Marshall's Electric, Inc.

CourtArmed Services Board of Contract Appeals
DecidedMarch 7, 2016
DocketASBCA No. 59749
StatusPublished

This text of Marshall's Electric, Inc. (Marshall's Electric, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Marshall's Electric, Inc., (asbca 2016).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) Marshall's Electric, Inc. ) ASBCA No. 59749 ) Under Contract No. FA4613-13-C-0011 )

APPEARANCE FOR THE APPELLANT: Ms. Cynthia L. Marshall Secretary/Treasurer

APPEARANCES FOR THE GOVERNMENT: Col Matthew J. Mulbarger, USAF Air Force Chief Trial Attorney Lawrence M. Anderson, Esq. Trial Attorney

OPINION BY ADMINISTRATIVE JUDGE DELMAN

In this appeal Marshall's Electric, Inc., (appellant or MEI) disputes the termination of its contract for default by the Department of the Air Force (government). The parties agreed to waive an oral hearing and to present their positions on the record under Board Rule 11. We have jurisdiction under the Contract Disputes Act, 41 U.S.C. §§ 7101-7109. For reasons stated below, we deny the appeal.

FINDINGS OF FACT

1. On 27 June 2013, the government issued a solicitation for Repair Fire Protection/Detection Systems, Weapons Storage Area, at F.E. Warren Air Force Base, Wyoming (Item 0001 ). The project was targeted as a 100% small business set-aside. (Compl., ex. 1)

2. The solicitation and the eventual contract included FAR 52.228-15, PERFORMANCE AND PAYMENT BONDS-CONSTRUCTION (OCT 2010). Block 12 of Standard Form 1442, "Solicitation, Offer, and Award," provided that these bonds were to be furnished to the government within 20 calendar days of award. The contract also contained FAR 52.249-10, DEFAULT (FIXED-PRICE CONSTRUCTION) (APR 1984). (Comp!., ex. 1 at 13)

3. The government awarded Contract No. FA4613-13-C-0011 to appellant on 25 September 2013. Accordingly, appellant was to furnish the bonds to the government no later than 15 October 2013. Appellant was to complete the project within 195 calendar days after receipt of notice to proceed. (Comp I., ex. 6)*

4. We take judicial notice that between 1 October 2013 and 16 October 2013, there was a federal government shutdown. As a result of this shutdown, the offices of the Small Business Administration (SBA) were closed. According to appellant, this closure impacted the processing of its application for SBA bond guarantees (see generally 13 C.F.R. § 115, Surety Bond Guarantee). However the record shows that appellant did not request the bonds from its surety and execute the necessary SBA fee authorization form until 11November2013 (compl., ex. 9), nearly one month after the government reopened and nearly one month after bonds were required to be furnished to the government.

5. On 13 November 2013, MEI was notified by its surety that its bond request was denied due to outstanding claims related to its work as a subcontractor on a contract between the U.S. Army Corps of Engineers and Graham Construction Services at Minot Air Force Base, North Dakota (compl., exs. 11, 12). Appellant advised the government of this matter by email dated 14 November 2013, stating in pertinent part as follows:

Until we can get this project closed out our bonding is on hold, which directly impacts our ability to bond this project. We apologize for the disruption this may cause for this project.

(Compl., ex. 12 at 2)

6. By memorandum dated 24 December 2013, entitled in part "Potential Termination for Default," the contracting officer (CO) issued a notice to appellant, in the nature of a notice to show cause, as follows:

1. You are hereby notified that, since you have failed to provide bonding of subject contract in accordance with the contract terms (20 days following contract award), the Government is considering terminating the contract for default in accordance with FAR 52.249-10 "Default

* The contract at Section F-Deliveries or Performance provided for a "winter exclusion" period prohibiting certain outdoor work between 1 October 2013 and 30 May 2014 (R4, tab 1 at 7), absent written approval of the contracting officer. Thus the contract completion date was 9 December 2014 (R4, tab 8). Neither party contends however that this exclusionary period had any bearing on the default termination.

2 (Fixed-Price Construction)." Pending a final decision in this matter, it will be necessary to determine whether your failure to perform arose out of causes beyond your control and without fault or negligence on your part. Accordingly, you are hereby afforded the opportunity to present, in writing, any facts bearing on the question to the undersigned within thirty calendar (30) days after receipt of this notice.

(Compl., ex. 15)

7. Appellant replied to this notice by letter dated 7 January 2014. Appellant explained the nature of its problems on the Minot job and its attempt to obtain bonding on the subject contract. Appellant also stated as follows:

Unfortunately, the government shutdown in October greatly impacted our bonding. Ifwe were able to submit our bonding request the first or second week of October, it would have been approved and the [subject] project would not have been impacted by the USACE Minot AFB project.

In closing, we humbly request a 45 day grace period to obtain bonding. The USACE Minot AFB project will be completely closed out and all vendors/suppliers will be paid in full with final lien releases issued. We will await your decision.

(R4, tab 6 at 24-25) Appellant has not provided any evidence to show that if it had submitted its bonding request in early October 2013, the bond request would have been approved and would not have been impacted by the Minot job.

8. The government allowed the next 45 days to pass and did not default terminate the contract. Appellant did not obtain bonding within these 45 days, nor was the Minot project closed within these 45 days, nor was appellant able to represent to the government when the Minot project would close and when it would obtain payment and performance bonds for this project.

9. By memorandum to appellant dated 15 April 2014, entitled "Show Cause," the CO again notified appellant of its failure to provide bonding as required by the

3 contract and that the government was considering a termination for default. The government gave appellant another opportunity to provide evidence excusing its failure to perform. (Compl., ex. 18)

10. Appellant replied to the show cause notice by letter dated 28 April 2014. Appellant restated its attempt to obtain bonding, the impact of the government shutdown and its difficulties on the Minot job. Appellant stated as follows:

With reference to the Minot, North Dakota project, we were a subcontractor and suffered losses directly relating to one of our direct subcontractor's failure. With this subcontractor we did not require bonding, [sic] if we would have required bonding this would have mitigated the losses we are now experiencing. The subcontractor failure has resulted in a lawsuit which is pending.

We respectfully request that you consider not terminating for default. Many of the factors which led to our inability to produce bonding for this project were not within our control. We were prepare [sic] to perform this contract but due the mitigating factors outlined above were unable to obtain the necessary bonding.

(R4, tab 6 at 6-7) (Emphasis added)

11. By email dated 29 May 2014, the government sought an update from appellant on the bonding issue. Appellant replied by email on the same day, as follows:

I apologize for my delay in responding. We are still working to get the Minot project closed out. Graham Construction [the prime contractor] is refusing to close out this project until the pending lawsuit with our failed subcontractor is resolved although Graham is not and never has been named in the suit.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

§ 7101-7109
41 U.S.C. § 7101-7109
§ 7101
41 U.S.C. § 7101

Cite This Page — Counsel Stack

Bluebook (online)
Marshall's Electric, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/marshalls-electric-inc-asbca-2016.