Mark Javery v. Charles Bolden, Jr.

697 F. App'x 810
CourtCourt of Appeals for the Fifth Circuit
DecidedJune 21, 2017
Docket16-60221 Summary Calendar
StatusUnpublished
Cited by1 cases

This text of 697 F. App'x 810 (Mark Javery v. Charles Bolden, Jr.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mark Javery v. Charles Bolden, Jr., 697 F. App'x 810 (5th Cir. 2017).

Opinion

PER CURIAM: *

Mark Javery and Brian Dejan filed administrative complaints pursuant to the Federal Acquisition Streamlining Act, 10 U.S.C. § 2409, with the National Aeronautics and Space Administration (NASA) after being terminated by Lockheed Martin (Lockheed) and its subcontractor Camgian Microsystems, Inc. (Camgian), respectively. They alleged that they were unlawfully terminated because they made protected disclosures regarding Lockheed’s performance of its contract with NASA. The NASA Administrator denied their claims. Javery and Dejan petition this court for review of the Administrator’s decision. We affirm.

I

Javery, an employee of Lockheed, and Dejan, an employee of Lockheed’s subcontractor Camgian, were terminated from their respective positions working on a Lockheed contract with NASA. They subsequently filed administrative complaints with the NASA Office of Inspector General (OIG), alleging they were unlawfully termi *812 nated because they made disclosures, protected under 10 U.S.C. § 2409, regarding Lockheed’s performance of the contract. Javery and Dejan contended they reported that preventative maintenance funds were being used to perform non-maintenance work, wrongdoing referred to as “misc-harging.”

OIG investigated the complaints and determined that Javery and Dejan made “disclosures of substantial violations of Federal law or regulation relating to a NASA contract” that were protected from reprisal under § 2409, and that those disclosures were a “contributing factor” in Lockheed’s decision to terminate Javery as well as its request that Camgian remove Dejan from the contract’s project. Camgi-an did remove Dejan and subsequently terminated him. OIG specifically rioted that the 2008 version of § 2409, which Congress amended in 2013, applied to the complaints filed by Javery and Dejan. Although OIG recognized that the 2008 version does not refer to the type of disclosures OIG maintains Javery and Dejan made, it concluded that “this [omission] was a drafting error” by Congress and the disclosures at issue qualified for. protection nonetheless.

OIG transmitted its report of findings (OIG Report) to the NASA Administrator, whom § 2409 authorizes to make the final determination regarding claims of reprisal. 1 NASA provided copies of the OIG Report to all parties and requested that Lockheed submit a written response to the OIG Report. It also invited Javery and Dejan to submit a reply to Lockheed’s response. The parties complied.

In its response, Lockheed “strenuously disagree[d]” with OIG’s findings, contending that no protected disclosures were made and that Javery and Dejan were terminated due to poor job performance. Lockheed challenged a variety of OIG’s factual findings and asserted that the 2008 version of § 2409 does not provide protection for the type of alleged disclosures Javery and Dejan made to NASA. Specifically, Lockheed noted that the 2008 statute does not include “substantial violations of Federal law or regulation relating to a NASA contract” in its language, the type of disclosure the OIG report concluded Javery and Dejan had made.

Javery and Dejan submitted a reply to NASA. They challenged Lockheed’s description of the facts and urged the NASA Administrator to take corrective action on their behalf. In the section of their reply titled the “law of the case,” Javery and Dejan quoted from the 2013 version of § 2409, but failed to challenge Lockheed’s assertion that the 2008 statute did not protect their disclosures to NASA. They also failed to argue that the 2013 version— which potentially protected the type of disclosures allegedly made—applied, rather than the 2008 version previously applied by OIG.

The NASA Administrator concluded that the 2008 statute applied and that the alleged disclosures were not protected under it. He denied relief. The Administrator reasoned that the 2008 language was plain and the result it required not absurd. Both the OIG Report and Lockheed had asserted that the 2008 statute governed, and the Administrator rioted that Javery and De-jan did not challenge the application of that version of the statute. Nor did they contest that the alleged disclosures are not protected under the 2008 statute. The Administrator also concluded that the alleged disclosures “concerned potential cost misc-harging, as opposed to ‘a substantial and specific danger to public health or safe *813 ty,’ ” the only category of disclosure in the 2008 version that applied to non-DOD contracts. The Administrator thus concluded that the findings and conclusions in the OIG Report did not establish “a sufficient basis” for a reprisal claim under § 2409.

II

Pursuant to § 2409 and the Administrative Procedure Act (APA), we may overturn the Administrator’s determination only if it is “arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law.” 2 We review the Administrator’s legal conclusions de novo, 3 giving deference to his interpretation of the statute as appropriate. 4 Although courts remain “the final authorities on issues of statutory construction” and “must reject administrative constructions of [a] statute ... that are inconsistent with the statutory mandate,” 5 “[i]f the agency interpretation is not in conflict with the plain language of the statute, deference is due.” 6

Ill

The Administrator’s final determination was not arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law. The 2008 statute does not provide protection for the type of disclosures allegedly made by Javery and De-jan, and we cannot conclude that the Administrator’s determination, consistent with the plain language of the statute, failed to satisfy the arbitrary and capricious standard.

The Administrator correctly applied the 2008 version of § 2409, rather than the 2013 version. The parties do not appear to dispute that the 2008 version of the statute applies to the instant case. Congress directed that the 2013 amendments to § 2409 apply to contracts awarded 180 days after enactment of the revised language. 7 Alternatively, contracts entered *814 into before the 2013 amendments went into effect could be modified to apply the new provisions, 8 The Lockheed contract was awarded on November 16, 2010, and was not modified to include the 2013 provisions until October 13, 2014, after Javery and Dejan were terminated. Thus, neither the contract date nor the date of modification provides a basis for applying the 2013 provisions,

We next consider the Administrator’s interpretation of the 2008 version of the statute. The 2008 statute provides, in pertinent part,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
697 F. App'x 810, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mark-javery-v-charles-bolden-jr-ca5-2017.