Mark Sampson v. Dci of Alexandria, Inc.

CourtLouisiana Court of Appeal
DecidedOctober 31, 2007
DocketCA-0007-0671
StatusUnknown

This text of Mark Sampson v. Dci of Alexandria, Inc. (Mark Sampson v. Dci of Alexandria, Inc.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mark Sampson v. Dci of Alexandria, Inc., (La. Ct. App. 2007).

Opinion

STATE OF LOUISIANA COURT OF APPEAL, THIRD CIRCUIT 07-671

MARK SAMPSON AND ALFREDA COLEMAN SAMPSON

VERSUS

DCI OF ALEXANDRIA, ET AL ********** APPEAL FROM THE TENTH JUDICIAL DISTRICT COURT PARISH OF NATCHITOCHES, NO. 78,912 HONORABLE DEE A. HAWTHORNE, DISTRICT JUDGE

**********

J. DAVID PAINTER

********** Court composed of Oswald A. Decuir, Elizabeth A. Pickett, and J. David Painter, Judges.

AFFIRMED AS AMENDED. William F. Henderson Attorney at Law 910 Foisy Avenue Alexandria, LA 71301 Counsel for Defendant-Appellant DCI of Alexandria, Inc.

Mark L. Roberts McCoy, Roberts & Begnaud, Ltd. 300 St. Denis Street Natchitoches, LA 71457 Counsel for Plaintiff-Appellee Mark and Alfreda Sampson PAINTER, Judge.

Defendant, DCI of Alexandria (DCI), appeals the trial court’s judgment in

favor of the plaintiffs, Mark and Alfreda Sampson, in the amount of $45,495.95 and

the court’s denial of its reconventional demand for $20,906.28, representing the

balance allegedly due under a building contract.

FACTS AND PROCEDURAL HISTORY

On May 11, 2004, the parties entered a fixed-sum contract to build a house for

the Sampsons. Under the term of the contract DCI agreed, in exchange for

$90,000.00, to:

“furnish all LABOR, AND TOOLS necessary to construct proposed building according to plans and specifications, provided by owner as specified below:

FOR FOUNDATIONS, FRAMING AND TRIM OUT OF DWELLING

ALL MATERIAL AND EQUIPMENT ARE TO BE FURNISHED BY OWNER. All work to be completed in a workmanlike manner according to standard practices. ANY ALTERATION OR DEVIATION FROM ABOVE SPECIFICATIONS INVOLVING EXTRA COSTS WILL BE EXECUTED ONLY UPON WRITTEN CHANGE ORDERS, AND WILL BECOME AN EXTRA CHARGE OVER AND ABOVE THIS CONTRACT AMOUNT TO BE PAID 50% UPON ACCEPTANCE AND 50% UPON COMPLETION OF EACH CHANGE ORDER. The contractor shall guarantee his work for a period of (1) year from date of final acceptance by the owner. This condition does not invalidate longer periods of warranty for equipment furnished by the manufacturer with longer periods of warranty. It is agreed NO OCCUPANCY OF DWELLING SHALL BE PERMITTED UNTIL FINAL PAYMENT OF CONTRACT & ALL CHANGE ORDERS HAVE BEEN PAID IN FULL. All agreements are contingent upon strikes, accidents, or delays beyond our control. The Contractor will carry General Liability Insurance. Owner to carry fire, tornado, and other necessary insurances. Our workers are fully covered by Workmen’s Compensation Insurance.

The following is undisputed: Alfreda Sampson tried to buy builder’s risk

insurance as required by the contract but found the prices to be prohibitively high.

1 When she discussed this with Mike Dunn, sole shareholder and operator of DCI , he

offered to obtain the insurance for a better price. He obtained the policy, and the

Sampsons paid the premium. However, when Dunn obtained the policy he named

DCI as the beneficiary.

Construction began with building materials supplied by the Sampsons. On

September 28, 2004, DCI sent an invoice to the Sampsons showing charges as

follows:

Foundation in Place $22,500.00 Builders Risk Policy $ 910.00 Termite Company $ 1,153.77 Dirt Work $ 5,500.00 Concrete Finishers $ 4,391.00

The Sampsons made a payment of $30,063.77 on October 1, 2004, which did not

include payment of the amount for the concrete finishers, because the Sampsons felt

that the contract made DCI responsible for providing that service.

On November 23, 2004, a storm damaged or destroyed the partially constructed

house. DCI made a claim against the builder’s risk policy for damages in the amount

of $23,221.11. Dunn testified that the claim included amounts as follows:

Materials $ 5,709.00

Labor to remove and sort damaged materials $ 3,024.00

Labor to reframe roof $ 6,430.00

Overhead and supervision $ 3,350.00

Workers’ compensation and general liability insurance and taxes $ 3,456.00

Profit $ 2,201.92

2 These amounts were reduced by the policy deductible of $1,000.00. The insurance

company deducted the amount claimed as profit and sent a check for $21,019.19 to

DCI. DCI kept the proceeds of the insurance check.

DCI began rebuilding the house, but, on January 12, 2005, another storm

destroyed the house, which was eighty-seven percent complete according to DCI’s

claim. DCI again made a claim against the builders’s risk insurance for the following

amounts:

Materials $45,021.77

Labor $35,697.52

Insurances $10,341.57

Matching Funds $ 1,341.57

Supervision $ 9,000.00

Insurances on Supervision $ 619.26

Matching Funds on Supervision $ 688.00

Overhead (10%) $10,275.40

Profit $10,275.40

Demolition $ 5,756.00

DCI began rebuilding the house, and on May 23, 2005 sent the Sampsons an

invoice showing the following charges:

Framing labor $58,500.00 Concrete Finishers (not included in layout and forming labor) $ 4,391.00 Concrete Finishers for Patio $ 882.00 Lowes for windows $ 2,039.80 Stine Lumber wood for windows $ 310.46 Coburn Supply Stove Top & Chimney Hood $ 2,454.37 Payment Received $68,000.00

Final 10% Due Upon Completion $ 9,000.00

3 On May 31, 2005, the Sampsons paid $60,000.00 but, according to the

testimony of Mrs. Sampson, deliberately left out the amounts for the concrete

finishers. On July 20, 2005, they made another payment of $8,000.00.

The Sampsons were billed $29,800.00 in connection with the heating and air

conditioning installation. The parties do not dispute that this item was not covered

by the contract between the Sampsons and DCI. However, DCI hired the

subcontractor, paid them, and billed the Sampsons for the work. DCI admits that it

added a $6,000.00 mark-up to the bill for the subcontractor’s work.

After the second storm, while attempting to settle the insurance claim, DCI

filed a lien against the Sampsons for $150,557.71. The insurance company sent Dunn

a check in the amount of $117,528.74 made payable to Dunn and the mortgage

holder, Hancock Bank. The Sampsons filed a petition seeking cancellation of the

lien, damages and attorney’s fees for the wrongful filing of the lien, damages for

defective workmanship, reimbursement of the value of the salvage materials, and

reimbursement of an overpayment made to DCI by the builder’s risk insurer. DCI

filed a reconventional demand seeking to recover amounts allegedly still owed to it

under the building contract, as well as attorney’s fees.

After a trial on the merits, the court rendered judgment in favor of the

Sampsons in the amount of $45,495.95 plus costs and attorney’s fees. It further

denied DCI’s reconventional demands. The court gave extensive written reasons for

its decision. DCI appeals.

4 DISCUSSION

Insurance

We first consider the question of the ownership of the insurance policy and its

proceeds as this will determine whether DCI has received full payment. DCI asserts

that the trial court erred in finding that the builder’s risk policy covered the Sampsons

and that the Sampsons still owed money on the original contract. It argues that the

trial court improperly reformed the policy to make it payable to the Sampsons where

DCI was the named beneficiary. The trial court found that the insurance proceeds

belonged to the Sampsons and that they were the actual and intended beneficiaries of

the policy. After reviewing the evidence of record, we conclude that Dunn and/or

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Hagerty
205 So. 2d 369 (Supreme Court of Louisiana, 1967)
Federal Deposit Insurance Corp. v. Caplan
874 F. Supp. 741 (W.D. Louisiana, 1995)
Plaquemines Par. Com'n Council v. Delta Dev. Co.
502 So. 2d 1034 (Supreme Court of Louisiana, 1987)
Noe v. Roussel
310 So. 2d 806 (Supreme Court of Louisiana, 1975)
Toombs v. Daniels
361 N.W.2d 801 (Supreme Court of Minnesota, 1985)
Scheffler v. Adams and Reese, LLP
950 So. 2d 641 (Supreme Court of Louisiana, 2007)
Beckstrom v. Parnell
730 So. 2d 942 (Louisiana Court of Appeal, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
Mark Sampson v. Dci of Alexandria, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/mark-sampson-v-dci-of-alexandria-inc-lactapp-2007.