MARTHA SIMON NO. 22-CA-585
VERSUS FIFTH CIRCUIT
MID SOUTH DEVELOPERS, INC. COURT OF APPEAL
STATE OF LOUISIANA
ON APPEAL FROM THE TWENTY-FOURTH JUDICIAL DISTRICT COURT PARISH OF JEFFERSON, STATE OF LOUISIANA NO. 814-393, DIVISION "J" HONORABLE STEPHEN C. GREFER, JUDGE PRESIDING
October 04, 2023
MARC E. JOHNSON JUDGE
Panel composed of Judges Fredericka Homberg Wicker, Marc E. Johnson, and Robert A. Chaisson
AFFIRMED MEJ FHW RAC COUNSEL FOR PLAINTIFF/APPELLANT, MARTHA SIMON R. A. Osborn, Jr.
COUNSEL FOR DEFENDANT/APPELLEE, MID SOUTH DEVELOPERS, INC. George H. Jones JOHNSON, J.
Plaintiff/Appellant, Martha Simon, appeals the sustaining of the peremptory
exception of peremption filed by Defendant/Appellee, Mid South Developers, Inc.
(hereinafter referred to as “Mid South”) in the 24th Judicial District Court, Division
“J”, that dismissed her petition for damages for breach of contract. For the
following reasons, we affirm the trial court’s judgment.
FACTS AND PROCEDURAL HISTORY
On February 1, 2021, Ms. Simon filed her “Petition for Damages for Breach
of Contract” against Mid South. In her petition, Ms. Simon alleged that she
entered into a contract with Mid South on June 30, 2013 for the elevation of her
home located at 3160 Sweet Gum Drive in Harvey, Louisiana. She asserted that
shortly after Mid South began the work, it abandoned the job and left the dwelling
in an unfinished status. Ms. Simon claimed that, throughout the period Mid South
worked on her home, she reported several problems to Mid South that were not
addressed, which included complaints that the house’s walls were cracking; water
remained under the house; the doors would not open and close properly; there was
a smell of raw sewage coming from under the house; the flooring inside the house
that sank; there was a separation of the cement application; and there were various
other defects in the work. She further asserted that an inspection of Mid South’s
work revealed a number of problem areas, including the concrete steps, walkways,
driveway, handrails, unleveled floors, and other defects under the house that were
yet to be identified. Ms. Simon alleged Mid South failed in its obligations to
provide all labor, materials and equipment, and to perform the work listed in a
good and workmanlike fashion to the dwelling.
In response, Mid South filed its “Answer and Reconventional Demand” on
May 25, 2021. It denied Ms. Simon’s allegations, specifically denying it failed in
its obligations to Ms. Simon. It alleged in its reconventional demand that Ms.
22-CA-585 1 Simon made sporadic payments pursuant to a promissory note she executed with
Mid South on June 30, 2013, leaving a balance of $28,800 owed. In its
supplemental answer1, Mid South alternatively alleged that, if Ms. Simon were to
be awarded any sum as a result of her petition for damages, the sum should be
offset against the alleged amount owed to it.:
In furtherance of prosecuting its reconventional demand, Mid South
requested responses to interrogatories and supplemental interrogatories from Ms.
Simon. Supplemental Interrogatory No. 2 asked, “On said date were you living in
or occupying said property?” Ms. Simon responded, “Subject to Response to
Supplemental Interrogatory No. 1, Respondent owned and was living at 3160
Sweet Gum Drive on October 10, 2013.” The next interrogatory posed, “If not,
what is the date on which you occupied or lived in said property before or
subsequent to October 10, 2013?” to which Ms. Simon responded, “See Response
to Supplemental Interrogatory No. 2.”
On June 10, 2022, Mid South filed a peremptory exception of peremption.2
In its exception, Mid South asserted that Ms. Simon admitted to living in the house
on October 10, 2013 in her response to the supplemental interrogatories. It argued
that, pursuant to La. R.S. 9:2772, Ms. Simon had five years from her October 10,
2013 occupancy of the property to file a timely suit; instead, Ms. Simon filed her
action seven years after she occupied the house in question. Consequently, Mid
South sought to have Ms. Simon’s action dismissed with prejudice based upon
peremption.
The trial on Mid South’s exception of peremption was held on August 9,
2022. During the trial, Mid South argued that, pursuant to La. R.S.
1 Mid South filed a “Supplemental and Amended Answer” on May 23, 2022. 2 Mid South attached copies of the contractor contract, the Jefferson Parish Inspections and Code Enforcement Office’s “Certificate of Completion” for Ms. Simon’s address and permit number RW- 249417-12, and Ms. Simon’s responses to the supplemental interrogatories as exhibits to its pleading. The exhibits were accepted into evidence by the trial court at the trial on the exception.
22-CA-585 2 9:2722(A)(1)(b), Ms. Simon’s failure to file her petition against it for faulty work
until seven years after she occupied her home perempted her action. Ms. Simon
countered that this case is governed by La. R.S. 9:2722(A)(1)(a). She argued that
the work on her home had never been completed, and she never accepted Mid
South’s work. At the conclusion of the trial, the trial court sustained Mid South’s
exception. The court orally reasoned that completion of the work was not a
relevant inquiry. It found the date of occupancy was the relevant inquiry, and Ms.
Simon’s action was filed more than five years from the date of her admitted
occupancy. The court also reasoned that the exception could not be cured with any
amendment to the pleadings. In a written judgment rendered on August 21, 2022,
the trial court sustained Mid South’s exception of peremption and dismissed Ms.
Simon’s petition with prejudice, at her cost. The trial court later issued an
amended judgment on June 1, 2023 to include the proper decretal language, and it
retained Mid South’s right to proceed with its reconventional demand. It also
found no just reason for delay and rendered the judgment final pursuant to La.
C.C.P. art. 1915(B)(1). The instant appeal followed.
ASSIGNMENTS OF ERROR
On appeal, Ms. Simon alleges the trial court erred by: 1) failing to consider
her argument that the terms, specifically “acceptance” and “completion”, in La.
R.S. 9:2722 are ambiguous; 2) failing to consider that the current language of La.
R.S. 9:2722, as interpreted by the trial court, leads to an erroneous and absurd
result, when considered with the unopposed evidence; and 3) failing to allow her
an opportunity to amend her petition to cure the defects.
LAW AND ANALYSIS
Ambiguity of Terms and Application of La. R.S. 9:27223
Ms. Simon alleges that the trial court erred in sustaining Mid South’s
3 The assignments of error are interrelated and will be jointly discussed.
22-CA-585 3 exception of peremption. She argues the court failed to consider her argument that
the terms “acceptance” and “completion” are ambiguous and have multiple
meanings in the context of determining whether La. R.S. 9:2772 applies to the
facts of this case. Ms. Simon contends that she timely objected to Mid South’s
incomplete work, and it cannot be assumed that she accepted the elevation work
performed by Mid South. Next, she contends that, while La. R.S. 9:2772 does not
contain the word “completion,” completion of the work is an integral part of the
determination of the meaning of “acceptance” in this context. Ms. Simon further
Free access — add to your briefcase to read the full text and ask questions with AI
MARTHA SIMON NO. 22-CA-585
VERSUS FIFTH CIRCUIT
MID SOUTH DEVELOPERS, INC. COURT OF APPEAL
STATE OF LOUISIANA
ON APPEAL FROM THE TWENTY-FOURTH JUDICIAL DISTRICT COURT PARISH OF JEFFERSON, STATE OF LOUISIANA NO. 814-393, DIVISION "J" HONORABLE STEPHEN C. GREFER, JUDGE PRESIDING
October 04, 2023
MARC E. JOHNSON JUDGE
Panel composed of Judges Fredericka Homberg Wicker, Marc E. Johnson, and Robert A. Chaisson
AFFIRMED MEJ FHW RAC COUNSEL FOR PLAINTIFF/APPELLANT, MARTHA SIMON R. A. Osborn, Jr.
COUNSEL FOR DEFENDANT/APPELLEE, MID SOUTH DEVELOPERS, INC. George H. Jones JOHNSON, J.
Plaintiff/Appellant, Martha Simon, appeals the sustaining of the peremptory
exception of peremption filed by Defendant/Appellee, Mid South Developers, Inc.
(hereinafter referred to as “Mid South”) in the 24th Judicial District Court, Division
“J”, that dismissed her petition for damages for breach of contract. For the
following reasons, we affirm the trial court’s judgment.
FACTS AND PROCEDURAL HISTORY
On February 1, 2021, Ms. Simon filed her “Petition for Damages for Breach
of Contract” against Mid South. In her petition, Ms. Simon alleged that she
entered into a contract with Mid South on June 30, 2013 for the elevation of her
home located at 3160 Sweet Gum Drive in Harvey, Louisiana. She asserted that
shortly after Mid South began the work, it abandoned the job and left the dwelling
in an unfinished status. Ms. Simon claimed that, throughout the period Mid South
worked on her home, she reported several problems to Mid South that were not
addressed, which included complaints that the house’s walls were cracking; water
remained under the house; the doors would not open and close properly; there was
a smell of raw sewage coming from under the house; the flooring inside the house
that sank; there was a separation of the cement application; and there were various
other defects in the work. She further asserted that an inspection of Mid South’s
work revealed a number of problem areas, including the concrete steps, walkways,
driveway, handrails, unleveled floors, and other defects under the house that were
yet to be identified. Ms. Simon alleged Mid South failed in its obligations to
provide all labor, materials and equipment, and to perform the work listed in a
good and workmanlike fashion to the dwelling.
In response, Mid South filed its “Answer and Reconventional Demand” on
May 25, 2021. It denied Ms. Simon’s allegations, specifically denying it failed in
its obligations to Ms. Simon. It alleged in its reconventional demand that Ms.
22-CA-585 1 Simon made sporadic payments pursuant to a promissory note she executed with
Mid South on June 30, 2013, leaving a balance of $28,800 owed. In its
supplemental answer1, Mid South alternatively alleged that, if Ms. Simon were to
be awarded any sum as a result of her petition for damages, the sum should be
offset against the alleged amount owed to it.:
In furtherance of prosecuting its reconventional demand, Mid South
requested responses to interrogatories and supplemental interrogatories from Ms.
Simon. Supplemental Interrogatory No. 2 asked, “On said date were you living in
or occupying said property?” Ms. Simon responded, “Subject to Response to
Supplemental Interrogatory No. 1, Respondent owned and was living at 3160
Sweet Gum Drive on October 10, 2013.” The next interrogatory posed, “If not,
what is the date on which you occupied or lived in said property before or
subsequent to October 10, 2013?” to which Ms. Simon responded, “See Response
to Supplemental Interrogatory No. 2.”
On June 10, 2022, Mid South filed a peremptory exception of peremption.2
In its exception, Mid South asserted that Ms. Simon admitted to living in the house
on October 10, 2013 in her response to the supplemental interrogatories. It argued
that, pursuant to La. R.S. 9:2772, Ms. Simon had five years from her October 10,
2013 occupancy of the property to file a timely suit; instead, Ms. Simon filed her
action seven years after she occupied the house in question. Consequently, Mid
South sought to have Ms. Simon’s action dismissed with prejudice based upon
peremption.
The trial on Mid South’s exception of peremption was held on August 9,
2022. During the trial, Mid South argued that, pursuant to La. R.S.
1 Mid South filed a “Supplemental and Amended Answer” on May 23, 2022. 2 Mid South attached copies of the contractor contract, the Jefferson Parish Inspections and Code Enforcement Office’s “Certificate of Completion” for Ms. Simon’s address and permit number RW- 249417-12, and Ms. Simon’s responses to the supplemental interrogatories as exhibits to its pleading. The exhibits were accepted into evidence by the trial court at the trial on the exception.
22-CA-585 2 9:2722(A)(1)(b), Ms. Simon’s failure to file her petition against it for faulty work
until seven years after she occupied her home perempted her action. Ms. Simon
countered that this case is governed by La. R.S. 9:2722(A)(1)(a). She argued that
the work on her home had never been completed, and she never accepted Mid
South’s work. At the conclusion of the trial, the trial court sustained Mid South’s
exception. The court orally reasoned that completion of the work was not a
relevant inquiry. It found the date of occupancy was the relevant inquiry, and Ms.
Simon’s action was filed more than five years from the date of her admitted
occupancy. The court also reasoned that the exception could not be cured with any
amendment to the pleadings. In a written judgment rendered on August 21, 2022,
the trial court sustained Mid South’s exception of peremption and dismissed Ms.
Simon’s petition with prejudice, at her cost. The trial court later issued an
amended judgment on June 1, 2023 to include the proper decretal language, and it
retained Mid South’s right to proceed with its reconventional demand. It also
found no just reason for delay and rendered the judgment final pursuant to La.
C.C.P. art. 1915(B)(1). The instant appeal followed.
ASSIGNMENTS OF ERROR
On appeal, Ms. Simon alleges the trial court erred by: 1) failing to consider
her argument that the terms, specifically “acceptance” and “completion”, in La.
R.S. 9:2722 are ambiguous; 2) failing to consider that the current language of La.
R.S. 9:2722, as interpreted by the trial court, leads to an erroneous and absurd
result, when considered with the unopposed evidence; and 3) failing to allow her
an opportunity to amend her petition to cure the defects.
LAW AND ANALYSIS
Ambiguity of Terms and Application of La. R.S. 9:27223
Ms. Simon alleges that the trial court erred in sustaining Mid South’s
3 The assignments of error are interrelated and will be jointly discussed.
22-CA-585 3 exception of peremption. She argues the court failed to consider her argument that
the terms “acceptance” and “completion” are ambiguous and have multiple
meanings in the context of determining whether La. R.S. 9:2772 applies to the
facts of this case. Ms. Simon contends that she timely objected to Mid South’s
incomplete work, and it cannot be assumed that she accepted the elevation work
performed by Mid South. Next, she contends that, while La. R.S. 9:2772 does not
contain the word “completion,” completion of the work is an integral part of the
determination of the meaning of “acceptance” in this context. Ms. Simon further
argues the trial court erred in failing to consider that its interpretation of La. R.S.
9:2772 leads to erroneous and absurd consequences (i.e., that she accepted Mid
South’s incomplete work), and it leaves her with no remedy.
Mid South avers that the trial court did not err in refusing to consider Ms.
Simon’s argument as to whether La. R.S. 9:2772’s terms of “acceptance” or
“completion” have any legal bearing on peremption. It maintains that La. R.S.
9:2772(1)(b) is the applicable provision to consider for this matter. Because Ms.
Simon admitted occupying the property on October 10, 2013, Mid South asserts
that her lawsuit is perempted according to Subsection (b).
La. C.C. art. 3458 states that “[p]eremption is a period of time fixed by law
for the existence of a right. Unless timely exercised, the right is extinguished upon
the expiration of the peremptive period.” Harding v. Raising Canes USA L.L.C.,
10-320 (La. App. 5 Cir, 11/23/10), 55 So.3d 837, 839, writ denied, 11-766 (La.
5/27/11), 63 So.3d 999. Peremption may be pleaded or supplied by the court’s
own motion. La. C.C. art. 3460. Peremption may not be renounced, interrupted,
or suspended. La. C.C. art. 3461.
“Peremption has been likened to prescription; namely it is prescription that
is not subject to interruption or suspension.” Lomont v. Bennett, 14-2483 (La.
6/30/15), 172 So.3d 620, 626-27, citing Rando v. Anco Insulations, Inc., 08-1163
22-CA-585 4 (La. 5/22/09), 16 So.3d 1065, 1082. However, peremption differs from
prescription in two respects: (1) the expiration of the peremptive time period
destroys the cause of action itself; and (2) nothing may interfere with the running
of a peremptive time period. Ebinger v. Venus Const. Corp., 10-2516 (La. 7/1/11),
65 So.3d 1279, 1286.
Peremptive statutes are to be strictly construed against peremption and in
favor of maintaining the claim. Lamar Contractors, LLC v. SRF Grp. Consulting,
LLC, 22-213 (La. App. 5 Cir. 2/1/23), 358 So.3d 907, 909, writ denied sub nom.,
Lamar Contractors, L.L.C. v. SRF Consulting, L.L.C., 23-308 (La. 5/23/23), 360
So.3d 1260. Of the possible constructions of a peremptive statute, the one that
maintains the claim, rather than the one that bars prosecution of the claim, should
be adopted. Id.
The rules governing the burden of proof as to prescription also apply to
peremption. Lomont, 172 So.3d at 627. Ordinarily, the exceptor bears the burden
of proof at the trial of the peremptory exception. Id. But, if prescription is evident
on the face of the pleadings, the burden shifts to the plaintiff to show the action has
not prescribed. Id. In the absence of evidence, an exception of peremption must
be decided upon the facts alleged in the petition with all of the allegations accepted
as true. Id. When evidence is introduced, the court is not bound to accept the
plaintiff’s allegations as true. Id.
A judgment sustaining an exception of peremption is generally reviewed de
novo because the exception raises a legal question and involves the interpretation
of a statute. Lamar Contractors, LLC, supra. If evidence is introduced at the
hearing on an exception of peremption, the trial court’s findings of fact are
evaluated under the manifest error standard of review. Id. If the trial court’s
findings are reasonable in light of the record viewed in its entirety, an appellate
court may not reverse, even if it is convinced that it would have weighed the
22-CA-585 5 evidence differently. Id.
The statute considered by the trial court in this matter was La. R.S. 9:2772,
entitled, “Peremptive period for actions involving deficiencies in surveying,
design, supervision, or construction of immovable or improvements thereon.” The
Louisiana Legislature enacted La. R.S. 9:2772 in 1964 to protect building
contractors from liability for past construction projects that could extend for an
indefinite period of time. Celebration Church, Inc. v. Church Mut. Ins. Co., 16-
245 (La. App. 5 Cir. 12/14/16), 1059, 1062. La. R.S. 9:2772 provides, in pertinent
part:
A. Except as otherwise provided in this Subsection, no action, whether ex contractu, ex delicto, or otherwise, including but not limited to an action for failure to warn, to recover on a contract, or to recover damages, or otherwise arising out of an engagement of planning, construction, design, or building immovable or movable property which may include, without limitation, consultation, planning, designs, drawings, specification, investigation, evaluation, measuring, or administration related to any building, construction, demolition, or work, shall be brought against any person performing or furnishing land surveying services, as such term is defined in R.S. 37:682, including but not limited to those services preparatory to construction, or against any person performing or furnishing the design, planning, supervision, inspection, or observation of construction or the construction of immovable, or improvement to immovable property, including but not limited to a residential building contractor as defined in R.S. 3:2150.1:
(1)(a) More than five years after the date of registry in the mortgage office of acceptance of the work by owner.
(b) If no such acceptance is recorded within six months from the date the owner has occupied or taken possession of the improvement, in whole or in part, more than five years after the improvement has been occupied by the owner.
In this matter, Ms. Simon’s petition alleges that she entered into a contract
with Mid South for the elevation of her home on June 30, 2013. It further alleges
that Mid South failed to fulfill its obligations of the contract and listed the alleged
deficiencies resulting from Mid South’s work. The petition was filed on February
1, 2021. From the face of the petition, Ms. Simon’s action is perempted because it
22-CA-585 6 is against a contractor, Mid South, for construction or improvement to her home
and La. R.S. 9:2772 applies. Thus, the burden shifted to Ms. Simon to show her
action has not been perempted.
There was no acceptance of the work by Ms. Simon in the registry of the
mortgage office; thus, Subsection (A)(1)(a) of La. R.S. 9:2772 is inapplicable to
this matter. Because there was no acceptance of the work recorded, the next
consideration is whether Ms. Simon filed her action within five years after the
improvement had been occupied. At the hearing, Mid South introduced Ms.
Simon’s responses to the supplemental interrogatories, and those responses were
admitted into evidence by the trial court. The responses showed that Ms. Simon
admitted to living in her home on October 10, 2013, starting the commencement of
the peremptive period under Subsection (A)(1)(b).
Ms. Simon introduced her opposition to the exception of peremption into
evidence, along with her attached exhibits, which included her July 22, 2022
affidavit; an inspection report from Robert Wolfe Construction, Inc., the costs of
repairing possible foundation issues; Mid South’s proposal for the work to be
performed at her home; a letter from Victor H. Pedraz of Design Office, LLC,
stating that the work had been completed as per the engineered drawings; a copy of
the “Certification of Completion” from the Jefferson Parish Inspections and Code
Enforcement Office; and her March 28, 2014 letter to the Louisiana Attorney
General, complaining of the work performed on her home. All of her exhibits
were accepted into evidence by the trial court. However, none of the exhibits
presented by Ms. Simon contradicted the evidence that she occupied her home on
October 10, 2013. Consequently, Ms. Simon failed to prove that La. R.S.
9:2772(A)(1)(b) was inapplicable in her case and the action was not perempted.
Ms. Simon would like for this Court to engage in the semantics of the use of
the words “acceptance” and “completion.” She asserts that completion of the work
22-CA-585 7 is an integral part of the determination of the meaning of acceptance. The
language of La. R.S. 9:2772 is clear and specific. Celebration Church, Inc., supra.
The peremptive period runs either (a) from the date of registry of the acceptance of
the work by the owner, or (b) if no acceptance is recorded, within six months of the
date the owner occupies or takes possession of the improvement in whole or in
part. Id. Substantial completion is not relevant as to when the peremptive period
set forth in La. R.S. 9:2772(A)(1) begins to run. Id. Like the trial court, we
conclude that the more relevant inquiry is whether she filed her action within five
years of occupying her home; and, Ms. Simon failed to file her action within the
time prescribed. That conclusion for this matter does not lead to any erroneous or
absurd consequences. From the evidence presented, we find the trial court was
correct in its determination that Ms. Simon’s action is perempted.
Amendment of Petition
Ms. Simon alleges that the trial court erred in failing to allow her to amend
her petition. She argues that her petition seeks to recover on a breach of contract
between her and Mid South, and La. R.S. 9:2772(A) does not apply to her action.
She contends that she should be allowed an opportunity to submit an amending
petition to remove the grounds of Mid South’s peremptory exception.
Mid South objects to Ms. Simon being allowed to amend her petition.
La. R.S. 9:2772(A) provides that “no action, whether ex contractu, ex
delicto, or otherwise, including but not limited to an action to recover damage, or
otherwise arising out of an engagement of planning, construction, design, or
building immovable or movable property…shall be brought against any
person…performing or furnishing the design, planning, supervision, inspection, or
observation of construction or the construction of immovable, or improvement to
immovable property…” more than five years after the improvement has been thus
occupied by the owner. Because Ms. Simon’s breach of contract action arises from
22-CA-585 8 the elevation of her home, we find that the allegations filed more than five years
after she occupied her home cannot be cured with an amendment to the petition.
Therefore, we deny Ms. Simon’s request to amend her petition to cure the
peremption defect.
DECREE
For the foregoing reasons, we affirm the trial court’s judgment that sustained
Mid-South’s exception of peremption and dismissed Ms. Simon’s action with
prejudice. Ms. Simon is assessed the costs of this appeal.
AFFIRMED
22-CA-585 9 SUSAN M. CHEHARDY CURTIS B. PURSELL
CHIEF JUDGE CLERK OF COURT
SUSAN S. BUCHHOLZ FREDERICKA H. WICKER CHIEF DEPUTY CLERK JUDE G. GRAVOIS MARC E. JOHNSON ROBERT A. CHAISSON LINDA M. WISEMAN STEPHEN J. WINDHORST FIRST DEPUTY CLERK JOHN J. MOLAISON, JR. SCOTT U. SCHLEGEL FIFTH CIRCUIT MELISSA C. LEDET JUDGES 101 DERBIGNY STREET (70053) DIRECTOR OF CENTRAL STAFF POST OFFICE BOX 489 GRETNA, LOUISIANA 70054 (504) 376-1400
(504) 376-1498 FAX www.fifthcircuit.org
NOTICE OF JUDGMENT AND CERTIFICATE OF DELIVERY I CERTIFY THAT A COPY OF THE OPINION IN THE BELOW-NUMBERED MATTER HAS BEEN DELIVERED IN ACCORDANCE WITH UNIFORM RULES - COURT OF APPEAL, RULE 2-16.4 AND 2-16.5 THIS DAY OCTOBER 4, 2023 TO THE TRIAL JUDGE, CLERK OF COURT, COUNSEL OF RECORD AND ALL PARTIES NOT REPRESENTED BY COUNSEL, AS LISTED BELOW:
22-CA-585 E-NOTIFIED 24TH JUDICIAL DISTRICT COURT (CLERK) HONORABLE STEPHEN C. GREFER (DISTRICT JUDGE) R. A. OSBORN, JR. (APPELLANT)
MAILED GEORGE H. JONES (APPELLEE) ATTORNEY AT LAW 3609 KENT AVENUE METAIRIE, LA 70006