Mars Associates, Inc. & Normel Construction Corp. Joint Venturers v. Health & Mental Hygiene Facilities Improvement Corp.

47 A.D.2d 5, 364 N.Y.S.2d 67, 1975 N.Y. App. Div. LEXIS 8703
CourtAppellate Division of the Supreme Court of the State of New York
DecidedFebruary 27, 1975
StatusPublished
Cited by10 cases

This text of 47 A.D.2d 5 (Mars Associates, Inc. & Normel Construction Corp. Joint Venturers v. Health & Mental Hygiene Facilities Improvement Corp.) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mars Associates, Inc. & Normel Construction Corp. Joint Venturers v. Health & Mental Hygiene Facilities Improvement Corp., 47 A.D.2d 5, 364 N.Y.S.2d 67, 1975 N.Y. App. Div. LEXIS 8703 (N.Y. Ct. App. 1975).

Opinion

Greenblott, J.

Plaintiff was the successful bidder for a construction contract on a facility owned by defendant. The proposal together with specifications, was put out for bidding, requesting bidders to state a base bid for the project as a whole plus the specific amount which would be added to or deducted [6]*6from 'the (base bid for each of 16 alternarte proposals. When the contract was executed, alternates numbered 2C, 130 and 150 were expressly included in the contract. In his first cause of action, plaintiff seeks payment of $50,000, the amount of its bid under alternate 120. That provision of the proposal reads as follows:

ALTERNATE NO. 12c — ACQUISITION 0E ADJACENT PROPERTY
“a. It is- anticipated that the adjacent property to the west of the present site, which is presently being utilized as a parking lot, will be acquired by New York City. In such event, the Contractor will be permitted to use a portion of this adjacent property for material storage, staging and access to the. present building site, (see Drawing A-l for extent of area rto be available) In the event this property is not acquired within 90 days of Notice to Proceed, the Contractor shall state the addition to the Contract Amount should this property not be available for use by the Contractor.”

It is not disputed that the property referred to in alternate 12C was not acquired within the appropriate time limits. Defendant successfully urged before Special Term that since alternate 120 was not expressly listed in the final contract, it was not a part of that contract and could not be claimed by plaintiff as ■an item which had been breached. Plaintiff contends that the contract 'stated that all terms and provisions contained in the proposal .and specifications were included in the contract, and that alternate 120, in addition to being included under the Umbrella of this provision, was in any event a self-executing provision which was not conditioned upon acceptance or rejection.

It is, of course, fundamental so as not to require citation of authority that a contract must be read to give meaning to all its provisions, and any ambiguity must be construed against the piarty who drafted the contract. Furthermore, in construing the words of a contract, they must be given their ordinary meaning unless the context requires a different construction. Thus, the general provision including within the contract all terms, conditions and provisions set forth in the notice rto bidders, the proposal, the general conditions, the drawings, and the specifications, as if such terms, conditions and provisions were expressly and specifically set forth, would ordinarily require inclusion of 12C. On the other hand, the express acceptance of 20, 130 and 150 gives rise to the implication that other alternates were not to be included. The court at Special Term [7]*7applied the latter rule, for in his view, adoption of the former would require the inclusion of all other alternates in the contract merely because they were contained in the proposals and •specifications.

Special Term did note that alternate 12C differed in nature from the three alternates which were expressly accepted. It is also obvious to us that the other 12 alternates were similar in nature to the three which were accepted and different from 120.

In our view, it was in failing to give any effect to this difference that Special Term erred. Alternate 130, for example, called for specified aluminum windows instead of steel windows. Similarly, all the other alternates, excepting 120, called for additions or deletions of components, substitution of materials, and the like with regard to specific and limited items. Obviously, only an alternate or the provision it replaced could be operative, lest there be a confusing duplication of work. None of them were of such ,a nature as to be automatically includable upon the occurrence or nonoccurrence of a specified condition.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Adelphia Communications Corp.
368 B.R. 348 (S.D. New York, 2007)
USA Network v. Jones Intercable, Inc.
729 F. Supp. 304 (S.D. New York, 1990)
Acme Builders, Inc. v. Facilities Development Corp.
69 A.D.2d 937 (Appellate Division of the Supreme Court of New York, 1979)
Bostwick-Westbury Corp. v. Commercial Trading Co.
94 Misc. 2d 401 (Civil Court of the City of New York, 1978)
Allied Chemical Corp. v. Alpha Portland Industries, Inc.
58 A.D.2d 975 (Appellate Division of the Supreme Court of New York, 1977)
Waxstein v. Waxstein
90 Misc. 2d 784 (New York Supreme Court, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
47 A.D.2d 5, 364 N.Y.S.2d 67, 1975 N.Y. App. Div. LEXIS 8703, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mars-associates-inc-normel-construction-corp-joint-venturers-v-health-nyappdiv-1975.