This text of 126 N.W. 190 (Marshalltown Stone Co. v. Des Moines Brick Manufacturing Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Marshalltown Stone Co. v. Des Moines Brick Manufacturing Co., 126 N.W. 190, 149 Iowa 141 (iowa 1910).

Opinion

Ladd, J.

This case has been here twice before. On the first appeal, the contract as alleged in the petition was held not to be vulnerable to the grounds of a demurrer that it was without consideration and against public policy. 114 Iowa, 574. On the second appeal, entering judgment of a dismissal after setting aside, the verdict was adjudged error. 101 N. W. 1124. On the last trial, it appeared that plaintiff, a corporation, owned a stone quarry near [143]*143Marshalltown in 1898, was selling “rubhie” therefrom, and had disposed of two or three carloads of stone, broken by hand. The spur track from the main line of the Chicago Great Western Bailway Company ran within four hundred feet of the face of the quarry, but was not extended to it until the latter part of that year. About the 15th or 20th of July, the company entered into a contract for the purchase of a crushing outfit on condition that it might be canceled within thirty days. About the same time Magden & Sheeley applied to the president of. the company, F. G. Pierce, for prices, on crushed stone for the pavement of Cottage Grove Avenue in Des Moines, and was informed that this would depend on freight rates. The company immediately applied therefor to the freight agent of the railroad company. This agent informed the manager of defendant, Thomas F. Flynn, of this application, and suggested that some arrangement be made to obviate the necessity of the railroad company making very low rates to the stone company which it would be inclined to do, and Flynn promised to see what could be done. Shortly afterwards Pierce was told by someone over the telephone that defendant would like to see him, and he visited its office, where he met Flynn. Pierce testified that after some conversation Flynn mentioned that he had heard that plaintiff was figuring on furnishing Magden & Sheeley stone for the pavement, and would rather plaintiff would not furnish it; that Pierce said he did not feel like withdrawing without getting something out of it; and that it was finally agreed that defendant would pay plaintiff twenty-five cents per cubic yard for all crushed stone used therein, and this was to be computed at one cubic yard to eight yards of pavement, and that, plaintiff undertook not to ship stone to Des Moines during the remainder of the year. Plaintiff immediately notified Magden & Sheeley that it could not quote prices to them, canceled its contract for the stone crusher, and in all respects performed said agreement if [144]*144such, there was. There were 20,534 cubic yards of pavement, and recovery, if at all, would be for $641.50, with interest. On the other hand, Flynn denied that any arrangement of the kind on the part of defendant was discussed, but testified that he requested J. M. Christy, secretary of the Earlham Land Company, engaged in crushing and selling stone, and W. P. Mumaugh, representing Jack Campbell, who also operated a stone quarry to meet Pierce at defendant’s office, and that these men agreed with him that the Earlham Land Company and Campbell should each pay plaintiff twenty-five cents per cubic yard of crushed stone furnished by his principal for said pavement, and that plaintiff should not ship any during the remainder of the year. Both Christy and Mumaugh corroborate Flynn’s story. On the other hand, Pierce’s testimony is somewhat corroborated by that of Boardman. It is apparent from this recital of the record that the issues of fact were for the jury, and, as we discover no error in the court’s rulings during the trial, the case may be disposed of on the theory that there was a contract such as alleged, and that the plaintiff observed its negative requirements. It will' be 'observed that this contract was not for the purchase of stone of plaintiff, nor was it for refraining from shipping stone for any improvement in which defendant was then interested, or in which subsequently it became or expected to become interested. So far as the defendant is concerned, it derived not the slightest advantage from the transaction. The sole consideration was in plaintiff not doing what it otherwise would have done but for defendant’s alleged promise. 114 Iowa, 574. According to the jury’s finding, the naked agreement was that plaintiff should not ship any broken stone to Des Moines during the remainder of the year, and defendant should pay twenty-five cents per cubic yard for all stone made use of in a certain job, and it may be conceded that unless this agreement was in excess of the corporate powers of defendant, or the latter was [145]*145estopped from raising that issue, the judgment must stand. Such powers are defined in one of the articles of incorporation.

The general nature of the business to be transacted by this corporation shall be to manufacture and sell paving brick, pressed brick, fire brick, and sewer or tile pipe in any part of the United States, and also enter into contracts for the performance of any work or construction of any structure or improvement, in the doing or construction of which products of the character of those to be manufactured by this company are used, and to do such work and construct such structures and improvements, the intention being that the company shall have the right to enter into contracts for the performance of such work or construction of such structures or improvements and to perform such work, construct such structures or improvements in the city of Des Moines or elsewhere within the state of Iowa and outside the limits of said state, also to purchase or lease real estate for the purpose of said manufacturing, erect buildings and improvements thereon, purchase the necessary material therefor, and to lease or sell any such real estate, buildings, improvements, or material, whether acquired by purchase, lease or contract.

Upon analyzing this, it will be observed that the company was authorized (1) to manufacture certain commodities ordinarily made of clay; (2) to enter into contracts to do work or construct improvements wherein products of the character of such commodities were used; (3) to execute such contracts; (4) to lease or purchase real estate for the purpose of said manufacturing, erect buildings and improvements thereon, and purchase necessary materials for the erection of these; and (5) to lease or sell any of such real estate, buildings, improvements, or materials.

[146]*146i Corporations: implied power: ultra vires contract. [145]*145No one could well claim that authority to make the agreement alleged herein might be included within the first or last two subdivisions. ' The power to contract for [146]*146the doing of work or making of improvements and to carry same out necessarily implied the power fp acquire materials with which this might be done. To that end there can he no doubt but that defendant was authorized to buy broken stone and other material whenever required for that purpose. This was an implied power. It was nowhere expressly conferred, and the implication is on the ground of necessity, for without it the corporation might be unable to discharge the functions for which it was created. "Whatever may fairly be regarded as incidental to and consequential upon those things which are authorized by the charter of a corporation will not be held ultra vires, unless expressly prohibited.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Miller v. Register and Tribune Syndicate, Inc.
336 N.W.2d 709 (Supreme Court of Iowa, 1983)
Waters v. Disbrow & Co.
70 F.2d 572 (Eighth Circuit, 1934)
City of Abbeville v. Eureka Fire Hose Manufacturing Co.
170 S.E. 23 (Supreme Court of Georgia, 1933)
Scott County v. Advance-Rumley Thresher Co.
288 F. 739 (Eighth Circuit, 1923)
Kellogg-Mackay Co. v. Havre Hotel Co.
199 F. 727 (Ninth Circuit, 1912)

Cite This Page — Counsel Stack

Bluebook (online)
126 N.W. 190, 149 Iowa 141, Counsel Stack Legal Research, https://law.counselstack.com/opinion/marshalltown-stone-co-v-des-moines-brick-manufacturing-co-iowa-1910.