Marquette Cty. Road Comm'n v. EPA

Court of Appeals for the Sixth Circuit·Decided March 20, 2018·No. 17-1154·Unpublished

Opinion

NOT RECOMMENDED FOR PUBLICATION File Name: 18a0145n.06

No. 17-1154

UNITED STATES COURT OF APPEALS FOR THE SIXTH CIRCUIT FILED Mar 20, 2018

MARQUETTE COUNTY ROAD COMMISSION, )

DEBORAH S. HUNT, Clerk

)

Plaintiff-Appellant, )

)

v. ) ON APPEAL FROM THE ) UNITED STATES DISTRICT UNITED STATES ENVIRONMENTAL ) COURT FOR THE WESTERN PROTECTION AGENCY, et al., ) DISTRICT OF MICHIGAN )

Defendants-Appellees. )

)

BEFORE: BATCHELDER, GRIFFIN, and WHITE, Circuit Judges.

ALICE M. BATCHELDER, Circuit Judge. In 2011, Plaintiff-Appellant Marquette County Road Commission (“Road Commission”) applied to Michigan’s permitting authority— Michigan Department of Environmental Quality (“MDEQ”)—for a permit to fill 25 acres of wetlands to construct County Road 595. See 33 U.S.C. § 1344. MDEQ wanted to issue the application, but the U.S. Environmental Protection Agency (“EPA”)—which the Clean Water Act (“CWA”) empowers to oversee state-run permitting programs—objected to various aspects of the proposal. Despite the Road Commission’s numerous attempts to revise the permit application over the following months, EPA remained unsatisfied. Eventually, authority to resolve the permit application transferred to the Army Corps of Engineers (“Corps”). 33 U.S.C. § 1344(j); 40 C.F.R. § 233.50(j). Frustrated with the time and expense of the process, the Road Commission declined to continue the permit review process before the Corps and instead

brought claims under the Administrative Procedure Act (“APA”) against EPA and the Corps based on EPA’s refusal to approve the issuance of the application and the Corps’ requirement that the Road Commission re-submit its application materials to continue the process. The district court determined that neither of these agency actions constituted a final agency action. The district court also rejected the Road Commission’s alternative arguments that EPA’s objections were reviewable, non-final agency action and that completion of the Corps review process would have been futile. The district court dismissed the suit. We agree and AFFIRM.

I.

Section 404 of the CWA regulates the release of dredged and fill matter into waterways, including wetlands. See § 33 U.S.C. § 1344. Generally, the Secretary of the Army oversees Section 404 permitting through the Corps. See id. However, the CWA also allows states to administer their own Section 404 permitting programs subject to federal approval and oversight by EPA. See id. § 1344(g)-(j); 40 C.F.R. §§ 233.16, 233.20, 233.50, 233.52, 233.53. Michigan is one of two states having federal approval to operate its own permitting program.

State-run permitting programs such as Michigan’s are subject to rigorous EPA oversight.

See 33 U.S.C. § 1344(j); 40 C.F.R. § 233.50. For example, states must submit copies of each permit application to EPA and notify EPA of any action that they take with respect to these applications. 33 U.S.C. § 1344(j).1 If EPA intends to comment on a state’s handling of an application, it must notify the state within thirty days and submit comments to the state within ninety days. Id. Once EPA notifies a state that it intends to comment on the permit application, a state may not issue a permit until it receives the comments or ninety days pass, whichever

1 EPA also functions as a liaison between the state and other involved federal agencies. EPA must provide copies of each application it receives to the Corps and the Department of the Interior (through the U.S. Fish and Wildlife Service), and is responsible for integrating comments from these other federal agencies into its comments to the state. Id. at § 1344(j).

comes first. Id. If EPA objects to the state’s issuing a permit, a state “shall not issue the permit unless [it] has taken the steps required by [EPA] to eliminate the objection,” regardless of how much time has passed. 40 C.F.R. § 233.50(f); accord 33 U.S.C. § 1344(j). EPA must provide reasons for objecting to the issuance of a permit “and the conditions which such permit would include if it were issued by [EPA].” 33 U.S.C. § 1344(j); accord 40 C.F.R. § 233.50(e).

A state has limited options when it wishes to issue a permit to which EPA objects. It may (i) issue a revised permit that eliminates EPA’s objection; (ii) deny the permit; or (iii) request a public hearing. See 33 U.S.C. § 1344(j); 40 C.F.R. § 233.50(f)-(g). If the state does not take one of these three actions within ninety days of EPA’s objection, authority to make a final decision regarding the permit transfers to the Corps. 33 U.S.C. § 1344(j); 40 C.F.R. § 233.50(j). If the state requests a public hearing, EPA must conduct the hearing and then “reaffirm, modify, or withdraw the objection or requirement for a permit.” 40 C.F.R. § 233.50(h). If EPA reaffirms or modifies its objection, the state has essentially the same recourse it had before the hearing: it must within thirty days either issue a revised permit that eliminates EPA’s objections or deny the permit. 40 C.F.R. § 233.50(f)-(j). If the state does not take either of these actions, authority to review and make a decision regarding the permit transfers to the Corps. 33 U.S.C. § 1344(j); 40 C.F.R. § 223.50(j).

II.

The Section 404 permitting process has the potential to be onerous, and proved to be so for the Road Commission. The Road Commission submitted its permit proposal for County Road 595 to MDEQ—the state agency that runs Michigan’s program—in October 2011 and a revised proposal in January 2012.2 On April 23, 2012, after consulting with the Corps and the

2 EPA, the Corps, and the U.S. Fish and Wildlife Service all received copies of the Road Commission’s revised permit application, per statutory directives.

U.S. Fish and Wildlife Service, EPA objected to the Road Commission’s proposal. EPA’s objections asserted that the Road Commission failed to comply with the requirements of the CWA because, among other things, it did not demonstrate that the proposed road was the “least environmentally damaging practical alternative.”

Over the next several months the Road Commission revised its proposal numerous times based on conversations between it, MDEQ, and EPA. Despite the Road Commission’s attempts to resolve EPA’s objections, EPA remained unsatisfied and believed the proposal failed to meet CWA standards. MDEQ, however, thought the most recently revised proposal met CWA standards and wished to grant the Road Commission a permit.

MDEQ requested a public hearing, which EPA held on August 28, 2012. Following the hearing, MDEQ sent a letter to EPA urging EPA to remove its objections so that it could grant the permit. MDEQ contended that “the Road Commission ha[d] been responsive to the concerns expressed in [MDEQ’s] and [EPA’s] correspondence . . . including the [EPA’s] April 23, 2012, objection letter.” Since EPA’s objection, the letter stated, the Road Commission had expanded its explanation “of the alternatives analysis that demonstrate[s] the proposed route is the least environmentally damaging practicable alternative to achieve the project purpose,” “effectively minimized . . . impacts to streams via shorter and wider stream crossings or bridges,” “narrowed or removed [the road footprint] across the rare and imperiled wetlands,” and “modified [the proposed road route] in several locations to avoid critical wetlands and further reduce overall impacts.” MDEQ stated that it believed these improvements adequately addressed EPA’s and MDEQ’s comments and brought MDEQ “to the point [where] Michigan will soon be in a position to issue a permit.” In closing, the letter “urge[d] []EPA to remove their objection to the MDEQ issuing a permit for construction of Marquette County Road 595.”

Free access — add to your briefcase to read the full text and ask questions with AI

Marquette Cty. Road Comm'n v. EPA, (6th Cir. 2018).

Marquette Cty. Road Comm'n v. EPA (Marquette Cty. Road Comm'n v. EPA) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Leedom v. Kyne
358 U.S. 184 (Supreme Court, 1958)
Bennett v. Spear
520 U.S. 154 (Supreme Court, 1997)
Sackett v. Environmental Protection Agency
132 S. Ct. 1367 (Supreme Court, 2012)
Jama v. Department of Homeland Security
760 F.3d 490 (Sixth Circuit, 2014)
U.S. Army Corps of Eng'rs v. Hawkes Co.
578 U.S. 590 (Supreme Court, 2016)
Berry v. United States Department of Labor
832 F.3d 627 (Sixth Circuit, 2016)