Marrs-Winn Co. v. Giberson Electric, Inc. (In Re Marrs-Winn Co.)

203 B.R. 964, 1995 Bankr. LEXIS 2112, 1995 WL 908277
CourtUnited States Bankruptcy Court, C.D. Illinois
DecidedFebruary 2, 1995
Docket19-70066
StatusPublished
Cited by2 cases

This text of 203 B.R. 964 (Marrs-Winn Co. v. Giberson Electric, Inc. (In Re Marrs-Winn Co.)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, C.D. Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Marrs-Winn Co. v. Giberson Electric, Inc. (In Re Marrs-Winn Co.), 203 B.R. 964, 1995 Bankr. LEXIS 2112, 1995 WL 908277 (Ill. 1995).

Opinion

*966 OPINION

LARRY L. LESSEN, Bankruptcy Judge.

The issue before the Court is whether a creditor wrongfully seized funds in the Debtor-in-Possession’s bank account. In resolving this issue, the Court must determine whether the funds were trust funds in which the Debtor held only bare legal title, or whether the funds were property of the estate and therefore subject to the creditor’s security interest.

St. Louis has been without a professional football team since Mr. Bidwell picked up the St. Louis Cardinals seven years ago and moved them to Arizona. In order to attract a new football team, St. Louis is currently building a domed stadium. J.S. Alberici Construction Co., Inc. is the general contractor on the Stadium Project. As part of its contract on the project, Alberici is required to help out or “mentor” minority-owned businesses. The Debtor, Marrs-Winn, a minority-owned business, was one of the several bidders submitting bids to Alberici to furnish and install the reinforcing steel, the post tensioning cable, and related accessories for the Stadium Project. On May 18, 1993, Al-berici informed the Debtor that it intended to award to the Debtor the Subcontract for the steel reinforcement work. The Subcontract price of $6,896,900 was based on the Debtor’s bid price, which included $36,100 for the Debtor’s cost to furnish the required payment and performance bonds.

The Debtor was initially unable to satisfy the requirements relating to the performance and payment bonds. The Debtor was also unable to contract with the local union iron-workers. In a letter dated June 11, 1993, Alberici informed the Debtor that Alberici had received the signed Subcontract from the Debtor but that Alberici was withholding its signature until it received the required payment and performance bonds. Alberici subsequently advised the Debtor that the failure to furnish the required bonds would prevent the Debtor from starting work on the scheduled June 17, 1993, start date. In a letter dated June 18, 1993, Alberici advised the Debtor that due to the lack of the required insurance coverage and bond protection, Al-berici would start the on-site reinforcing work on June 21, 1993, and “charge Marrs-Winn’s Subcontract for the costs associated with this activity.” Alberici did in fact begin the reinforcing steel work in late June, 1993, using ironworkers employed and paid by Al-berici. Alberici later “backcharged” the Debtor $296,724.25 for the work performed by Alberici through August, 1993. Of this amount, $205,772.59 was incurred before August 10,1993.

The Debtor continued to negotiate with Alberici over the summer on the subject of what would constitute an adequate bond, and this issue was finally resolved on August 9, 1993, by Exhibit G to the Subcontract. Subcontract Exhibit G requires that the Debtor post a $100,000 letter of credit in favor of Alberici as security for any default by the Debtor under the Subcontract. Exhibit G also set an agreed procedure for establishing and operating a special account to insure the payment of the Debtor’s payroll related expenses for the project.

The Debtor filed its petition pursuant to Chapter 11 of the Bankruptcy Code on August 10,1993.

The Debtor was able to provide the necessary letter of credit to Alberici through an agreement with Giberson Electric, Inc. This agreement was incorporated into a Business Loan and Security Agreement dated August 19, 1993. Pursuant to this Loan Agreement, Giberson agreed to loan or advance to the Debtor up to $150,000 in order to allow the Debtor to proceed with its performance under the Subcontract. In addition, Giberson agreed to post the $100,000 letter of credit required under Exhibit G. The Debtor and Giberson presented this agreement to the Court with the representations that the loan was necessary for the Debtor to complete the Subcontract, that the Subcontract was necessary to the continued viability of the Debtor, that time was of the essence, and that the completion of the Subcontract would result in a 100% payout to all creditors. Based on these representations, the Court approved the Loan Agreement on an emergency basis without notice to the Debtor’s unsecured creditors on August 20, 1993. A final hearing was set for September 9, 1993, at which time the only objection was to a provision in *967 the Loan Agreement which would pay Giber-son $400,000 in exchange for Giberson’s “expertise, skills, and advice” in assisting the Debtor in its performance of the Subcontract. This provision was not addressed in the Court’s Order approving the Loan Agreement, and the Court indicated that it would closely scrutinize any request by Gi-berson for consulting fees before approving the payment of such fees. Alberiei did not receive notice of the Loan Agreement.

On August 18, 1998, Alberiei received the $100,000 letter of credit. A week later, Al-berici received the Debtor’s Certificate of Insurance. As a result of these actions, Al-berici signed the Subcontract. Notice of the signed Subcontract was sent to the Debtor on August 27, 1993. The Debtor executed the labor agreement with the ironworkers on August 31, 1993, and commenced work with its own employees on the project on September 1,1993.

Pursuant to the Loan Agreement, a bank account was opened on August 17, 1993, at Magna Bank of Illinois in the name of “Marrs-Winn Co., Inc., Debtor-in-Possession.” All payments by Alberiei under the Subcontract were to be deposited into this account. According to the Loan Agreement, all funds placed in the Magna account “shall be withdrawn only pursuant to the signature of Marrs-Winn and Giberson.” A bank resolution supplied by Magna Bank was signed only by the Debtor’s president, and the Debt- or’s president was the only named individual authorized to make a transfer of funds. The account was not specifically designated as a “trust account”.

As of December 1, 1993, the Magna account had a balance of nearly $20,000. At this time, Alberiei approved two transfers to the Magna account: (1) a payroll-related transfer of $79,610.67 to cover the Debtor’s upcoming project payroll and payroll-related expenses; and (2) a progress payment of $112,452.61.

On December 1, 1993, Giberson transferred $112,462.61 from the Debtor’s Magna account to Giberson’s own account. On December 3,1993, Giberson transferred $99,000 from the Magna account to its own account. These transfers were made without the consent of the Debtor.

On January 4,1994, the Debtor and Alber-ici filed a Joint Complaint to Avoid Post-Petition Transfer and For a Declaratory Judgment. The Complaint seeks the return of the withdrawn funds and a declaration that the withdrawn funds are trust fund assets pursuant to the Subcontract. On January 25, 1994, Giberson filed a Motion for Order Approving Application of Funds and Provision of Priority Interest. As the title of its motion suggests, Giberson seeks approval, of its application of the withdrawn fund to its debt.

At the outset, the Court finds that Giber-son’s withdrawal of the funds from the Mag-na account violated the Loan Agreement. According to the Loan Agreement, withdrawals from the account were to be made “only pursuant to the signature of MARRS-WINN and GIBERSON”. Marrs-Winn did not sign the two withdrawals in dispute.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
203 B.R. 964, 1995 Bankr. LEXIS 2112, 1995 WL 908277, Counsel Stack Legal Research, https://law.counselstack.com/opinion/marrs-winn-co-v-giberson-electric-inc-in-re-marrs-winn-co-ilcb-1995.