Mark Herman v. Gregory Asquith

CourtMichigan Court of Appeals
DecidedAugust 17, 2023
Docket362570
StatusUnpublished

This text of Mark Herman v. Gregory Asquith (Mark Herman v. Gregory Asquith) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mark Herman v. Gregory Asquith, (Mich. Ct. App. 2023).

Opinion

If this opinion indicates that it is “FOR PUBLICATION,” it is subject to revision until final publication in the Michigan Appeals Reports.

STATE OF MICHIGAN

COURT OF APPEALS

MARK HERMAN, doing business as MDH UNPUBLISHED CONSTRUCTION, August 17, 2023

Plaintiff-Appellant,

v No. 362570 Muskegon Circuit Court GREGORY T. ASQUITH, LC No. 2020-004633-CK

Defendant-Appellee, and

ALLEGHENY CASUALTY CO.,

Defendant.

Before: YATES, P.J., and BORRELLO and PATEL, JJ.

PER CURIAM.

In this action involving claims for foreclosure of a construction lien and breach of contract, plaintiff Mark Herman, doing business as MDH Construction, appeals as of right the trial court’s order dismissing the case for lack of jurisdiction. For the reasons set forth in this opinion, we affirm in part, reverse in part, and remand for further proceedings.

I. FACTUAL BACKGROUND

This case stems from a dispute over payment for stone retaining walls that Herman built for defendant Gregory Asquith on Asquith’s property. Herman is a builder, contractor, and “hardscaper.” He explained that his hardscaping work involved setting brick, block, and stone into landscaping and that he worked on lakefront properties, terraces, patios, fire pits, and retaining walls. In October 2019, Herman provided Asquith with a quote to build stone retaining walls on Asquith’s property for $12,000, with $6,000 to be paid at the outset and the remainder to be paid upon completion of the project. Herman testified that Asquith called him to accept the quote and to discuss scheduling.

-1- On November 1, 2019, Herman arrived on Asquith’s property to begin work on the project and, according to Herman, Asquith presented him with a written agreement to sign. The parties stipulated that this agreement was drafted by Asquith and was executed by both Herman and Asquith. According to Herman, the plan for the project evolved during the course of construction through verbal discussions between Herman and Asquith. There were no written change orders. Asquith testified that the changes to the plan were actually the result of mistakes Herman made during construction. Asquith further testified that he did not agree to all of the changes that Herman made.

Herman testified that he finished the project on approximately December 1, 2019, and that Asquith did not pay him the remaining $6,000 balance. Herman believed that he completed the work for which Asquith contracted. Asquith testified, however, that he contacted Herman and told him that there were still issues to fix and portions of the project to complete. On January 23, 2020, Herman filed a claim of construction lien on the subject real property for $6,000 with the Muskegon County Register of Deeds.

II. PROCEDURAL HISTORY

Herman subsequently initiated this action in the circuit court for foreclosure of the construction lean and breach of contract. In the complaint, Herman alleged that Asquith owed him $6,000, plus interest, for the work he performed on Asquith’s property and that he had complied with all of the requirements of the Construction Lien Act (CLA), MCL 570.1101 et seq. Herman sought an order from the trial court determining that Herman had a valid lien on the property, superior to other claims, and further ordering the property to be sold to satisfy Herman’s claim. In his breach-of-contract claim, Herman alleged that he had performed all of his obligations under the contract and that Asquith had refused to pay the outstanding $6,000 that was due pursuant to the contract. With respect to this count, Herman sought a judgment for $6,000 plus interest, costs, and attorney fees.

Asquith filed a counterclaim alleging that Herman breached the contract by failing to construct the walls in conformance with the plan, abandoning the project before installing all of the stone and completing all backfilling and soil compacting, and “constructing the base of the wall at the wrong elevation so as to contour with the adjacent property owners.” Asquith sought judgment “in an amount exceeding $25,000.00, together with costs, interest, attorney fees as provided by statute, and such other relief as may be agreeable to equity and good conscience.”

The matter was initially assigned to Judge Timothy Hicks, who was nearing the end of his tenure on the bench as trial approached. Eventually, a bench trial was held before visiting Judge Charles Johnson. Following the trial, Judge Johnson issued a written opinion finding by preponderance of the credible evidence that Herman properly performed under the contract and was entitled to the remaining $6,000 of the contract price from Asquith. Judge Johnson entered a judgment of no cause of action on Asquith’s counterclaim, finding that Herman did not breach the contract. As particularly relevant to the issues on appeal, Judge Johnson stated in his opinion:

At the beginning of the trial, the Court and counsel discussed and agreed upon the need for briefing on the issue of whether Plaintiff is entitled to a construction lien remedy, in the event of a ruling in his favor on liability. As the

-2- Court so rules herein, Plaintiff’s counsel shall file his brief within 14 days from the date of this Opinion. Defendant’s response brief is due 14 days thereafter.

The parties submitted their respective briefs, and the case was reassigned to Judge Kenneth Hoopes, who succeeded Judge Hicks. Judge Hoopes subsequently issued a written opinion and order dismissing the case for lack of “jurisdiction.” Judge Hoopes framed the issue as follows:

In its order of March 10, 2022, the court found that Herman is entitled to the balance, which is $6000. That amount is below the monetary threshold for this court’s jurisdiction. See MCL 600.8301(1). Thus, this court only has jurisdiction over this matter if Herman has an enforceable lien. See MCL 600.601(1). Therefore, the court asked the parties for briefs on the question of whether the lien is enforceable lien [sic].

Judge Hoopes found that the parties’ contract failed to comply with the requirements in MCL 570.1114 that all amendments must be in writing and regarding the inclusion of language stating the trades for which a license was required. Consequently, Judge Hoopes concluded: “the court finds that Herman does not have a valid construction lien and dismisses this case for lack of jurisdiction.” The trial court denied reconsideration. This appeal followed.

III. STANDARD OF REVIEW

This Court reviews de novo, as questions of law, whether a court has subject-matter jurisdiction and whether the trial court properly applied this state’s statutes and court rules. Meisner Law Group PC v Weston Downs Condo Ass’n, 321 Mich App 702, 725; 909 NW2d 890 (2017); New Products Corp v Harbor Shores BHBT Land Dev, LLC, 308 Mich App 638, 644; 866 NW2d 850 (2014). “A trial court is duty-bound to recognize the limits of its subject-matter jurisdiction, and it must dismiss an action when subject-matter jurisdiction is not present.” Meisner Law Group, 321 Mich App at 714.

IV. ANALYSIS

Here, the trial court concluded that it lacked “jurisdiction” over the entire action based on its determination that Herman’s construction lien was unenforceable and the amount that Asquith owed Herman under the contract was below the circuit court’s jurisdictional minimum.

MCL 600.601(1) provides that the

circuit court has the power and jurisdiction that is any of the following:

(a) Possessed by courts of record at the common law, as altered by the state constitution of 1963, the laws of this state, and the rules of the supreme court.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Solution Source, Inc. v. LPR Associates Ltd. Partnership
652 N.W.2d 474 (Michigan Court of Appeals, 2002)
Dane Construction, Inc v. Royal’s Wine & Deli, Inc
480 N.W.2d 343 (Michigan Court of Appeals, 1991)
Altman v. Nelson
495 N.W.2d 826 (Michigan Court of Appeals, 1992)
Alan Custom Homes, Inc v. Krol
667 N.W.2d 379 (Michigan Court of Appeals, 2003)
Fradco, Inc. v. Department of Treasury
495 Mich. 104 (Michigan Supreme Court, 2014)
New Products Corporation v. Harbor Shores Bhbt Land Development
866 N.W.2d 850 (Michigan Court of Appeals, 2014)
Ronnisch Construction Group, Inc v. Lofts on the Nine, LLC
886 N.W.2d 113 (Michigan Supreme Court, 2016)
the Meisner Law Group v. Weston Downs Condominium Association
909 N.W.2d 890 (Michigan Court of Appeals, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
Mark Herman v. Gregory Asquith, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mark-herman-v-gregory-asquith-michctapp-2023.