Marjorie Linder Cooley v. Federal Energy Regulatory Commission

843 F.2d 1464, 269 U.S. App. D.C. 136, 1988 U.S. App. LEXIS 4617, 1988 WL 31903
CourtCourt of Appeals for the D.C. Circuit
DecidedApril 12, 1988
Docket87-1249
StatusPublished
Cited by12 cases

This text of 843 F.2d 1464 (Marjorie Linder Cooley v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Marjorie Linder Cooley v. Federal Energy Regulatory Commission, 843 F.2d 1464, 269 U.S. App. D.C. 136, 1988 U.S. App. LEXIS 4617, 1988 WL 31903 (D.C. Cir. 1988).

Opinion

Opinion for the Court filed by Chief Judge WALD.

WALD, Chief Judge:

This is an appeal from a grant by the Federal Energy Regulatory Commission (FERC or the Commission) of a license to Clifton Power Corporation (Clifton) for the operation of a small hydroelectric plant on the Pacolet River, in Spartanburg County, South Carolina. The license is challenged by Marjorie Linder Cooley, the owner of a one-half acre strip of riparian land flooded by the project.

The principal issue in the case is whether the Commission may grant licenses under § 4(e) of the Federal Power Act (FPA or thé Act), 16 U.S.C. § 797(e), to voluntary applicants to operate hydroelectric plants constructed prior to 1935 on certain non-navigable streams, despite its inability to require such licenses under § 23(b) of the Act, 16 U.S.C. § 817. See Farmington River Power Co. v. FPC, 455 F.2d 86 (2d Cir.1972). We affirm the Commission’s authority under § 4(e) to grant such licenses. We also reject Cooley’s contention that the Commission committed numerous errors in determining that Clifton was a “fit” licensee. Despite some concerns about the Commission’s handling of this case, we find its licensing decision neither arbitrary nor capricious.

I. Background

In May, 1981, Clifton applied for a license from the FERC to operate an idle hydroelectric plant on the Pacolet River. Joint Appendix (J.A.) at 1-37. In July, Clifton began operating the project without a license and selling its electricity to Duke Power Company. Cooley then intervened in the license proceeding, claiming that Clifton’s project had flooded 16.4 acres of her land 1 and that Clifton had refused to negotiate a lease with her. J.A. at 38.

*1466 The Commission, in November, 1983, issued an order to show cause why Clifton should not stop operating its plant without the license apparently required by § 23(b). 2 J.A. at 175. In response, Clifton claimed, contrary to statements in its initial application, that both of the plant’s generators had been installed prior to 1935. If true, this fact would put the project outside the scope of § 23(b)’s requirements. 3

In June, 1985, the Commission terminated the show cause proceeding because of the substantial possibility that it did not have § 23(b) jurisdiction to require a license. 4 The FERC transferred the record of the show cause proceeding to the pending license proceeding. 5

Following a brief, unsuccessful attempt to obtain relief in South Carolina state court, Cooley supplemented her barrage of motions before the Commission with an action in federal district court seeking damages and injunctive relief for the flooding of her land. After an initial adverse ruling by the trial court, the Fourth Circuit held that Clifton had violated South Carolina statutory and common law by causing the water level of the Pacolet to rise six feet at Cooley’s lower property line. Cooley v. Clifton Power Corp., 747 F.2d 258 (4th Cir.1984). On remand, the district court awarded damages of $89.50 for the three-year rental value of that flooded land and injunction requiring Clifton to maintain its reservoir at a level below the elevation of Cooley’s land. Because of operational dif *1467 ficulties, 6 Clifton was unable to keep the water level below 588.3 feet above mean sea level, thereby violating the court’s order. J.A. at 233-34. In an enforcement proceeding, the district court ordered Clifton to either pay a $5,000 fine or monitor the elevation with whatever device or personnel was necessary to ensure compliance. As a result, Clifton installed monitoring equipment.

In the ongoing FERC license proceeding, Cooley suggested that the Commission dismiss Clifton’s application for lack of jurisdiction and, in the alternative, requested an evidentiary hearing on several matters regarding Clifton’s fitness as a license. 7 J.A. at 50-63. The FERC nonetheless issued the license, finding that it possessed the power under § 4(e) to grant licenses voluntarily sought, though not required under § 23(b); Clifton “may seek, but is not required to obtain, a license for its ... project.” J.A. at 67. The Commission also summarily rejected Cooley’s several concerns about Clifton’s fitness to be a licensee.

Cooley requested a rehearing on a number of grounds. She argued that § 4(e) of the Act does not confer any independent licensing authority on the Commission over and above § 23(b)’s requirements and also that the FERC erred in issuing the license without adequately addressing Clifton’s fitness. As an example, she pointed to its refusal to give sufficient weight to Clifton’s repeated violations of South Carolina law regarding river banks and beds. See 16 U.S.C. § 802(a)(2) (Supp.1986) (requiring license applicants to submit satisfactory evidence of compliance with state law).

Seven months after filing her rehearing request, Cooley submitted additional information alleging that Clifton had failed to meet a number of financial obligations; Clifton had defaulted on a loan agreement and failed to pay both federal and county taxes, and Spartanburg County had issued a tax execution and sold the property. J.A. at 125-38. 8

On May 5, 1987, after examining both her jurisdictional and fitness arguments, the Commission denied Cooley’s petition for rehearing. The Commission refused to consider her final post-hearing submission on the technical ground that it constituted a new request for rehearing filed outside the 30-day statute of limitations. See 16 U.S.C. § 825i (a).

Before this court, Cooley seeks review of the Commission’s orders granting the license to Clifton and denying her rehearing request. She reasserts her claim that § 4(e) does not give the FERC jurisdiction over voluntary license applicants and raises an amalgam of arguments why, even if the Commission does not have the power to issue a license, Clifton should be considered unfit to receive one.

II. Section 4(e) Jurisdiction

Cooley argues that the Commission does not have authority under § 4(e) to grant a license voluntarily sought by the operator of a project constructed prior to 1935 on nonnavigable waters.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
843 F.2d 1464, 269 U.S. App. D.C. 136, 1988 U.S. App. LEXIS 4617, 1988 WL 31903, Counsel Stack Legal Research, https://law.counselstack.com/opinion/marjorie-linder-cooley-v-federal-energy-regulatory-commission-cadc-1988.