Maritech Marine Services, LLC v. Bay Welding Services, Inc.

District Court, D. Alaska·Decided March 23, 2022·No. 3:20-cv-00231·Unknown

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF ALASKA

MARITECH MARINE SERVICES, LLC,

Plaintiff,

v. Case No. 3:20-cv-00231-SLG BAY WELDING SERVICES, INC.,

Defendant.

ORDER RE MOTION FOR SUMMARY JUDGMENT Before the Court at Docket 17 is Plaintiff Maritech Marine Services, LLC’s (“Maritech”) Motion for Summary Judgment or, in the Alternative, Partial Summary Judgment. Defendant Bay Welding Services, Inc. (“Bay Weld”) responded in opposition at Docket 29, to which Maritech replied at Docket 36. Oral argument was held on January 13, 2022. BACKGROUND This action stems from the alleged defective repair and modification of a 44- foot aluminum catamaran, the M/V Lightning, owned by Maritech, a vessel chartering company based in Anchorage, Alaska. Maritech alleges that Bay Weld, a custom boat manufacturer based in Homer, Alaska, negligently retrofitted the vessel with a defective control system, among other issues, which resulted in the vessel’s allision with a fuel dock in Cordova, Alaska.1 Maritech’s claimed damages include the net proceeds lost from a cancelled charter arrangement for the Lightning and the cost of hiring other contractors to investigate the control system

issues, complete additional work on the vessel, and repair damage from the allision.2 Maritech filed the instant motion on September 17, 2021, asserting that it is entitled to summary judgment on its claims for breach of contract, negligence, breach of the implied warranty of workmanlike performance, and violation of Alaska’s Unfair Trade Practices Act (“UTPA”).3 The parties agree that maritime

law applies to this case.4 The facts, viewed in the light most favorable to Bay Weld for purposes of this summary judgment motion, are as follows.5 In the fall of 2018, Brian Edmondson, the sole member of Maritech,6 approached Eric Engebretsen, the

1 See generally Docket 1. 2 See Docket 17 at 20–21. 3 Docket 17. 4 See Docket 1 at 2, ¶ 4; Docket 11 at 2, ¶ 4. 5 See Tolan v. Cotton, 572 U.S. 650, 657 (2014) (stating that for summary judgment, “a court must view the evidence ‘in the light most favorable to the opposing party’” (quoting Adickes v. S.H. Kress & Co., 398 U.S. 144, 157 (1970))). 6 Docket 17-1 at 1, ¶ 1 (Edmondson Decl.)

Case No. 3:20-cv-00231-SLG, Maritech Marine Services, LLC v. Bay Welding Services, Inc. Order re Motion for Summary Judgment Page 2 of 30 owner and operator of Bay Weld,7 about a remodel and upgrade of the Lightning.8 Mr. Engebretsen initially turned down the project based on lack of labor capacity but later informed Mr. Edmondson that Bay Weld could complete the project after

learning that contractor Mike Stockburger was available to provide assistance.9 After discussions with Mr. Edmondson regarding the scope of the project, Mr. Engebretsen drafted a cost estimate and explained the details of it to Mr. Edmondson.10 Following further discussions, Mr. Engebretsen produced an updated Cost/Work Proposal Estimate (“the Estimate”).11 Maritech signed the

Estimate in early December 2019, and Bay Weld began work on the Lightning shortly thereafter.12 According to Bay Weld, Mr. Engebretsen did not state or imply “that Bay Weld would certify that any component in the Lightning would function for a particular period of time,” and the Estimate does not contain such a certification.13

7 Docket 30 at 1, ¶ 1 (Engebretsen Aff.). 8 Docket 29 at 2 (citing Docket 30 at 2, ¶ 4 (Engebretsen Aff.)). 9 Docket 29 at 2–3 (citing Docket 30 at 2, ¶ 4 (Engebretsen Aff.)). 10 Docket 29 at 3 (citing Docket 30 at 3, ¶ 5 (Engebretsen Aff.)). 11 Docket 29 at 3 (citing Docket 30 at 3, ¶ 6 (Engebretsen Aff.); Docket 17-1 at 52–56 (Ex. 8)). 12 Docket 29 at 4 (citing Docket 30 at 4, ¶ 9 (Engebretsen Aff.)). 13 Docket 29 at 4 (citing Docket 30 at 4, ¶ 8 (Engebretsen Aff.); Docket 17-1 at 52–56 (Ex. 8)).

Case No. 3:20-cv-00231-SLG, Maritech Marine Services, LLC v. Bay Welding Services, Inc. Order re Motion for Summary Judgment Page 3 of 30 Moreover, while Mr. Edmondson and Mr. Engebretsen discussed a rough project completion timeline of spring 2020, they did not agree on a specific completion date, and no such deadline is specified in the Estimate.14 The Estimate contains

eighteen line items, three of which are relevant to the parties’ dispute: Items 4, 5, and 10. Item 4 provides that Bay Weld will “[u]pgrade UltraJet 340’s w/ full internal inspection.”15 According to Bay Weld, this provision “arose from Edmondson’s request for Bay Weld to ‘take a look at’ the jets while replacing the impellers.”16

Bay Weld determined that the Lightning’s bearings and bearing seals were in “good working condition” by looking for damaged or worn-out components when disassembling and reassembling the bearings, rotating the bearings to listen for noises indicating problems, and listening for noises during sea trials after the work on the Lightning was complete.17

Item 5 provides that Bay Weld will “[a]dd Glendinning Joystick controls w/ full electronic controls replacement and electronic steering system.”18 Before the

14 Docket 29 at 4–5 (citing Docket 30 at 4, ¶ 9 (Engebretsen Aff.); Docket 17-1 at 52–56 (Ex. 8)). 15 Docket 17-1 at 53 (Ex. 8). 16 Docket 29 at 4 (citing Docket 30 at 4, ¶ 10 (Engebretsen Aff.)). 17 Docket 29 at 4 (citing Docket 30 at 4–5, ¶ 11 (Engebretsen Aff.)). 18 Docket 17-1 at 53 (Ex. 8).

Case No. 3:20-cv-00231-SLG, Maritech Marine Services, LLC v. Bay Welding Services, Inc. Order re Motion for Summary Judgment Page 4 of 30 retrofit project, the Lightning had an existing functional Glendinning control system, which Bay Weld removed to install a new, modern system.19 Bay Weld worked directly with John Glendinning, the system’s manufacturer, to determine which

existing components of the original system could be integrated into the new system and which needed replacement.20 Item 5 also provides that Bay Weld’s work will include “complete controls and steering package for two stations and complete hydraulic system w/ dual pumps.”21 Bay Weld states that after discussing the original hydraulic system with

Mr. Glendinning, it determined that the “existing pumps functioned well and [were] an acceptable configuration” and thus chose to retain the pumps and integrate them into the new system.22 According to Bay Weld, “[t]he hydraulic system, including the pumps, functioned well upon delivery of the vessel.”23 Finally, Item 10 provides that Bay Weld will “[t]est and inspect all vessel systems.”24

19 Docket 29 at 6 (citing Docket 30 at 5–6, ¶ 12 (Engebretsen Aff.)). 20 Docket 29 at 6 (citing Docket 30 at 5–6, ¶ 12 (Engebretsen Aff.)). 21 Docket 17-1 at 53 (Ex. 8). 22 Docket 29 at 6–7 (citing Docket 30 at 6, ¶ 13 (Engebretsen Aff.)). 23 Docket 29 at 7 (citing Docket 30 at 6, ¶ 13 (Engebretsen Aff.)). 24 Docket 17-1 at 55 (Ex. 8).

Case No. 3:20-cv-00231-SLG, Maritech Marine Services, LLC v. Bay Welding Services, Inc. Order re Motion for Summary Judgment Page 5 of 30 Bay Weld completed its work on the Lightning in May 2019.25 Before delivering the Lightning to Maritech, Bay Weld tested the vessel’s systems in the water in Homer for over a week.26 Mr. Engebretsen, Mr. Stockburger, and Mr.

Glendinning were all present for the launch and initial testing of the Lightning.27 During the initial testing and calibration of the control system, the system’s joystick failed to properly respond to commands.28 Mr. Glendinning determined that the failure was due to a control system software issue and resolved the problem by upgrading the software.29 Mr. Engebretsen detected a different issue with the

control system involving “the bucket position sensors going into a dead zone and the control bucket becoming unresponsive,” which he and Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Maritech Marine Services, LLC v. Bay Welding Services, Inc., (D. Alaska 2022).

Maritech Marine Services, LLC v. Bay Welding Services, Inc. (Maritech Marine Services, LLC v. Bay Welding Services, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Stolt Achievement, Ltd. v. Dredge B.E. Lindholm
447 F.3d 360 (Fifth Circuit, 2006)
Adickes v. S. H. Kress & Co.
398 U.S. 144 (Supreme Court, 1970)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Cliff May v. Morganelli-Heumann & Associates
618 F.2d 1363 (Ninth Circuit, 1980)
Clevo Co. v. Hecny Transportation, Inc.
715 F.3d 1189 (Ninth Circuit, 2013)
Prince v. Thomas
25 F. Supp. 2d 1045 (N.D. California, 1997)
White Ex Rel. Estate of Bournakel v. Sabatino
526 F. Supp. 2d 1143 (D. Hawaii, 2007)
Tolan v. Cotton
134 S. Ct. 1861 (Supreme Court, 2014)
Poincon v. Offshr Mrne Contractors
9 F.4th 289 (Fifth Circuit, 2021)
Klamath Water Users Protective Ass'n v. Patterson
204 F.3d 1206 (Ninth Circuit, 1999)
Tug Blarney, LLC v. Ridge Contracting, Inc.
14 F. Supp. 3d 1255 (D. Alaska, 2014)
State v. Rock
380 P.3d 1084 (Court of Appeals of Oregon, 2016)