Martel Construction, Inc. v. State

817 P.2d 677, 249 Mont. 507, 48 State Rptr. 812, 1991 Mont. LEXIS 231
CourtMontana Supreme Court
DecidedAugust 30, 1991
Docket90-519
StatusPublished
Cited by13 cases

This text of 817 P.2d 677 (Martel Construction, Inc. v. State) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Martel Construction, Inc. v. State, 817 P.2d 677, 249 Mont. 507, 48 State Rptr. 812, 1991 Mont. LEXIS 231 (Mo. 1991).

Opinion

JUSTICE GRAY

delivered the Opinion of the Court.

The appellant, State of Montana, appeals from a judgment entered on a jury verdict rendered in the District Court of the First Judicial District, Lewis and Clark County, awarding the respondent, Martel Construction, Inc., $549,000 in damages for breach of contract. We affirm in part, reverse in part and remand for a new trial.

The sole issue for review is whether the District Court erred in ruling that Martel could recover, as an element of damages against the State, the interest expense paid on funds it was allegedly required to borrow in order to finance extra work caused by the State.

In June, 1984, the appellant, State of Montana, acting by and through the Montana Department of Highways, solicited bids for the reconstruction of the existing Burlington Northern Railroad overpass at Havre, Montana. The project called for the complete refurbishment of the existing railroad overpass and the addition of two more traffic lanes. The end result was to be a four-lane overpass consisting of a new bridge built immediately adjacent and attached to the refurbished old bridge.

The Department of Highways did not make a new survey of the existing bridge prior to putting the project out for bid. Instead, it used the plans prepared for construction in 1936 which the Department believed actually represented the elevation and dimensions of the bridge in 1984. The 1936 data was transposed onto the contract *509 drawings sent out to contractors for bidding purposes. Martel, relying upon the accuracy of the contract drawings, submitted the lowest bid and was awarded the contract on July 27, 1984.

Martel began construction on September 12, 1984. When Martel started to construct the new bridge to attach to the old bridge, it discovered that the elevation of the old bridge and certain other dimensions were not as represented on the contract drawings. Martel was required to perform extra work not contemplated under the contract in order to make the new bridge fit. Martel completed the contract on August 1, 1986.

On January 16, 1986, prior to completing the contract, Martel submitted a series of claims associated with extra work in performing the contract to the Department of Highways for administrative resolution. Some of the claims were allowed; most were denied by the Department on April 17, 1986. Martel appealed the denial of the claims to the Department’s Board of Contract Appeals on May 9,1986. The Board affirmed the original denial on December 31, 1986.

On March 26,1987, Martel filed suit in the District Court against the state of Montana seeking damages for breach of contract. Martel sought to recover its actual construction costs for the extra work it had performed under the contract as well as the interest it had paid on funds allegedly borrowed to finance the extra work. Martel denominated the interest it had paid on the borrowed funds as “moratory interest.”

Prior to trial, the District Court requested briefs from counsel on the issue of whether “moratory interest” could be recovered as an item of damages in a contract action against the State. The District Court ruled, as a matter of law, that the “moratory interest” claimed by Martel is part of the actual damages claimed to have been incurred by Martel, rather than prejudgment interest; thus, it could be recovered as an item of special or general damages for breach of contract.

Ajury trial was held May 28 through June 8,1990. At trial, Martel presented testimony and exhibit evidence that it incurred an actual expense of $170,841.46 through the payment of interest on funds borrowed during the period 1985-1990 in order to finance the construction project and that the average interest rate dining this time was 103/4%. During closing argument Martel’s counsel, stated:

‘You will also have with you exhibit number 126 which is the moratory interest calculations .... That is the actual money that Bill Martel paid out of his pocket to a bank to finance this job. And *510 whatever money you determine that he is entitled to you should add a factor of interest and I would suggest that once you have come up with a lump sum for delays and the... [extra construction] costs, that you can apply the 10 point three quarter percent interest.”

Later, in discussing the verdict form, counsel stated:

“I have not filled in any amounts for moratory interest because I trust that on any amounts that you find that Martel is entitled to you can apply the 10 point three quarter interest factor and come up with your own amount.”

In addition, Jury Instruction No. 23 instructed the jury that:

“Martel Construction is seeking ‘moratory interest’ damages from the State of Montana. Moratory interest is interest allowed in actions for breach of contract as damages for unlawful detention of money found due.
“As a jury, you may award moratory interest damages to Martel Construction if you find that the State of Montana caused Martel Construction to borrow money to pay for extra work or delays ordered by or caused by the State of Montana.”

At the conclusion of the trial the jury found the State had breached the contract between the parties and awarded Martel damages in the amount of $384,000 for extra work and $165,000 for “moratory interest,” for a total award of $549,000. The State appeals the portion of the judgment relating to the “moratory interest.”

Contract actions against the State of Montana are governed by Title 18, Chapter 1, part 4, MCA. The extent of the State’s liability in contract actions is set out in § 18-1-404, MCA, which provides, in pertinent part:

“Liability of state — limitations—costs. (1) The state of Montana shall be liable in respect to any contract entered into in the same manner and to the same extent as a private individual under like circumstances, except the state of Montana shall not be liable for interest prior to or after judgment or for punitive damages.”

As quoted above, except for the prohibition against interest prior to or after judgment and punitive damages, § 18-1-404(1), MCA, renders the State liable for damages in contract cases to the same extent as a similarly situated private litigant. The general measure of damages for breach of contract, including a breach of contract by the State, is set out in § 27-1-311, MCA.

“Breach of contract. For the breach of an obligation arising from contract, the measure of damages, except when otherwise expressly provided by this code, is the amount which will compensate the party *511 aggrieved for all the detriment which was proximately caused thereby or in the ordinary course of things would be likely to result therefrom. Damages which are not clearly ascertainable in both their nature and origin cannot be recovered for a breach of contract.”

In Ehly v. Cady (1984), 212 Mont. 82, 97, 687 P.2d 687, 695, we made the following observation regarding the types of damages recoverable for breach of contract:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State Farm Mutual Automobile Insurance v. Freyer
2013 MT 301 (Montana Supreme Court, 2013)
State Farm v. Freyer
2013 MT 301 (Montana Supreme Court, 2013)
McEwen v. MCR, LLC
2012 MT 319 (Montana Supreme Court, 2012)
Blanton v. DEPT. OF PUBLIC HEALTH SERVICES
2011 MT 110 (Montana Supreme Court, 2011)
Blanton v. Department of Public Health & Human Services
2011 MT 110 (Montana Supreme Court, 2011)
City of Dillon v. Montana Municipal Insurance Authority
2009 MT 393 (Montana Supreme Court, 2009)
Rothing v. Kallestad
2007 MT 109 (Montana Supreme Court, 2007)
Tipp v. Skjelset
1998 MT 263 (Montana Supreme Court, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
817 P.2d 677, 249 Mont. 507, 48 State Rptr. 812, 1991 Mont. LEXIS 231, Counsel Stack Legal Research, https://law.counselstack.com/opinion/martel-construction-inc-v-state-mont-1991.