Markley v. Allison

47 Pa. D. & C. 525, 1943 Pa. Dist. & Cnty. Dec. LEXIS 429
CourtPennsylvania Court of Common Pleas, Beaver County
DecidedMay 17, 1943
Docketno. 168
StatusPublished

This text of 47 Pa. D. & C. 525 (Markley v. Allison) is published on Counsel Stack Legal Research, covering Pennsylvania Court of Common Pleas, Beaver County primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Markley v. Allison, 47 Pa. D. & C. 525, 1943 Pa. Dist. & Cnty. Dec. LEXIS 429 (Pa. Super. Ct. 1943).

Opinion

Wilson, J.,

On April 26, 1930, the Monongahela Land Company accepted a proposal of S. B. Markley to put in approximately 3,000 feet of sewer at $1 per lineal foot, approximately 2,650 feet of water line at 85 cents per lineal foot, and approximately six manholes at $80 each, with payment of 50 percent upon completion of the work, and the balance January 1, 1931. Payment was guaranteed by Agnes McG. Hice and Dwight M. Allison, who were, respectively, the president and secretary of the land company.

Ascertaining that the trench for the sewer, water, and manholes woulcf have to be deeper, a supplementary contract was entered into between the parties in May 1930, providing for the payment of 15 cents per lineal foot for each additional foot of depth, and $10 for each additional foot of excavation and construction of manholes, payment to be made in the manner and at the times specified in the original contract. Payment for this extra excavating was also guaranteed by Mrs. Hice and Mr. Allison.

From May 5, 1930, to August 4, 1930, extra work was done and material furnished by Markley which was not within the contracts payment of which had been guaranteed by Mrs. Hice and Mr. Allison. The charge for this extra work and material was $874.70, of which $82.50 was admitted to be within the guaranties.

The account of Mr. Markley, as put into evidence by his executrix, appears to have been made up by his bookkeeper, at his dictation, on or about December 31,1930, and is, in part, as follows:

[527]*527Contract signed April 26,1930.

Laying sewer and water lines, per contract

8" sewer line, 3316 ft. at $1.00. . $3,316.00

Extra sewer depth............ 585.60

6 Manholes, at $80.00.......... 480.00

4" Water line, 3427 ft. at 85‡.... 2,912.95

$7,294.55

Extra Time and'Material charges at cost, plus

15%, except shovel straight $5.50

per hour................ 536.25

(This is broken down into hours from May 5 to August 4, 1930)

Extra time and material on water line...... 214.30

Plus 15%.. 32.12

2 hrs. shovel @ 5.50. 11.00 257.45

Extra work on sewer line ............. 26.09

Plus 15%.. 3.91

Truck hauling sewer & water line 7.00 -81.00

Total Extra Time & Material and Shovel. . . 874.70

Total . . $8,169.25

The account showed credits as follows:

July 29,1930, cash............. 500.00

July 31, “ “ 2,000.00

(( Jany 20,1931 1,500.00

[528]*528Feby 2,1931. 1,500.00

“ 11, “ 1,000.00

March 2, “ 300.00

July 23 “ Dec 9, “ 400.00 200.00

Cash — April 13,1933. $20.00

“ 28, “ . 50.00

Nov. 7, “ . 20.00

Mar. 29,1934. 15.00

May 9, “ . 12.00

Sept. 1, “ . 25.00 142.00

Cash — May 25,1935. 20.00

July 8, “ . 20.00

Mar. 2,1936. 20.00

Oct. 2,1936. 20.00

Apr. 6,1937. 50.00 130.00

The record discloses no application by either the land company or S. B. Markley of the foregoing payments to any particular account, contract or item. The dates of the extra work done and materials furnished, as compared with the dates of the two first payments, total-ling $2,500, together with the heading of the account, “Contract Signed April 26, 1930”, conclusively establish that the first four items of the account, totaling $7,294.55, were items charged to the contracts payment of which was guaranteed by Dwight M. Allison and Agnes McG. Hice, upon which contracts of guaranty (surety) Emma G. Markley, executrix of Samuel B. Markley, deceased, brought the action in assumpsit now before us.

At the trial counsel for the defendants made a motion for a compulsory nonsuit at the close of the plaintiff’s case,.and we directed a verdict for the defendants, for the reason that the guaranteed debts were paid.

[529]*529(As to a directed verdict on a motion for a nonsuit we see no injury to the plaintiff. A new trial can be granted as readily as a nonsuit can be taken off, with no added expense or trouble. The only question was: Were the debts paid? If they were, that should be the end of all controversy. And it was conceded by counsel for both the plaintiff and the defendants that if the $874.70, less $82.50 for the extra work, was excluded from the liability of the guarantors more than $7,-294.55, plus $82.50, together with interest, had been paid to Markley by the land company. Nor was there any question of construction of the contracts of surety-ship. There were two contracts for specific work and charges, in neither of which could the extra work and material be included by any possible construction or interpretation, and were such possible, it would be negatived by plaintiff’s account. We have carefully considered Cancelmo’s Estate, 308 Pa. 178, and Brock’s Assigned Estate (No. 1), 312 Pa. 7, and find in them no application.)

The question for determination is the application of payments made without specific appropriation by either the debtor or creditor, as between secured or unsecured debts, or items in an account, as governed by the law of Pennsylvania.

As between debtor and creditor, a debtor may make specific application of payment to any debt or item he may designate; if the debtor fails to do this, then the creditor may make specific application of payment to any debt or item he may designate; if both the debtor and creditor fail to make specific application of payment, then the law, under equitable principles, makes application of payment as follows:

(а) To the oldest debt, or oldest or first item in an account, first applying such payment to accrued interest.

(б) To an unsecured or precarious debt.

[530]*530Both (a) and (6) are to be applied together, and in such manner as to be to the best interest of the creditor.

As between debtor and creditor, third parties have no rights as to the application of payment, except in certain circumstances of suretyship, as where the very purpose of the creation of the relationship of principal and surety is the insurance of payment to third parties, such as the bond in a construction contract conditioned that the contractor apply payments to him in liquidation of his obligations for labor and material. In such cases payment by the debtor to the creditor (contractor) must be applied first to the relief of the surety. See Columbia Digger Co. v. Sparks et al., 227 Fed. 780. This rule of application of payment first to the relief of a surety has a very limited and special application, and has no relation to the question before us.

Conflict arising in the application óf (a) and (5), as the same may affect the surety of the debtor, has been resolved as follows:

The law will apply payment to the oldest debt or item, and this regardless of whether such payment enures to the relief of a surety. The rule of application of payment to the interest of the creditor in the liquidation of unsecured or precarious debts or items has been set aside, in the interest of the surety, in cases where such surety is for the oldest debt or item. Pardee v. Markle, 111 Pa.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Kirkpatrick
22 U.S. 720 (Supreme Court, 1824)
Cancelmo's Estate
162 A. 454 (Supreme Court of Pennsylvania, 1932)
Brock's Assigned Estate (No. 1)
166 A. 778 (Supreme Court of Pennsylvania, 1933)
Page v. Wilson
28 A.2d 706 (Superior Court of Pennsylvania, 1942)
Pierce v. Sweet
33 Pa. 151 (Supreme Court of Pennsylvania, 1859)
Johnson's Appeal
37 Pa. 268 (Supreme Court of Pennsylvania, 1860)
Hollister v. Davis
54 Pa. 508 (Supreme Court of Pennsylvania, 1867)
Foster v. McGraw
64 Pa. 464 (Supreme Court of Pennsylvania, 1870)
Woods v. Sherman
71 Pa. 100 (Supreme Court of Pennsylvania, 1872)
Garrett's Appeal
100 Pa. 597 (Supreme Court of Pennsylvania, 1882)
Pardee v. Markle
5 A. 36 (Supreme Court of Pennsylvania, 1886)
Bell v. Clark
38 Pa. Super. 365 (Superior Court of Pennsylvania, 1909)
Berghaus v. Alter
9 Watts 386 (Supreme Court of Pennsylvania, 1840)
Speck v. Commonwealth
3 Watts & Serg. 324 (Supreme Court of Pennsylvania, 1842)
McKee's v. Commonwealth
2 Grant 23 (Supreme Court of Pennsylvania, 1853)
Arbuckles & Co. v. Chadwick
23 A. 346 (Alleghany County Court of Common Pleas, 1892)
Columbia Digger Co. v. Sparks
227 F. 780 (Ninth Circuit, 1915)

Cite This Page — Counsel Stack

Bluebook (online)
47 Pa. D. & C. 525, 1943 Pa. Dist. & Cnty. Dec. LEXIS 429, Counsel Stack Legal Research, https://law.counselstack.com/opinion/markley-v-allison-pactcomplbeaver-1943.