Marrs-Winn Co. v. Giberson Electric, Inc. (In Re Marrs-Winn Co.)

193 B.R. 491, 1996 U.S. Dist. LEXIS 2992, 1996 WL 109279
CourtDistrict Court, C.D. Illinois
DecidedMarch 11, 1996
Docket95-3108
StatusPublished
Cited by1 cases

This text of 193 B.R. 491 (Marrs-Winn Co. v. Giberson Electric, Inc. (In Re Marrs-Winn Co.)) is published on Counsel Stack Legal Research, covering District Court, C.D. Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Marrs-Winn Co. v. Giberson Electric, Inc. (In Re Marrs-Winn Co.), 193 B.R. 491, 1996 U.S. Dist. LEXIS 2992, 1996 WL 109279 (C.D. Ill. 1996).

Opinion

*493 OPINION

RICHARD MILLS, District Judge:

Bankruptcy appeal.

In short, the bankruptcy judge is affirmed.

I. BACKGROUND

A. Facts 1

This case arises out of the construction of St. Louis, Missouri’s new domed football stadium, now known as the TransWorld Dome.

Plaintiff/Appellee J.S. Alberici Construction Co., Inc. (Alberici) was the general contractor for the stadium construction project, and Plaintiff/Appellee Marrs-Winn Co., Inc. (Marrs-Winn) — the debtor — was a subcontractor on the stadium project. Defendant/Appellant Giberson Electric, Inc. made a business loan to Marrs-Winn to enable Marrs-Winn to comply with the conditions of its subcontract with Alberici.

On May 18, 1993, Alberici informed Marrs-Winn that it intended to award Marrs-Winn the subcontract to install reinforcing steel and post tensioning cable on the stadium project. In exchange for the work to be done, Alberici stated that it would pay $6,896,900, a price based on Marrs-Winn’s bid and the requirement that Marrs-Winn furnish payment and performance bonds.

Marrs-Winn was unable to satisfy the bonding requirements set forth in the subcontract and was unable to contract with union ironworkers needed to do the job. On June 11,1993, Alberici informed Marrs-Winn that it would withhold its signature on the subcontract until it received adequate bonds. Alberici subsequently stated that Marrs-Winn’s failure to obtain proper bonds meant that Alberici would have to begin the reinforcing work itself and charge Marrs-Winn for the expense of doing so. On June 21, 1993, Alberici began the reinforcing work, and eventually “backcharged” Marrs-Winn $296,724.25 for the work it did.

On August 9, 1993, Marrs-Winn finally obtained suitable guarantees to satisfy Alber-ici. Alberici and Marrs-Winn added “Exhibit G” to the subcontract. Exhibit G required Marrs-Winn to post a $100,000 letter of credit in favor of Alberici and established a special account to facilitate payment of Marrs-Winn’s payroll expenses.

On August 10, 1993, Marrs-Winn filed a petition in Bankruptcy under Chapter 11 of the Bankruptcy Code. To meet its obligation under Exhibit G and to begin work on the St. Louis Stadium project, Marrs-Winn entered into a Business Loan and Security Agreement (BLSA) with Giberson. The BLSA, dated August 19, 1993, required Giberson to post the $100,000.00 letter of credit required by Exhibit G and provided for Giberson to advance up to $150,000.00 to Marrs-Winn.

Giberson and Marrs-Winn presented the BLSA to the bankruptcy court for approval. They represented that the agreement was essential to Marrs-Winn’s ability to perform the subcontract, completion of which would benefit all the creditors. The bankruptcy court approved the BLSA in an Order Autho-rising Debtor to Borrow Money, Grant Security Interest and Accord Priority Claim Status (the Financing Order). The Financing Order granted Giberson a first priority security interest in:

[A]ll of the personal property of the Debt- or that is presently existing, hereafter created or acquired by it or its estate or in which Debtor or its estate hereafter acquires any interest, wheresoever such property may be situated, including, without limitation, the following: All inventory of every kind and description, whether raw materials, work in process or finished goods, and all materials used or useable for the processing packaging or shipping of inventory; all accounts, accounts receivable, contracts (specifically including the Stadium contact), contract rights, and general intangibles; all documents, instruments and chattel paper; all returned, rejected and repossessed goods; all machinery, equipment, fixtures, furniture and motor vehicles; and all cash and non-cash *494 proceeds of the foregoing items, including insurance proceeds....

On August 18, 1993, Alberici received the $100,000 letter of credit from Giberson. A week later, Alberici received Marrs-Winn’s certificate of insurance, and on August 27, 1993, Alberici signed the subcontract. By the end of August Marrs-Winn had contracted with union ironworkers and by September 1, 1993, Marrs-Winn began work on the stadium project.

On August 17, 1993, a bank account was opened at Magna Bank of Illinois, under the name “Marrs-Winn Co., Inc., Debtor-in-Possession” (Magna Account). Payments from Alberici, under the subcontract, were to be deposited in the account. 2 The Loan agreement prohibited withdrawals from the account except with the signatures of Marrs-Winn and Giberson. Pursuant to a bank resolution, only Marrs-Winn’s president was permitted to transfer funds.

On December 1, 1993, the balance of the Magna Account was approximately $20,000. On that day, Alberici approved two transfers to the account. The first was a payroll-related transfer of $79,610.67 and the second was a progress payment of $112,452.61.

On December 1, 1993, Giberson transferred $112,452.61 from the Marrs-Winn account to its own account. On December 3, 1993 Giberson again transferred funds from the Marrs-Winn account, this time $99,000.

On January 4, 1994, Marrs-Winn and Al-berici filed a complaint in the bankruptcy court, seeking to force Giberson to return the funds it had transferred out of the Marrs-Winn account at Magna bank. On January 25, 1994, Giberson filed a motion seeking the bankruptcy court’s approval of its application of the funds in the Marrs-Winn account to its debt. As the bankruptcy court noted, Giberson made these transfers without Marrs-Winn’s permission or signature.

B. Decision Below

The bankruptcy court made several findings regarding Giberson’s withdrawal of funds from the Magna Account. First, the bankruptcy court found that the withdrawal violated the loan agreement, which provides that withdrawals from the account were to be made “only pursuant to the signature of Marrs-Winn and Giberson.”

Second, the bankruptcy court found that Giberson’s withdrawal also violated the automatic stay imposed by 11 U.S.C. § 362. The bankruptcy court found that by taking possession of the funds Giberson violated the stay because it was not authorized by the Financing Order to seize the funds. Specifically, the bankruptcy court found that Giber-son lacked authority to unilaterally decide to apply the funds in the Magna Account to its own debt.

After making these preliminary findings, the bankruptcy court evaluated whether Gi-berson had a right to the funds it had withdrawn. The bankruptcy court rejected Giberson’s claim that the BLSA and the Financing Order entitled it to the money Al-berici placed in the Magna Account. The bankruptcy court acknowledged that the Financing Order granted Giberson a first priority security interest in all of Marrs-Winn’s property and that the Order authorized Giberson to receive and apply post-Chapter 11 accounts receivable and to withdraw remittances from lock boxes.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
193 B.R. 491, 1996 U.S. Dist. LEXIS 2992, 1996 WL 109279, Counsel Stack Legal Research, https://law.counselstack.com/opinion/marrs-winn-co-v-giberson-electric-inc-in-re-marrs-winn-co-ilcd-1996.