Marine Resource Development Foundation, Inc. v. Moore

121 So. 3d 1072, 2013 WL 3336865, 2013 Fla. App. LEXIS 10600
CourtDistrict Court of Appeal of Florida
DecidedJuly 3, 2013
DocketNo. 3D11-1218
StatusPublished

This text of 121 So. 3d 1072 (Marine Resource Development Foundation, Inc. v. Moore) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Marine Resource Development Foundation, Inc. v. Moore, 121 So. 3d 1072, 2013 WL 3336865, 2013 Fla. App. LEXIS 10600 (Fla. Ct. App. 2013).

Opinion

FERNANDEZ, J.

Marine Resources Development Foundation, Inc., etc. (“Foundation”), appeals the trial court’s entry of final summary judgment in favor of appellees Moore & Company, P.A. (“Firm”), Michael Moore, Esq. (“Moore”), and Erin Ackor, Esq. (“Ackor”) (collectively, “defendants”) involving claims for professional negligence. We reverse the final summary judgment because genuine issues of material fact exist regarding the sufficiency and clarity of the Firm’s legal advice to the Foundation, and whether its advice affected the Foundation’s decision to continue construction of the subject vessel.

This case arises out of the Firm’s representation of the Foundation, a non-profit entity engaged in marine education and research. Under its “donated boats program,” the Foundation raises funds by acquiring boats for below market-value, and then restores/repairs them and resells them for a profit. At the center of this dispute is a 120-foot, 1988 model aluminum yacht, the “Cajun Princess,” which the Foundation purchased in May of 2004. The Foundation received an initial loan for $4.5 million to cover the costs of purchase, restoration, and other fees from David Bo-gle, a private investor. The Foundation initially planned to refurbish the yacht so it could be sold for an estimated $7-9 million on the open market.

Plans for the project changed when, during the course of refurbishment, the marine architect employed by the Foundation discovered extensive corrosion on the boat’s superstructure.1 The Foundation then decided to rebuild the yacht to a more modern tri-deck configuration, which resulted in higher projected costs.

Another change in plans occurred after the yacht lost its coastwise privileges in the United States because it was flagged [1074]*1074as a foreign vessel.2 Consequently, the architect advised the Foundation that it would be more prudent to deconstruct and re-build the boat instead, and then pursue a new build determination (“NBD”)3 from the Naval Vessel Documentation Center (“NVDC”). This would nearly double the Foundation’s projected costs, but would substantially increase its value, which would allow the vessel to potentially be sold for up to $18 million.

Acting on this recommendation, the Foundation retained the Firm to obtain coastwise privileges for the yacht. Ackor, who was an associate at the Firm, worked with Moore, the Firm’s managing partner, on the file. The Firm, at the Foundation’s request, pursued a NBD to obtain the coastwise privileges. Ackor e-mailed the governing statute, 46 C.F.R. § 67.3 (2005), which states the standard for obtaining a NBD,4 to Rick Pineiro, the Vice President of the Foundation. Under the standard followed by NVDC when it grants “new vessel” status — which is notoriously difficult to meet — a “new vessel” is one which:

1) The hull and superstructure of which are constructed entirely of new materials; or
2) Which is constructed using structural parts of an existing vessel, which parts have been torn down so that they are no longer advanced to a degree which would commit them to use in the building of a vessel.

See 46 C.F.R. § 67.3 (2005) (emphasis added).

In her e-mail, Ackor also informed Pi-neiro that the Coast Guard’s “primary concern and critical factor when reviewing the applications [for NBD] is the extent to which the vessel was torn down to mere parts and then rebuilt.” Finally, it listed the documentation required to prove compliance with the statute and to be submitted with the NBD application.

Ackor sent the NBD application and documents to the NVDC. The Foundation included in its application a written statement and inboard profile that described the extent to which materials from the existing vessel were used in the construction, along with a sketch that identified, where practicable, the components of the old vessel. In other words, the Foundation’s written statement and inboard profile listed certain parts of the vessel that had not been completely torn down but rather re-used with extensive local repair.

The NVDC thereafter informed the Firm that the submission would not meet the definition of “new vessel” under 46 C.F.R. § 67.3. Ackor discussed the problems with the NBD application with Pinei-ro. Ackor also sent an email in which she requested more detailed reports and photos of the yacht so that further action could be taken on the NBD application. Pineiro testified that the Firm had a “very positive approach to the whole thing” with regard to whether a NBD would ultimately be obtained.

The Foundation held a board meeting in January of 2006 to decide whether to end [1075]*1075the rebuilding of the yacht or continue with the project. Pineiro, based on his belief that a NBD certification would be forthcoming, told the Board that the vessel was going to be “newly titled” and would, therefore, be more valuable if the Foundation completed the rebuild. Nevertheless, the Foundation requested that Pineiro cease work on the boat. Thereafter, Pinei-ro and Ron Hertel, a private investor, entered into a contract for Hertel to buy the yacht. Pineiro also secured an investment from Hertel in order to continue the yacht rebuild according to the new contract’s specifications. However, Hertel ultimately decided not to close on the contract, partly because he learned that the Cajun Princess was not a new vessel.

On November 20, 2006, Ackor sent a formal application for a NBD to the NVDC. However, the application was rejected in December of 2006. The NVDC noted that while the vessel did undergo substantial modifications, some parts of the boat’s hull were still intact and never torn down, and was therefore not “new” under § 67.3. The Firm subsequently met with the Foundation to review future options to obtain coastwise privileges. On January 5, 2007, the Firm appealed the NVDC’s denial of the NBD. The Foundation thereafter terminated the Firm.

Rear Admiral James A. Watson denied the appeal for the NBD on behalf of the NVDC in March of 2009. After the NBD denial, Bogle foreclosed the mortgage he held on the yacht and obtained a judgment against the Foundation. Bogle subsequently became the successful bidder and took possession of the yacht.

The Foundation subsequently filed a lawsuit against defendants for professional negligence, seeking economic damages in the form of profits it would have earned from the sale of the yacht had the NBD been obtained. Defendants moved for final summary judgment. The trial court denied defendants’ motion, stating that factual issues remained. Defendants then filed a motion for rehearing and reconsideration. The court ultimately reversed its prior ruling and entered final summary judgment in favor of defendants.

We agree with the Foundation that the trial court erred when it granted final summary judgment in favor of defendants, as there were genuine issues of material fact as to whether defendants were negligent in their representation of the Foundation. Summary judgment is proper only if no genuine issue of material fact exists and if the moving party is entitled to a judgment as a matter of law.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

New Bedford Dry Dock Co. v. Purdy
258 U.S. 96 (Supreme Court, 1922)
Palafrugell Holdings, Inc. v. Cassel
940 So. 2d 492 (District Court of Appeal of Florida, 2006)
Volusia County v. Aberdeen at Ormond Beach
760 So. 2d 126 (Supreme Court of Florida, 2000)
DAYTONA DEVELOPMENT CORP v. McFarland
505 So. 2d 464 (District Court of Appeal of Florida, 1987)
Riccio v. Stein
559 So. 2d 1207 (District Court of Appeal of Florida, 1990)
Shear v. Hornsby & Whisenand, P.A.
603 So. 2d 129 (District Court of Appeal of Florida, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
121 So. 3d 1072, 2013 WL 3336865, 2013 Fla. App. LEXIS 10600, Counsel Stack Legal Research, https://law.counselstack.com/opinion/marine-resource-development-foundation-inc-v-moore-fladistctapp-2013.