MARINE DESIGN DYNAMICS, INC. v. ALL CITY CONSTRUCTION SERVICES, LLC

CourtDistrict Court of Appeal of Florida
DecidedAugust 17, 2022
Docket21-0278
StatusPublished

This text of MARINE DESIGN DYNAMICS, INC. v. ALL CITY CONSTRUCTION SERVICES, LLC (MARINE DESIGN DYNAMICS, INC. v. ALL CITY CONSTRUCTION SERVICES, LLC) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
MARINE DESIGN DYNAMICS, INC. v. ALL CITY CONSTRUCTION SERVICES, LLC, (Fla. Ct. App. 2022).

Opinion

Third District Court of Appeal State of Florida

Opinion filed August 17, 2022. Not final until disposition of timely filed motion for rehearing.

________________

No. 3D21-0278 Lower Tribunal No. 19-10020 ________________

Marine Design Dynamics, Inc., Appellant,

vs.

All City Construction Services, LLC, Appellee.

An Appeal from the Circuit Court for Miami-Dade County, Alan Fine, Judge.

The Bravo Law Firm, PLLC, and Jason Bravo, for appellant.

Business and Family Law Center, and Kraig S. Weiss (Weston), for appellee.

Before SCALES, MILLER and BOKOR, JJ.

BOKOR, J. Marine Design Dynamics, Inc., appeals a grant of summary judgment

and final judgment in favor of All City Construction Services, LLC, in a breach

of contract claim. Marine Design argues that the trial court erred by

concluding as a matter of law that the contract mandated All City receive a

40% share of certain payments as “net profits” under the contract. 1 The plain

language of the contract supports the trial court’s determination that the

payments at issue constitute “net profits.” However, the final judgment fails

to account for permissible deductions under the same contractual provision

for expenses incurred. Accordingly, we affirm the summary judgment order

but vacate the final judgment to permit further proceedings to determine

what, if any, monies should be deducted from the payment at issue before

allocating All City’s contractual share.

1 Marine Design challenges the denial of its post-judgment motion for reconsideration based on the same. Marine Design also raises several other issues concerning the timeliness, authentication, and sufficiency of the evidence presented in support of the opposing summary judgment motion. However, these issues may not now be presented for the first time on appeal. See, e.g., 12550 Biscayne Condo. Ass’n, Inc. v. NRD Invs., LLC, 336 So. 3d 750, 756 (Fla. 3d DCA 2021) (explaining that “[m]erely referring to an authority without expressly arguing to the lower court the principle that flows from it is inadequate to preserve the issue for review if the argument was not considered by the trial court”).

2 BACKGROUND

In 2017, Marine Design contracted with the Federal Emergency

Management Agency (FEMA) to provide charter vessels for hurricane relief

efforts in the U.S. Virgin Islands and Puerto Rico. To finance the vessel

procurement, Marine Design separately executed a joint venture agreement

with All City Construction Services, by which All City would provide an initial

investment of $1,600,000 and receive a 40% share of the “net profits” from

the FEMA contract after expenses, as well as reimbursement of investment

money. This agreement also included a clause providing that the contract

would automatically terminate if FEMA ceased its need for the services

sought for the venture.

Eleven days after the execution of the FEMA contract, and before

Marine Design had provided the requested services, FEMA terminated its

contract with Marine Design for convenience and issued a stop work notice.

Marine Design timely notified All City of the termination and returned All

City’s $1,600,000 investment pursuant to the terms of the contract.

Subsequently, Marine Design also requested FEMA reimburse reasonable

charges reflecting the percentage of work performed under the contract prior

3 to receiving the notice of termination, pursuant to 48 C.F.R. 52.212-4(l). 2

FEMA ultimately reimbursed Marine Design for $1,329,517.85 in reasonable

charges demonstrated.

All City then requested that Marine Design pay it a 40% share of that

FEMA payment, alleging that those monies constituted “net profits” within

the meaning of the joint venture agreement. When Marine Design refused,

All City sued Marine Design. After discovery, All City and Marine Design

both moved for summary judgment. In support of its motion, All City

proffered an email Marine Design had received from a FEMA contracting

officer describing the payment as “a percentage of the contract price

reflecting reasonable charges demonstrated in your effort to satisfy the

contract requirements,” alleging that FEMA had characterized the payment

as being for partial performance. Conversely, Marine Design argued that the

payment was properly characterized as a mandatory termination for

convenience fee that was not encompassed by the agreement’s definition of

“net profits,” emphasizing the fact that the same FEMA email mirrored the

2 Specifically, 48 C.F.R. 52.212-4(l), which was incorporated by reference into the FEMA contract, requires certain federal agency procurement contracts to include a termination for convenience clause providing that the agency may terminate at any time for its sole convenience, but that the contractor will then “be paid a percentage of the contract price reflecting the percentage of the work performed prior to the notice of termination, plus reasonable charges the Contractor can demonstrate.”

4 language of 48 C.F.R. 52.212-4(l) and stated that the “vessels were not

delivered and performance . . . never occurred.”

Following a hearing, the trial court concluded as a matter of law that

the $1,329,517.85 FEMA payment constituted “net profits” under the joint

venture agreement, granted summary judgment in All City’s favor, and

entered final judgment awarding All City 40% of the payment plus

prejudgment interest. After Marine Design unsuccessfully moved for

reconsideration, this appeal followed.

ANALYSIS

We review the trial court’s grant of summary judgment de novo. See,

e.g., Volusia County v. Aberdeen at Ormond Beach, L.P., 760 So. 2d 126,

130 (Fla. 2000). 3 Summary judgment is proper when there are no genuine

issues of material fact and the moving party is entitled to prevail as a matter

of law. Id. Marine Design argues that genuine issues of material fact

precluded summary judgment as to the issue of whether the FEMA

reimbursement constituted a “net profit” for purposes of the profit-sharing

3 The standard of review for summary judgments in Florida has since changed to mirror the federal standard articulated in Celotex Corp. v. Catrett, 477 U.S. 317 (1986), with respect to judgments rendered after May 1, 2021. See In re Amends. to Fla. Rule of Civ. Proc. 1.510, 309 So. 3d 192, 195 (Fla. 2020). However, as the judgment at issue here was rendered before then, we instead apply the prior standard expressed above.

5 provision of the joint venture agreement. An issue of fact is “genuine” for

summary judgment purposes if it could allow a jury to return a verdict in favor

of the non-moving party, and an issue of fact is “material” if it could have any

bearing on the outcome of the case under the applicable law. Anderson v.

Liberty Lobby, Inc., 477 U.S. 242, 248–49 (1986).

The trial court correctly found that the $1,329,517.85 FEMA payment

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Volusia County v. Aberdeen at Ormond Beach
760 So. 2d 126 (Supreme Court of Florida, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
MARINE DESIGN DYNAMICS, INC. v. ALL CITY CONSTRUCTION SERVICES, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/marine-design-dynamics-inc-v-all-city-construction-services-llc-fladistctapp-2022.