Martha Simon Versus Mid South Developers, Inc.

Louisiana Court of Appeal·Decided October 4, 2023·No. 22-CA-585·Unknown

Opinion

MARTHA SIMON NO. 22-CA-585 VERSUS FIFTH CIRCUIT MID SOUTH DEVELOPERS, INC. COURT OF APPEAL STATE OF LOUISIANA

ON APPEAL FROM THE TWENTY-FOURTH JUDICIAL DISTRICT COURT PARISH OF JEFFERSON, STATE OF LOUISIANA NO. 814-393, DIVISION "J"

HONORABLE STEPHEN C. GREFER, JUDGE PRESIDING

October 04, 2023

MARC E. JOHNSON

JUDGE

Panel composed of Judges Fredericka Homberg Wicker, Marc E. Johnson, and Robert A. Chaisson

AFFIRMED MEJ FHW RAC

COUNSEL FOR PLAINTIFF/APPELLANT, MARTHA SIMON R. A. Osborn, Jr.

COUNSEL FOR DEFENDANT/APPELLEE, MID SOUTH DEVELOPERS, INC.

George H. Jones

JOHNSON, J.

Plaintiff/Appellant, Martha Simon, appeals the sustaining of the peremptory exception of peremption filed by Defendant/Appellee, Mid South Developers, Inc. (hereinafter referred to as “Mid South”) in the 24th Judicial District Court, Division “J”, that dismissed her petition for damages for breach of contract. For the following reasons, we affirm the trial court’s judgment.

FACTS AND PROCEDURAL HISTORY On February 1, 2021, Ms. Simon filed her “Petition for Damages for Breach of Contract” against Mid South. In her petition, Ms. Simon alleged that she entered into a contract with Mid South on June 30, 2013 for the elevation of her home located at 3160 Sweet Gum Drive in Harvey, Louisiana. She asserted that shortly after Mid South began the work, it abandoned the job and left the dwelling in an unfinished status. Ms. Simon claimed that, throughout the period Mid South worked on her home, she reported several problems to Mid South that were not addressed, which included complaints that the house’s walls were cracking; water remained under the house; the doors would not open and close properly; there was a smell of raw sewage coming from under the house; the flooring inside the house that sank; there was a separation of the cement application; and there were various other defects in the work. She further asserted that an inspection of Mid South’s work revealed a number of problem areas, including the concrete steps, walkways, driveway, handrails, unleveled floors, and other defects under the house that were yet to be identified. Ms. Simon alleged Mid South failed in its obligations to provide all labor, materials and equipment, and to perform the work listed in a good and workmanlike fashion to the dwelling.

In response, Mid South filed its “Answer and Reconventional Demand” on May 25, 2021. It denied Ms. Simon’s allegations, specifically denying it failed in its obligations to Ms. Simon. It alleged in its reconventional demand that Ms.

Simon made sporadic payments pursuant to a promissory note she executed with Mid South on June 30, 2013, leaving a balance of $28,800 owed. In its supplemental answer1, Mid South alternatively alleged that, if Ms. Simon were to be awarded any sum as a result of her petition for damages, the sum should be offset against the alleged amount owed to it.:

In furtherance of prosecuting its reconventional demand, Mid South requested responses to interrogatories and supplemental interrogatories from Ms. Simon. Supplemental Interrogatory No. 2 asked, “On said date were you living in or occupying said property?” Ms. Simon responded, “Subject to Response to Supplemental Interrogatory No. 1, Respondent owned and was living at 3160 Sweet Gum Drive on October 10, 2013.” The next interrogatory posed, “If not, what is the date on which you occupied or lived in said property before or subsequent to October 10, 2013?” to which Ms. Simon responded, “See Response to Supplemental Interrogatory No. 2.”

On June 10, 2022, Mid South filed a peremptory exception of peremption.2 In its exception, Mid South asserted that Ms. Simon admitted to living in the house on October 10, 2013 in her response to the supplemental interrogatories. It argued that, pursuant to La. R.S. 9:2772, Ms. Simon had five years from her October 10, 2013 occupancy of the property to file a timely suit; instead, Ms. Simon filed her action seven years after she occupied the house in question. Consequently, Mid South sought to have Ms. Simon’s action dismissed with prejudice based upon peremption.

The trial on Mid South’s exception of peremption was held on August 9, 2022. During the trial, Mid South argued that, pursuant to La. R.S.

1 Mid South filed a “Supplemental and Amended Answer” on May 23, 2022.

2 Mid South attached copies of the contractor contract, the Jefferson Parish Inspections and Code Enforcement Office’s “Certificate of Completion” for Ms. Simon’s address and permit number RW- 249417-12, and Ms. Simon’s responses to the supplemental interrogatories as exhibits to its pleading. The exhibits were accepted into evidence by the trial court at the trial on the exception.

9:2722(A)(1)(b), Ms. Simon’s failure to file her petition against it for faulty work until seven years after she occupied her home perempted her action. Ms. Simon countered that this case is governed by La. R.S. 9:2722(A)(1)(a). She argued that the work on her home had never been completed, and she never accepted Mid South’s work. At the conclusion of the trial, the trial court sustained Mid South’s exception. The court orally reasoned that completion of the work was not a relevant inquiry. It found the date of occupancy was the relevant inquiry, and Ms. Simon’s action was filed more than five years from the date of her admitted occupancy. The court also reasoned that the exception could not be cured with any amendment to the pleadings. In a written judgment rendered on August 21, 2022, the trial court sustained Mid South’s exception of peremption and dismissed Ms. Simon’s petition with prejudice, at her cost. The trial court later issued an amended judgment on June 1, 2023 to include the proper decretal language, and it retained Mid South’s right to proceed with its reconventional demand. It also found no just reason for delay and rendered the judgment final pursuant to La. C.C.P. art. 1915(B)(1). The instant appeal followed.

ASSIGNMENTS OF ERROR

On appeal, Ms. Simon alleges the trial court erred by: 1) failing to consider her argument that the terms, specifically “acceptance” and “completion”, in La. R.S. 9:2722 are ambiguous; 2) failing to consider that the current language of La. R.S. 9:2722, as interpreted by the trial court, leads to an erroneous and absurd result, when considered with the unopposed evidence; and 3) failing to allow her an opportunity to amend her petition to cure the defects.

LAW AND ANALYSIS

Ambiguity of Terms and Application of La. R.S. 9:27223 Ms. Simon alleges that the trial court erred in sustaining Mid South’s

3 The assignments of error are interrelated and will be jointly discussed.

exception of peremption. She argues the court failed to consider her argument that the terms “acceptance” and “completion” are ambiguous and have multiple meanings in the context of determining whether La. R.S. 9:2772 applies to the facts of this case. Ms. Simon contends that she timely objected to Mid South’s incomplete work, and it cannot be assumed that she accepted the elevation work performed by Mid South. Next, she contends that, while La. R.S. 9:2772 does not contain the word “completion,” completion of the work is an integral part of the determination of the meaning of “acceptance” in this context. Ms. Simon further argues the trial court erred in failing to consider that its interpretation of La. R.S. 9:2772 leads to erroneous and absurd consequences (i.e., that she accepted Mid South’s incomplete work), and it leaves her with no remedy.

Mid South avers that the trial court did not err in refusing to consider Ms.

Simon’s argument as to whether La. R.S. 9:2772’s terms of “acceptance” or “completion” have any legal bearing on peremption. It maintains that La. R.S. 9:2772(1)(b) is the applicable provision to consider for this matter. Because Ms. Simon admitted occupying the property on October 10, 2013, Mid South asserts that her lawsuit is perempted according to Subsection (b).

Free access — add to your briefcase to read the full text and ask questions with AI

Martha Simon Versus Mid South Developers, Inc., (La. Ct. App. 2023).

Martha Simon Versus Mid South Developers, Inc. (Martha Simon Versus Mid South Developers, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Rando v. Anco Insulations Inc.
16 So. 3d 1065 (Supreme Court of Louisiana, 2009)
Ebinger v. Venus Construction Corp.
65 So. 3d 1279 (Supreme Court of Louisiana, 2011)
Harding v. Raising Canes USA L.L.C.
55 So. 3d 837 (Louisiana Court of Appeal, 2010)
Tracy Ray Lomont v. Michelle Myer-Bennett and Xyz Insurance Company
172 So. 3d 620 (Supreme Court of Louisiana, 2015)