Marine Office of America Corp. v. Quarry Associates, Inc.

963 F. Supp. 1392, 1997 U.S. Dist. LEXIS 6589, 1997 WL 256065
CourtDistrict Court, E.D. Pennsylvania
DecidedMay 12, 1997
DocketCivil Action 95-2309
StatusPublished
Cited by3 cases

This text of 963 F. Supp. 1392 (Marine Office of America Corp. v. Quarry Associates, Inc.) is published on Counsel Stack Legal Research, covering District Court, E.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Marine Office of America Corp. v. Quarry Associates, Inc., 963 F. Supp. 1392, 1997 U.S. Dist. LEXIS 6589, 1997 WL 256065 (E.D. Pa. 1997).

Opinion

MEMORANDUM

RAYMOND J. BRODERICK, District Judge.

Presently before the Court in this declaratory judgment action are motions by both parties for summary judgment. Plaintiff Marine Office of America Corporation (“Marine”) issued a comprehensive general liability policy on behalf of Continental Insurance Company to building contractor J.E. Brenneman Company (“Brenneman”). Marine seeks a declaration that the insurance policy does not cover damages which may be awarded to Quarry Associates, Inc. (“Quarry”) in an action currently pending in the Delaware County Court of Common Pleas, captioned Quarry Associates v. J.E. Brenneman Company (Civil Action No. 88-13409). In that action, Quarry claims that Brenneman breached their contract and negligently installed foundation piles for Quarry’s building, causing the building’s foundation to settle four inches.

Marine, as attorneys in fact for Continental Insurance Company, instituted this declaratory judgment action against Quarry on April 19, The Court has diversity jurisdiction pursuant to 28 U.S.C. § 1332 (1993). On June 11, 1996, the Court denied Quarry’s motion to dismiss pursuant to Fed.R.Civ.P. 12(b)(7) for failure to join Brenneman as a necessary party. Marine Office of Am. Corp. v. Quarry Assocs., Inc., No. 95-2309, 1996 WL 325114 (E.D.Pa. June 11, 1996). At a subsequent pretrial conference, the parties indicated that there were few, if any, issues of material fact in dispute. Accordingly, the Court directed the parties to conduct discovery and submit a stipulation of facts and motions for summary judgment concerning the construction of the insurance policy.

The insurance policy at issue is a standard comprehensive general liability (“CGL”) policy covering “occurrences” as defined by the policy. The cross-motions for summary judgment raise the following two issues: (1) did an “occurrence” take place while the policy was in force providing coverage for Quarry’s claims against Brenneman?; and (2) do any policy exclusions limit coverage?

Because the Court has determined that Brenneman’s alleged negligence in driving *1394 the piles constitutes an “occurrence” during the policy period and that the policy exclusions exclude recovery for damage to work performed by Brenneman, declaratory judgment will be awarded as follows: in the event Brenneman is found negligent in the underlying state court action, Continental Insurance Company must pay the property damages awarded to Quarry which were proximately caused by Brenneman’s negligence, except for damages to the foundation piles installed by Brenneman.

I. FACTS

The parties have stipulated to the following material facts: Quarry Associates, Inc. owns property located at 740 South Chester Road in Swarthmore, Pennsylvania. Until the mid-1960’s, the property had been the site of a stone quarry. After the mid-1960’s, the property was used for uncontrolled filling and dumping of miscellaneous material such as dirt, concrete, steel, wood, and trash. The depth of the fill ranged from approximately 6.4 feet in the front of the property to more than sixty-seven feet at the rear of the property.

In or about 1984, Quarry embarked on a project to construct a medical facility on top of the former quarry. Quarry planned a two-story steel frame structure of approximately 16,000 square feet. Because of the uncontrolled fill at the site, Quarry’s architects concluded that the foundation of the building required support from steel piles driven approximately seventy-five feet below the surface of the fill into the rock below. J. E. Brenneman Company, a subcontractor, entered into a contract with Quarry on October 3, 1985, to install the foundation piles in accordance with Quarry’s designs. Before beginning construction, Brenneman obtained a CGL policy from Continental Insurance Company through its underwriting agent, Marine. The policy, number L2927679, was effective from September 1, 1985 through September 1,1986.

Brenneman drove the piles from October 11, 1985 through October 15, 1985. Brenneman’s records indicate that the piles were driven in a manner which would support forty tons per pile, as specified by the contract. However, some of the piles were not driven deep enough to encounter subsurface rock underneath the uncontrolled fill. These piles encountered metal, concrete, or other materials which had been dumped in the quarry and consequently “hung up” in the fill.

Quarry’s contractors poured concrete grade beams and pile caps over the piles in November, 1985 to complete the foundation system. Following installation of the foundation, Quarry halted construction for more than a year because of environmental problems at the site. When construction resumed in December, 1986 — after Brenneman’s insurance policy had expired — a mason discovered that the foundation in the rear portion of the building had settled four inches below the rest of the building. Despite these problems, the building was completed in the summer of 1987.

Shortly after construction had finished in 1987, Quarry discovered structural cracks in the budding’s concrete floor and masonry walls. An investigation revealed that several of the piles driven by Brenneman in 1985 had failed to reach the subsurface rock underneath the quarry by twenty to thirty feet. Because the piles were seated in uncontrolled fill rather than the underlying rock, the foundation system settled approximately four inches from the time the foundation was poured in November, 1985 to December, 1986.

Marine and Quarry have stipulated that the building’s foundation settled during the period of November, 1985 through September 1, 1986, while Brenneman’s insurance policy was in force. The stipulation of fact states that “the foundation system and piles in the rear of the building settled during the period November, 1985 through September 1, 1986 while the subject insurance policy was in effect.” See Stipulation ¶ 33. The parties also agree that the foundation’s settling was caused by Brenneman’s drilling of the piles into uncontrolled fill instead of subsurface rock. This defect made the rear wing of the building unstable and unsafe, requiring Quarry to demolish that portion of the building.

*1395 In October, 1988, Quarry filed a breach of contract and negligence action against Brenneman in the Court of Common Pleas of Delaware County, captioned Quarry Associates v. J.E. Brenneman Company (Civil Action No. 88-13409). On September 11, 1990, while the state court action was still pending, Brenneman filed a petition in the United States Bankruptcy Court for the Eastern District of Pennsylvania seeking protection under Chapter 11 of the United States Bankruptcy Code. Pursuant to the automatic stay provision of the Bankruptcy Code, 11 U.S.C. § 362 (1993), all actions against Brenneman, including Quarry’s state court action in Delaware County, were stayed.

On September 24, 1991, Quarry and Brenneman entered into a stipulation approved by the bankruptcy court to modify the stay.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kentucky Farm Bureau Mutual Insurance Co. v. Blevins
268 S.W.3d 368 (Court of Appeals of Kentucky, 2008)
West American Insurance v. Lindepuu
128 F. Supp. 2d 220 (E.D. Pennsylvania, 2000)
American Planned Communities, Inc. v. State Farm Insurance
28 F. Supp. 2d 964 (E.D. Pennsylvania, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
963 F. Supp. 1392, 1997 U.S. Dist. LEXIS 6589, 1997 WL 256065, Counsel Stack Legal Research, https://law.counselstack.com/opinion/marine-office-of-america-corp-v-quarry-associates-inc-paed-1997.