Judgment rendered June 30, 2021. Application for rehearing may be filed within the delay allowed by Art. 2166, La. C.C.P.
No. 53,957-CA
COURT OF APPEAL SECOND CIRCUIT STATE OF LOUISIANA
*****
MARK DOYLE Plaintiff-Appellant CONSTRUCTION, LLC
versus
DVR LA2, LLC, AND DVR Defendants-Appellees SHREVEPORT, LLC
Appealed from the First Judicial District Court for the Parish of Caddo, Louisiana Trial Court No. 612657
Honorable Craig O. Marcotte, Judge
McMICHAEL, MEDLIN, D’ANNA, Counsel for Appellant WEDGEWORTH & LAFARGUE, L.L.C. By: James C. McMichael, Jr. Mark E. Carter
JUSTIN P. SMITH Counsel for Appellees
Before STEPHENS, THOMPSON, and HUNTER, JJ. HUNTER, J.
The plaintiff, Mark Doyle Construction, LLC, appeals a summary
judgment in favor of the defendants, DVR LA2, LLC and DVR Shreveport,
LLC. The district court determined that plaintiff had not presented evidence
to raise an issue of fact as to whether additional payment was owed for the
work performed. For the following reasons, we affirm.
FACTS
In 2013, Shreveport Business Park, LLC (“SBP”), leased a portion of
the former General Motors automobile plant (“GM Plant”) and 437
adjoining acres. In 2016, SBP subleased 100,000 square feet of
office/processing space in the GM Plant and the acreage to DVR LA2, LLC,
and DVR Shreveport, LLC (collectively referred to as “DVR”). In April
2017, DVR and Mark Doyle Construction, LLC (“Doyle”), entered into an
agreement providing that Doyle would make parking area improvements at
the plant, including land clearing, site preparation and paving. The contract
stated that the two-phase project would consist of 75 unimproved acres in
Phase I and 115 unimproved acres in Phase II, a total of 190 acres. In
addition, section 15.7.4 of the contract provided that acceptance of final
payment “shall constitute a waiver of claims by the payee except those
previously made in writing” and identified as unsettled at the time of final
payment.
From April to July 2017, Doyle worked on 68 acres of the 75 acres
included in Phase I. During that time, Doyle submitted 34 invoices to DVR
seeking payment for work performed and expenses in the total amount of
$2,925,864.78. DVR paid each of those invoices in full. On July 24, 2017,
Doyle sent DVR an invoice marked “Final Payment for 45 acres at GM Plant in Shreveport” in the amount of $75,000. On that same date, DVR
wired the full amount of the invoice to Doyle, which accepted the payment.
In December 2017, the parties agreed to a second contract, which
provided that Doyle would finish work on 9 acres of parking that had been
partially completed in Phase I and develop an additional 24 unimproved
acres with new parking for a total price of $505,000. This second contract
was signed by the parties and contained an integration clause in section
1.1.2, stating that this contract “represents the entire and integrated
agreement between the parties hereto and supersedes prior negotiations,
representations or agreements, either written or oral.” The contract does not
refer to an agreement to pay for work already performed by Doyle or a
promise of future work regarding an additional 50 acres. While performing
the work described in the second contract, Doyle submitted weekly invoices
to DVR, which paid each invoice in full. Doyle was paid the full amount for
the work completed under the December 2017 contract.
In February 2018, Doyle sent an invoice to DVR seeking payment of
$1,206,854 for work allegedly completed by Doyle during the months of
April-June 2017, for which it had not been paid. DVR refused to pay and a
short time later, Doyle sent another invoice seeking payment of $1,390,256.
After DVR refused to pay, Doyle sent a third invoice, dated August 18,
2018, for the amount of $1,426,012. DVR denied that any amount was
owed and again declined to pay. Doyle then filed a statement of claim and
privilege in the public records of Caddo Parish to preserve its claims against
DVR for payment of the alleged indebtedness.
Subsequently, the plaintiff, Doyle, filed a petition alleging that
contrary to the parties’ agreements, DVR had failed to pay Doyle for the 2 work described in the disputed invoice and to provide Doyle with the
opportunity for additional work. DVR filed an answer and reconventional
demand alleging that Doyle’s statement of claim and privilege was not valid.
Following discovery, DVR filed a motion for summary judgment on the
grounds that Doyle had been paid for the work performed and that the
integration clause in the December 2017 contract superseded any prior
agreements between the parties. In its opposition, Doyle argued that issues
of genuine fact existed as to whether it intended to waive all claims against
DVR by submitting an invoice for final payment regarding 45 acres and
whether the parties intended the integration clause to apply to the prior
written contract and oral agreements.
After a hearing, the district court granted DVR’s motion for summary
judgment, finding that Doyle’s acceptance of final payment waived any
claims under the first contract and that the integration clause in the second
contract superseded any prior agreements by the parties. The district court
rendered summary judgment in favor of DVR, dismissing Doyle’s claims
and cancelling the statement of privilege. Doyle appeals the judgment.
DISCUSSION
We first address Doyle’s assignment of error alleging that the trial
court erred in finding insufficient evidence of an oral agreement by the
parties providing that Doyle would be paid for the work shown on the
disputed August 2018 invoice. After reviewing the trial court’s oral reasons
for judgment, we note that the court did not grant summary judgment based
on a finding of a lack of evidence of an oral agreement. Rather, the trial
court determined that even if there was evidence of an oral agreement by the
parties, Doyle had waived its claims by accepting final payment without 3 reserving in writing its rights to an unpaid amount and by signing the
subsequent contract, which superseded all prior oral or written agreements.
Thus, the assignment of error lacks merit.
Doyle contends the trial court erred in granting DVR’s motion for
summary judgment. Doyle argues there is a genuine issue of material fact as
to whether accepting payment for an invoice noted as “final payment for 45
acres” constitutes a waiver of its claim based on an oral agreement with
DVR.
Appellate courts review summary judgments de novo, using the same
criteria that govern the trial court’s consideration of whether summary
judgment is appropriate. Samaha v. Rau, 2007-1726 (La. 2/26/08), 977
So.2d 880; Argonaut Great Central Ins. Co. v. Hammett, 44,308 (La. App. 2
Cir. 6/3/09), 13 So.3d 1209, writ denied, 2009-1491 (La. 10/2/09), 18 So.3d
122. Summary judgment shall be rendered if the motion, memorandum and
supporting documents show there is no genuine issue as to material fact and
that the mover is entitled to judgment as a matter of law. La. C.C.P. art.
966(A)(3). A fact is “material” if it potentially ensures or precludes
recovery, affects a litigant’s ultimate success or determines the outcome of
the legal dispute. Van v. Ferrell, 45,977 (La. App. 2 Cir. 3/2/11), 58 So.3d
522.
Free access — add to your briefcase to read the full text and ask questions with AI
Judgment rendered June 30, 2021. Application for rehearing may be filed within the delay allowed by Art. 2166, La. C.C.P.
No. 53,957-CA
COURT OF APPEAL SECOND CIRCUIT STATE OF LOUISIANA
*****
MARK DOYLE Plaintiff-Appellant CONSTRUCTION, LLC
versus
DVR LA2, LLC, AND DVR Defendants-Appellees SHREVEPORT, LLC
Appealed from the First Judicial District Court for the Parish of Caddo, Louisiana Trial Court No. 612657
Honorable Craig O. Marcotte, Judge
McMICHAEL, MEDLIN, D’ANNA, Counsel for Appellant WEDGEWORTH & LAFARGUE, L.L.C. By: James C. McMichael, Jr. Mark E. Carter
JUSTIN P. SMITH Counsel for Appellees
Before STEPHENS, THOMPSON, and HUNTER, JJ. HUNTER, J.
The plaintiff, Mark Doyle Construction, LLC, appeals a summary
judgment in favor of the defendants, DVR LA2, LLC and DVR Shreveport,
LLC. The district court determined that plaintiff had not presented evidence
to raise an issue of fact as to whether additional payment was owed for the
work performed. For the following reasons, we affirm.
FACTS
In 2013, Shreveport Business Park, LLC (“SBP”), leased a portion of
the former General Motors automobile plant (“GM Plant”) and 437
adjoining acres. In 2016, SBP subleased 100,000 square feet of
office/processing space in the GM Plant and the acreage to DVR LA2, LLC,
and DVR Shreveport, LLC (collectively referred to as “DVR”). In April
2017, DVR and Mark Doyle Construction, LLC (“Doyle”), entered into an
agreement providing that Doyle would make parking area improvements at
the plant, including land clearing, site preparation and paving. The contract
stated that the two-phase project would consist of 75 unimproved acres in
Phase I and 115 unimproved acres in Phase II, a total of 190 acres. In
addition, section 15.7.4 of the contract provided that acceptance of final
payment “shall constitute a waiver of claims by the payee except those
previously made in writing” and identified as unsettled at the time of final
payment.
From April to July 2017, Doyle worked on 68 acres of the 75 acres
included in Phase I. During that time, Doyle submitted 34 invoices to DVR
seeking payment for work performed and expenses in the total amount of
$2,925,864.78. DVR paid each of those invoices in full. On July 24, 2017,
Doyle sent DVR an invoice marked “Final Payment for 45 acres at GM Plant in Shreveport” in the amount of $75,000. On that same date, DVR
wired the full amount of the invoice to Doyle, which accepted the payment.
In December 2017, the parties agreed to a second contract, which
provided that Doyle would finish work on 9 acres of parking that had been
partially completed in Phase I and develop an additional 24 unimproved
acres with new parking for a total price of $505,000. This second contract
was signed by the parties and contained an integration clause in section
1.1.2, stating that this contract “represents the entire and integrated
agreement between the parties hereto and supersedes prior negotiations,
representations or agreements, either written or oral.” The contract does not
refer to an agreement to pay for work already performed by Doyle or a
promise of future work regarding an additional 50 acres. While performing
the work described in the second contract, Doyle submitted weekly invoices
to DVR, which paid each invoice in full. Doyle was paid the full amount for
the work completed under the December 2017 contract.
In February 2018, Doyle sent an invoice to DVR seeking payment of
$1,206,854 for work allegedly completed by Doyle during the months of
April-June 2017, for which it had not been paid. DVR refused to pay and a
short time later, Doyle sent another invoice seeking payment of $1,390,256.
After DVR refused to pay, Doyle sent a third invoice, dated August 18,
2018, for the amount of $1,426,012. DVR denied that any amount was
owed and again declined to pay. Doyle then filed a statement of claim and
privilege in the public records of Caddo Parish to preserve its claims against
DVR for payment of the alleged indebtedness.
Subsequently, the plaintiff, Doyle, filed a petition alleging that
contrary to the parties’ agreements, DVR had failed to pay Doyle for the 2 work described in the disputed invoice and to provide Doyle with the
opportunity for additional work. DVR filed an answer and reconventional
demand alleging that Doyle’s statement of claim and privilege was not valid.
Following discovery, DVR filed a motion for summary judgment on the
grounds that Doyle had been paid for the work performed and that the
integration clause in the December 2017 contract superseded any prior
agreements between the parties. In its opposition, Doyle argued that issues
of genuine fact existed as to whether it intended to waive all claims against
DVR by submitting an invoice for final payment regarding 45 acres and
whether the parties intended the integration clause to apply to the prior
written contract and oral agreements.
After a hearing, the district court granted DVR’s motion for summary
judgment, finding that Doyle’s acceptance of final payment waived any
claims under the first contract and that the integration clause in the second
contract superseded any prior agreements by the parties. The district court
rendered summary judgment in favor of DVR, dismissing Doyle’s claims
and cancelling the statement of privilege. Doyle appeals the judgment.
DISCUSSION
We first address Doyle’s assignment of error alleging that the trial
court erred in finding insufficient evidence of an oral agreement by the
parties providing that Doyle would be paid for the work shown on the
disputed August 2018 invoice. After reviewing the trial court’s oral reasons
for judgment, we note that the court did not grant summary judgment based
on a finding of a lack of evidence of an oral agreement. Rather, the trial
court determined that even if there was evidence of an oral agreement by the
parties, Doyle had waived its claims by accepting final payment without 3 reserving in writing its rights to an unpaid amount and by signing the
subsequent contract, which superseded all prior oral or written agreements.
Thus, the assignment of error lacks merit.
Doyle contends the trial court erred in granting DVR’s motion for
summary judgment. Doyle argues there is a genuine issue of material fact as
to whether accepting payment for an invoice noted as “final payment for 45
acres” constitutes a waiver of its claim based on an oral agreement with
DVR.
Appellate courts review summary judgments de novo, using the same
criteria that govern the trial court’s consideration of whether summary
judgment is appropriate. Samaha v. Rau, 2007-1726 (La. 2/26/08), 977
So.2d 880; Argonaut Great Central Ins. Co. v. Hammett, 44,308 (La. App. 2
Cir. 6/3/09), 13 So.3d 1209, writ denied, 2009-1491 (La. 10/2/09), 18 So.3d
122. Summary judgment shall be rendered if the motion, memorandum and
supporting documents show there is no genuine issue as to material fact and
that the mover is entitled to judgment as a matter of law. La. C.C.P. art.
966(A)(3). A fact is “material” if it potentially ensures or precludes
recovery, affects a litigant’s ultimate success or determines the outcome of
the legal dispute. Van v. Ferrell, 45,977 (La. App. 2 Cir. 3/2/11), 58 So.3d
522. In ruling on a motion for summary judgment, the district court’s role is
not to evaluate the weight of the evidence or to determine the truth of the
matter, but instead to determine whether there is a genuine issue of triable
fact. Hines v. Garrett, 2004-0806 (La. 6/25/04), 876 So.2d 764.
A contract is an agreement by two or more parties whereby
obligations are created, modified or extinguished. La. C.C. art. 1906.
Contracts have the effect of law for the parties. La. C.C. art. 1983. When 4 the words of a contract are explicit and do not lead to absurd consequences,
no further interpretation may be made in search of the parties’ intent. La.
C.C. art. 2046.
In this case, Doyle asserts in its brief that while performing the work
described in the first written contract, Doyle made oral agreements with
DVR’s representative, Gallub, to perform additional work that was beyond
the scope of the written contract. In performing this additional work, Doyle
did not follow the practice of submitting invoices as the work progressed.
Vernon Thomas, Doyle’s supervisor at the GM Plant site, testified in his
deposition that Doyle stopped work at the site because DVR had run out of
money and needed to sign a new lease to obtain funding for the project.
Thomas stated that he was told by Gallub that DVR would pay Doyle for the
additional work in the second phase of the project after a lease was signed.
Even accepting Doyle’s argument that its claim for the additional
work was not waived by the acceptance of payment in July 2017, we must
consider the provisions of the parties’ subsequent written contract in
December 2017, providing that Doyle would perform work on a specified
number of acres for a set price. Article 1 of this contract states that it is the
“entire and integrated agreement between the parties hereto and supersedes”
prior written or oral representations or agreements.
Doyle contends the trial court erred in finding that the integration
clause in the second written contract applied to Doyle’s claims based on the
first written contract and the oral agreements. Doyle argues that the
integration clause does not supersede the first contract and prior oral
agreements because these agreements are separate and unique from the
December 2017 contract. 5 An integration clause, also known as a merger clause, is a contractual
provision stating that the contract represents the parties’ complete and final
agreement. Wall v. Bryan, 52,165 (La. App. 2 Cir. 6/27/18), 251 So.3d 650,
writs denied, 2018-1280, 2018-1270 (La. 11/5/18), 255 So.3d 1047, 1051.
An integration clause precludes any prior or contemporaneous agreements
which are not set forth in the contract. Wall v. Bryan, supra.
In the present case, the record shows that Doyle was able to review
the December 2017 contract that included the integration clause before
signing. However, although the contract includes a number of exhibits, such
as the scope of work and site plan, Doyle did not include any provision
requiring DVR to pay for the extra work performed pursuant to the alleged
prior oral agreement.
In Wall, supra, this court found that a subsequent settlement
agreement, which included an integration clause, explicitly stated the
parties’ intent that the settlement agreement superseded all prior agreements.
Similar to the situation in Wall, supra, in this case the language of the
integration clause explicitly sets forth the parties’ intent that the December
2017 contract superseded all prior written or oral agreements. The
December 2017 contract is the entire agreement between the parties and
makes no provision for payment to Doyle for the work described in the
disputed invoice. Thus, in signing the contract Doyle waived its claims
based on agreements made prior to execution of the contract in December
2017. The authority cited by Doyle in its brief does not support the position
that the integration clause is not applicable to its claims.
Based upon this record, we cannot say the trial court erred in
determining that the December 2017 contract superseded any prior oral and 6 written agreements on which Doyle based its claims. Consequently, the trial
court did not err in granting DVR’s motion for summary judgment. Thus,
the assignment of error lacks merit.
Because the record supports the summary judgment in favor of DVR
and the dismissal of Doyle’s claims, we conclude the trial court correctly
cancelled Doyle’s statement of claim and privilege based on the finding that
Doyle had failed to establish a valid claim to support the filing of the lien.
CONCLUSION
For the foregoing reasons, the trial court’s judgment is affirmed.
Costs of this appeal are assessed to the appellant, Mark Doyle Construction,
LLC.
AFFIRMED.