Marshall v. LaBoi

270 P.2d 99, 125 Cal. App. 2d 253, 1954 Cal. App. LEXIS 1873
CourtCalifornia Court of Appeal
DecidedMay 18, 1954
DocketCiv. 15420
StatusPublished
Cited by6 cases

This text of 270 P.2d 99 (Marshall v. LaBoi) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Marshall v. LaBoi, 270 P.2d 99, 125 Cal. App. 2d 253, 1954 Cal. App. LEXIS 1873 (Cal. Ct. App. 1954).

Opinion

*255 PETERS, P. J.

The litigants involved in the various appeals here presented are:

Frank S. Marshall, a general contractor engaged in the building construction business, a respondent.
Wurster, Bernardi & Emmons, a copartnership of architects, and respondents.
Sam F. Termini and Alyce C. Termini, husband and wife, who built a home in Hillsborough, and who, directly or indirectly, employed Marshall as contractor, and the Wurster partnership, as architects, to design and construct the house. The Terminis are appellants herein.
Jesse LaBoi, nephew of the Terminis, and world war veteran, also an appellant.

The house involved cost well over $300,000. When it was nearly completed disputes arose between the parties, and the Terminis refused to pay Marshall and the architects large balances claimed to be due. These disputes resulted in the filing of the various actions here involved. Several pleadings and amended pleadings were filed. Only the final amended pleadings appear in the transcript. These need not be summarized in detail because of the limited nature of the issues presented on these appeals. Suffice it to say that from these pleadings it appears that the first action was brought by Marshall against LaBoi and the Terminis to foreclose Marshall’s mechanic’s lien, and for breach of contract. In addition to the filing of the lien, this pleading alleged the making of a written contract with LaBoi, who, it is averred, acted as agent for the Terminis, LaBoi being charged with being the record owner of the property and the Terminis the true owners, the breach of that contract, and the claim that $104,435.88 * was due and owing under it. The Terminis filed an answer and cross-complaint. It was stipulated that the answer should also be deemed to be that of LaBoi. In their answer the Terminis admitted the terms of the contract as pleaded by Marshall, alleged that the work had not been performed as required by the contract, and that Marshall had breached the contract in several respects. As one affirmative defense it was alleged that the contract and the work performed under it were illegal, being in claimed violation of certain pleaded federal statutes and the regulations adopted thereunder. By their cross-complaint the Terminis sought not only to defeat *256 Marshall’s recovery of any sum, but also sought damages from him for the claimed breach of his contract to keep the costs as low as possible. By this cross-complaint the Terminis also brought in the Wurster firm as new parties, alleging an oral agreement with the architects to pay them 10 per cent of the building costs to plan and supervise the construction of the house, and praying for damages for the claimed breach of that contract. In addition, the Terminis asked damages based on an alleged fraudulent conspiracy between Marshall and the Wurster firm to maintain an artificially high construction cost. This pleading of the Terminis admitted that the construction of the house had started September 19, 1946.

Marshall filed an answer denying the allegations of the cross-complaint, as did the Wurster firm. In addition, the architects cross-complained against the Terminis for breach of their contract for architectural services, it being averred that a balance was due and owing to them of $16,319.42, the precise amount of the judgment later entered in their favor. No further basic pleadings are included in the transcript, although it is assumed by all the litigants that the Terminis properly pleaded the defense of illegality against the Wurster firm. Certainly, the case was tried on that theory, and it will be hereafter assumed that such issue was properly raised by a proper pleading.

Thus, under the pleadings, the cases involving Marshall presented an equitable action for the foreclosure of a mechanic’s lien, and legal actions for breach of contract and conspiracy. The eases relating to the Wurster firm involved legal actions involving breach of contract and conspiracy.

The legal actions were tried before a jury. At the close of the presentation of the evidence on behalf of Marshall and the Wurster film, motions of nonsuit made by the Termiids based on the claimed illegality were denied. But after the Terminis had rested their eases, motions for nonsuit directed against the Terminis ’ cross-complaints for breach of contract made by Marshall and the Wurster firm were granted on the ground that Termini had admitted that he had consciously engaged in an illegal transaction.

There was then submitted to the jury the questions of breach of contract, conspiracy and common counts for work, labor and material furnished pleaded by Marshall and the Wurster firm, and the affirmative defenses of breach of contract and illegality raised by the Terminis. The jury returned verdicts in favor of Marshall for $103,079.10, plus interest, against *257 LaBoi and the Terminis, and against the Terminis and in favor of the Wurster firm in the amount of $16,319.42. Judgment was entered on these verdicts. Thereafter, the trial court, on the same evidence, entered its judgment in favor of Marshall in the foreclosure proceeding. Thereafter, the Terminis moved for new trials in all the actions. The trial court denied the motion as to Marshall but purported to grant it as to the Wurster firm on the ground of insufficiency of the evidence on the issue of illegality. This order was made, however, more than 60 days after notice of entry of the judgments, and so was admittedly- ineffectual. As a result the motions for a new trial were denied as a matter of law. The Terminis and LaBoi have appealed from the judgments.

A large portion of the lengthy reporter’s transcript is devoted to evidence relating to the claimed breaches of contract, to the value of the services rendered, and to the claimed conspiracy. These issues are not involved on these appeals. Appellants now urge only that the contracts and work performed thereunder were illegal, error in the instructions on illegality, and that there was misconduct on the part of the jury. In other words, on these appeals it is admitted that the evidence supports the implied and express findings that appellants breached the contracts, and that the damages recoverable, if not barred by illegality, are in the amounts fixed in the judgments. Appellants likewise concede that the contracts were illegal, being in violation of the federal statutes and regulations. It is their theory that respondents are barred because they participated in such illegality.

On the illegality issue, the statutes involved are the Second War Powers Act of 1942, as amended (56 U.S. Stats. at Large (1942), p. 176), and the Veterans’ Emergency Housing Act of 1946, as amended (60 U.S. Stats. at Large (1946), p. 207). Under these statutes, particularly the last, in an attempt to meet the problems caused by the housing shortage resulting from the war, and to aid veterans, an office of housing expediter was created with power by regulation to “establish the maximum sales prices for such housing accommodations,” and to issue regulations so as to insure that scarce building materials would be used in construction of veterans’ homes. Pursuant to the powers conferred by these statutes, various regulations here relevant were issued.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Castro v. Sangles
637 So. 2d 989 (District Court of Appeal of Florida, 1994)
Tri-Q, Inc. v. Sta-Hi Corp.
404 P.2d 486 (California Supreme Court, 1965)
Ulwelling v. Crown Coach Corp.
206 Cal. App. 2d 96 (California Court of Appeal, 1962)
Holland v. Morgan & Peacock Properties Co.
335 P.2d 769 (California Court of Appeal, 1959)
Cain v. Burns
280 P.2d 888 (California Court of Appeal, 1955)
May v. Herron
274 P.2d 484 (California Court of Appeal, 1954)

Cite This Page — Counsel Stack

Bluebook (online)
270 P.2d 99, 125 Cal. App. 2d 253, 1954 Cal. App. LEXIS 1873, Counsel Stack Legal Research, https://law.counselstack.com/opinion/marshall-v-laboi-calctapp-1954.