Marshall Construction Co. v. Bigelow

29 Haw. 641, 1927 Haw. LEXIS 36
Hawaii Supreme Court·Decided February 23, 1927·No. No. 1711.·Published·Cited by 2 cases

Opinion

OPINION OF THE COURT BY

PERRY, C. J.

This is a petition for a writ of mandamus to be directed to the members of the board of harbor commissioners of the Territory of Hawaii to compel them to award to the petitioner the contract for the construction of a wharf and approach thereto at Kaunakakai on the Island of Molokai. The allegations of the petition and of the alternative writ are that upon plans and specifications prepared by the board the petitioner and the Hawaiian Dredging Company, Limited, presented bids; that “by virtue of petitioner’s said tender petitioner became and was the lowest responsible bidder” but that, nevertheless, both bids were rejected by the board; and that “pe *642 tition er’s said tender was rejected by said board, not in the exercise of any discretion vested in it, or the members thereof, by law, but arbitrarily and capriciously, and upon the pretext and subterfuge that said tender was not, or might not be, the lowest tender.” A demurrer by the respondents was ordered overruled by this court (29 Haw. 48), the ruling being that the allegation above quoted, to the effect that the board’s action was arbitrary and capricious, was an allegation of fact, susceptible of proof, and not a mere conclusion of law. This court said that mandamus will lie “where there has been a palpable abuse of discretion, that discretion must always be reasonably, fairly and impartially exercised, in good faith, and that whether or not it has been so exercised is a question for the courts”; and it also said that “there can be no doubt that a writ of mandamus will not issue to direct or control the judgment or discretion of public officers.” Thereafter the respondents filed a return or answer to the alternative writ, setting forth the history of the case at some length, denying that the petitioner was the lowest bidder, asserting that the price bid by the petitioner upon certain units “was so large and so disproportionate to the remainder of the bid, that the cost of the improvement under a contract with such bidder would have been greater, or probably greater, than if such contract were awarded to said Hawaiian Dredging Company, Limited,” alleging that the petitioner’s bid was “unbalanced” and that an award of the contract to it “would have been detrimental to the public interest,” that the respondents “by reason of said exorbitant unit prices of said bid” (of the petitioner) “could not be sure that sufficient money had been appropriated by the legislature to complete a contract let in accordance with said bid” and that respondents, “after a full consideration of the bids and of the specifications,” rejected both bids *643 “believing that such action Avas necessary to subserve the public interest and believing that the bids Avere too high.” After hearing evidence the trial judge found the facts to be in accordance AA’ith the allegations of the petitioner’s bill and entered judgment ordering a peremptory mandate to issue as prayed for. From that judgment the respondents appealed to this court.

Plans and specifications for the improvement in question were prepared by the board of harbor commissioners and were furnished to intending bidders as the basis of the bids to be offered. Upon the first call for tenders one bid only was presented, that being by the Hawaiian Dredging Company, Limited, and in the sum of $167,120. The appropriation at that time available for payment of the cost of the project was in the sum of $125,000. Shortly after the presentation and opening of this bid the legislature was in session and increased the appropriation to $175,000. Nevertheless the bid of the dredging company Avas rejected by the board. Bids Avere called for a second time. Two Avere presented, one by the Hawaiian Dredging Company, Limited, in the same sum of $167,120 and one by the Marshall Construction Company, Limited, in the sum of $158,273.50. These were the “lump-sum proposals,” as they have been called in this case; but in each tender there were certain additional prices bid, which aaíII be hereafter referred to. Both of these bids were rejected by the board. Thereupon the present proceeding Avas instituted by the petitioner to compel the acceptance of its bid and the awarding of the contract to it.

Free access — add to your briefcase to read the full text and ask questions with AI

Marshall Construction Co. v. Bigelow, 29 Haw. 641, 1927 Haw. LEXIS 36 (haw 1927).

29 Haw. 641 (Marshall Construction Co. v. Bigelow) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Matter of Application of Air Terminal Services, Inc.
393 P.2d 60 (Hawaii Supreme Court, 1964)