Mark Hawks and Design Consultants, Inc. v. CD Development, LLC and Chris Davis

CourtCourt of Appeals of Tennessee
DecidedSeptember 25, 2013
DocketW2013-00499-COA-R3-CV
StatusPublished

This text of Mark Hawks and Design Consultants, Inc. v. CD Development, LLC and Chris Davis (Mark Hawks and Design Consultants, Inc. v. CD Development, LLC and Chris Davis) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mark Hawks and Design Consultants, Inc. v. CD Development, LLC and Chris Davis, (Tenn. Ct. App. 2013).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE AT JACKSON Submitted on Briefs on August 20, 2013

MARK HAWKS and DESIGN CONSULTANTS, INC. v. CD DEVELOPMENT, LLC and CHRIS DAVIS

Appeal from the Circuit Court of Madison County No. CO8292 Roy B. Morgan, Jr., Judge

No. W2013-00499-COA-R3-CV - Filed September 25, 2013

This appeal involves the tolling of the statute of limitations for a breach of contract. The plaintiff architect rendered services to the defendant real estate developer, and the developer failed to pay for the architect’s services. Approximately four years later, the architect recorded a lien against the real property to secure the indebtedness. The developer then promised the architect he would pay the indebtedness if the architect released the lien. The architect released the lien but still was not paid. Approximately four years after that, the architect filed this lawsuit against the developer to collect the debt. The developer asserted that the architect’s claim was barred by the six-year statute of limitations. After a trial, the trial court held that the statute of limitations was tolled under the doctrine of equitable estoppel, so the architect’s lawsuit was timely filed. The trial court entered a judgment in favor of the architect. The developer appeals only on the issue of whether the claim was time-barred. Discerning no error, we affirm.

Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Circuit Court is Affirmed

H OLLY M. K IRBY, J., delivered the opinion of the Court, in which A LAN E. H IGHERS, P.J., W.S., and J. S TEVEN S TAFFORD, J., joined.

Andrea Sipes Lester, Jackson, Tennessee, for the Defendant/Appellants, Chris Davis and/or CD Development, LLC

Lanis L. Karnes and Christopher G. Covellis, Jackson, Tennessee, for the Plaintiff/Appellees, Mark Hawks and Design Consultants, Inc. OPINION

F ACTS AND P ROCEDURAL H ISTORY

Plaintiff/Appellee Mark Hawks is a certified architect, employed by his own design firm, Plaintiff/Appellee Design Consultants, Inc. In 1998 and 1999, Mr. Hawks was hired by Defendant/Appellant Chris Davis and Mr. Davis’s now-defunct development company, Defendant/Appellant CD Development LLC, to perform architectural services.

The projects for which Mr. Hawks was hired included Mr. Davis’s development of a restaurant, the Peking Restaurant. While Mr. Hawks was working on the Peking Restaurant project, the parties signed a written contract setting forth the fee due from Mr. Davis for Mr. Hawks’ services and providing for interest of 1.5% per month on unpaid amounts. On April 23, 1999, pursuant to the contract, Mr. Hawks presented Mr. Davis with an invoice for the work on the Peking Restaurant project, totaling $17,246.32. Mr. Davis did not pay Mr. Hawks’ invoice.

In the years that followed, Mr. Hawks spoke to Mr. Davis on a number of occasions, and in fact they continued to work together on other projects. Still no payment for Mr. Hawks’ work on the Peking Restaurant project ever materialized.

In August 2003, after Mr. Hawks heard that Mr. Davis planned to sell the development that included the Peking Restaurant, Mr. Hawks filed a lien on the property for an amount that exceeded $60,000, for Mr. Hawks’ unpaid services. Shortly after filing the lien, Mr. Hawks spoke to Mr. Davis about it. Mr. Hawks also received a faxed letter from Mr. Davis’s attorney that indicated Mr. Davis would pay Mr. Hawks if he released the lien to allow the sale of the development to proceed. Expecting payment from Mr. Davis, Mr. Hawks released the lien. However, Mr. Hawks never received the promised payment.

Several years later, on September 26, 2008, Mr. Hawks filed the instant lawsuit against Mr. Davis and his development company in the Circuit Court of Madison County, Tennessee. The lawsuit alleged breach of the parties’ contract and sought damages plus pre-judgment interest, post-judgment interest, and the costs of collection. The amended answer filed by Mr. Davis asserted, inter alia, that Mr. Hawks’ action was time-barred under the applicable statute of limitations.1 Discovery and various delays ensued.

1 The amended answer also asserted a third-party complaint against Home Banking Company. The third-party complaint is not at issue in this appeal.

-2- The trial court conducted a bench trial on November 1, 2012. The trial court heard testimony from Mr. Hawks, Mr. Davis, and Charles Patterson, the attorney who sent the letter to Mr. Hawks regarding the lien. The trial court also heard telephone conversations between Mr. Hawks and Mr. Davis, recorded by Mr. Hawks without Mr. Davis’s knowledge.

At the conclusion of the trial, the trial court rendered an oral ruling in favor of Mr. Hawks. The trial court found that the parties had a valid contract, breached by Mr. Davis on April 23, 1999. Addressing why the lawsuit was not barred by the six-year statute of limitations for such a claim, the trial court held that Mr. Davis was estopped from asserting the statute of limitations or, in the alternative, the statute of limitations was tolled. Citing the parties’ testimony, the recorded telephone conversations, and the letter to Mr. Hawks from attorney Patterson, the trial court made factual findings that, in 2003, Mr. Davis promised Mr. Hawks that he would pay for Mr. Hawks’ work on the Peking Restaurant project if Mr. Hawks released the lien he had placed on the property. The trial court found that the letter to Mr. Hawks from attorney Patterson, on behalf of Mr. Davis, likewise promised payment to Mr. Hawks on the Peking Restaurant project. Mr. Hawks released the lien in reasonable reliance on these promises, the trial court found. Based on these factual findings, the trial court held that Mr. Hawks’ complaint was not time-barred.

On January 16, 2013, the trial court entered a written order awarding judgment in favor of Mr. Hawks in the amount of Mr. Hawks’ original invoice, $17,246.32, plus 1.5% interest per month as per the contract, plus pre-judgment interest back to the date the lawsuit was filed, plus post-judgment interest. The order declined Mr. Hawks’ request for his attorney fees and assessed costs against Mr. Davis. The written order attached a transcript of the trial court’s oral ruling setting forth its findings of fact and conclusions of law. From this order, Mr. Davis now appeals.

I SSUE ON A PPEAL AND S TANDARD OF R EVIEW

On appeal, Mr. Davis argues that the trial court erred in holding that the complaint is not barred by the statute of limitations.

Because this matter was decided by the trial court without a jury, the trial court’s findings of fact are reviewed de novo on the record, with a presumption that those findings are correct unless the evidence preponderates otherwise. Tenn. R. App. P. 13(d). For the evidence to preponderate against the trial court’s factual finding, it must support another finding of fact with greater convincing effect. Walker v. Sidney Gilreath & Assocs., 40 S.W.3d 66, 70–71 (Tenn. Ct. App. 2000); Realty Shop v. RR Westminster Holding., 7 S.W.3d 581, 596 (Tenn. Ct. App. 1999)). The trial court’s conclusions of law are reviewed de novo, with no presumption of correctness. Nashville Ford Tractor, Inc. v. Great Am. Ins. Co., 194 S.W.3d

-3- 415, 424–25 (Tenn. Ct. App. 2005). It is also well settled that a trial court’s assessment of the witnesses’ credibility is entitled to great weight on appeal because the trial court saw and heard the witnesses testify; thus, we defer to the trial court’s assessment on credibility absent clear and convincing evidence to the contrary. C & W Asset Acquisition, LLC v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Norman Redwing v. Catholic Bishop for the Diocese of Memphis
363 S.W.3d 436 (Tennessee Supreme Court, 2012)
Walker v. Sidney Gilreath & Associates
40 S.W.3d 66 (Court of Appeals of Tennessee, 2000)
Realty Shop, Inc. v. RR Westminster Holding, Inc.
7 S.W.3d 581 (Court of Appeals of Tennessee, 1999)
C.A. Hobbs, Jr., Inc. v. David Brainard, Susan B. Reyes, and Carol B. Ham
919 S.W.2d 337 (Court of Appeals of Tennessee, 1995)
Finova Capital Corp. v. Regel
195 S.W.3d 656 (Court of Appeals of Tennessee, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
Mark Hawks and Design Consultants, Inc. v. CD Development, LLC and Chris Davis, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mark-hawks-and-design-consultants-inc-v-cd-develop-tennctapp-2013.