law.counselstack.com/opinion/martin-v-a-l-scott-lumber-co-kan-1929.