Marina Lane, LLC v. Camp Cherokee, Inc.

Court of Appeals of Georgia·Decided June 25, 2012·No. A12A0546·Published

Opinion

THIRD DIVISION

MIKELL, P. J.,

MILLER and BLACKWELL, JJ.

NOTICE: Motions for reconsideration must be physically received in our clerk’s office within ten days of the date of decision to be deemed timely filed.

(Court of Appeals Rule 4 (b) and Rule 37 (b), February 21, 2008)

http://www.gaappeals.us/rules/

June 25, 2012

In the Court of Appeals of Georgia A12A0545, A12A0546. CAMP CHEROKEE, INC. v. MARINA LANE, LLC et al.; and vice versa.

MILLER, Judge.

Camp Cherokee, Inc. filed this suit for nuisance and trespass against Marina Lane, LLC, Clara Ruth Brooks, and Jerry Kyle (collectively “Marina Lane”) after Marina Lane built a dock on Camp Cherokee’s property at Lake Burton in Rabun County, Georgia. The case was referred to an auditor pursuant to OCGA § 9-7-1 et seq. Following an evidentiary hearing, the auditor issued a report with findings in favor of Marina Lane. Camp Cherokee filed its exceptions to the auditor’s report pursuant to OCGA § 9-7-14 (a). The trial court reversed the auditor’s conclusion that Marina Lane had a right to erect the dock. The trial court ruled as a matter of law that the erection of the dock on Camp Cherokee’s property constituted a nuisance and

trespass; ordered that the dock be removed; and, found that the issue of damages would be submitted to the jury. Although the trial court initially ruled that Camp Cherokee was also entitled to attorney fees under OCGA § 13-6-11 and punitive damages under OCGA § 51-12-5.1 (b), it later reconsidered its ruling and dismissed those claims.

We granted the parties’ respective applications for interlocutory appeal to review the trial court’s rulings. In Case No. A12A0545, Camp Cherokee contends that the trial court erred in dismissing its claims for attorney fees and punitive damages. In Case No. A12A0546, Marina Lane contends that the trial court erred in setting aside the auditor’s finding that they had a legal right to erect and maintain the dock; erred in ruling that the auditor’s report could not be submitted to the jury; and erred in ruling that Camp Cherokee would be allowed to present new evidence to the jury as to its damages. For the reasons that follow, we affirm the trial court’s rulings in Case No. A12A0546. However, we conclude that there was some evidence that would authorize an award of attorney fees and punitive damages; therefore, we reverse the trial court’s dismissal of those claims in Case No. A12A0545.

The record evidence shows that Camp Cherokee, a family owned corporation, owns certain property, including the land under the lake (“the lake bed”) and the

shoreline, surrounding Lake Barton in Rabun County (“the property”). Camp Cherokee’s property was subject to a perpetual easement granted to Georgia Power Company, which allowed Georgia Power to flow and back water upon the property extending up to the 1866-foot contour line. Notwithstanding Georgia Power’s easement, Camp Cherokee retained fee simple ownership in the lake bed and shoreline.

In the 1920’s, Camp Cherokee created the Cherokee Camp subdivision. Camp Cherokee retained ownership of the property, and conveyed to other individuals internal land lots in Block 11 that neither fronted nor abutted the lake. Brooks, Kyle, and the members of Marina Lane acquired ownership of lots in Block 11 of the subdivision. The chain of title and deeds of record conveying the subdivision lots in Block 11 did not contain express easements for access to the subject lake property or to the lake.

In May of 2007, Marina Lane approached Georgia Power to request a permit to erect a floating dock in the waters of the lake. Upon learning of Marina Lane’s efforts to obtain dock permits on the lake, Camp Cherokee retained counsel to protect their property interest. In October of 2007, and again in November of 2007, Marina Lane was advised that Camp Cherokee owned the property and that it had not given

permission for the proposed erection of a dock on its property. In January of 2008, Georgia Power’s counsel advised Marina Lane that it did not own fee simple title to the land under the lake, and that Marina Lane was required to deal with the owner of the lake bed.

In March of 2008, Georgia Power issued a license to Marina Lane for the erection of a dock within Georgia Power’s easement on the lake. The license expressly provided that “[Georgia Power] has not and does not now extend any invitation, either expressed or implied, to use said lake or lands in, on and adjacent thereto . . . for the erection of . . . docks, boat ramps, or other structures[.]” The license further provided that Marina Lane did not and would not claim any property rights to the lake or the lands “in, on and adjacent to the [l]ake[.]”

In April of 2008, the property owners officially formed Marina Lane, LLC for the sole purpose of erecting and maintaining the dock on the lake. In July of 2008, they obtained a county building permit to erect a floating dock, contending that the property owner was the “Cherokee Subdivision.” Marina Lane also obtained a construction permit from Georgia Power for a floating dock.

On September 16, 2008, Marina Lane erected the dock on the lake. Kyle and Brooks acknowledged that Camp Cherokee owned the lake bed, and that the dock

was not allowed to touch the lake bed. Kyle and Brooks also testified that they did not request Camp Cherokee’s permission to erect the dock because they knew that Camp Cherokee would reject their request. The evidence and photographs nevertheless established that the dock had been erected on and attached to Camp Cherokee’s lake bed and property.

On the same day that the dock was erected, Camp Cherokee’s counsel sent Marina Lane letters again notifying it that Camp Cherokee owned both the shoreline and the lake bed, that Camp Cherokee had not given permission for the erection and attachment of a dock on the property, and that the dock’s erection would constitute a trespass on the property. Camp Cherokee’s counsel further directed Marina Lane to remove the poles that attached the dock onto the property, and advised that Camp Cherokee would pursue a civil action and seek attorney fees and punitive damages if the removal was not timely completed.

Marina Lane failed to take any action to remove the poles and the dock that were attached to Camp Cherokee’s property. The instant lawsuit ensued.

Case No. A12A0546

1. Marina Lane contends that the trial court erred in reversing the auditor’s ruling that it had legal rights to access the lake and to maintain the dock. We disagree.

The trial court was not obligated to accept the auditor’s erroneous legal conclusions. See OCGA § 9-7-16 (“Exceptions of law [from an auditor’s report] shall be for the exclusive consideration of the judge.”); see, e.g., Eardley v. McGreevy, 279 Ga. 562, 564-565 (2) (615 SE2d 744) (2005) (ruling that in submitting a land title case to a special master, the trial court does not cede jurisdiction to render a final decision and is not obligated to accept a special master’s erroneous legal conclusion). Based upon the evidence presented in this case, the trial court was authorized to reject the auditor’s erroneous legal rulings.

It is undisputed that the deeds conveying the subdivision lots to the Marina Lane owners did not contain express easements to access the lake. Marina Lane nevertheless argues that it acquired an irrevocable implied easement for lake access since Camp Cherokee had sold the subdivision lots pursuant to a recorded subdivision plat that showed the lake and since had been a newspaper advertisement for an auction sale of residence and business lots at the lake with a representation that “[e]ach lot will carry [b]oating, [s]wimming and [f]ishing [p]rivilege.” In this regard, Marina Lane relies upon the legal principles set forth in Walker v. Duncan, 236 Ga. 331, 332 (223 SE2d 675) (1976), stating that

Free access — add to your briefcase to read the full text and ask questions with AI

Marina Lane, LLC v. Camp Cherokee, Inc., (Ga. Ct. App. 2012).

Marina Lane, LLC v. Camp Cherokee, Inc. (Marina Lane, LLC v. Camp Cherokee, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

De Castro v. Durrell
671 S.E.2d 244 (Court of Appeals of Georgia, 2008)
Wallace v. Swift Spinning Mills, Inc.
511 S.E.2d 904 (Court of Appeals of Georgia, 1999)
Forsyth County v. Martin
610 S.E.2d 512 (Supreme Court of Georgia, 2005)
Paine v. Nations
641 S.E.2d 180 (Court of Appeals of Georgia, 2006)
Eardley v. McGreevy
615 S.E.2d 744 (Supreme Court of Georgia, 2005)
Higgins v. Odom
271 S.E.2d 211 (Supreme Court of Georgia, 1980)
Shaver v. Kawasaki Motors Corp., U. S. A.
614 S.E.2d 240 (Court of Appeals of Georgia, 2005)
Walker v. Duncan
223 S.E.2d 675 (Supreme Court of Georgia, 1976)
Merlino v. City of Atlanta
657 S.E.2d 859 (Supreme Court of Georgia, 2008)
Tyler v. Lincoln
527 S.E.2d 180 (Supreme Court of Georgia, 2000)
LN West Paces Ferry Associates, LLC v. McDonald
703 S.E.2d 85 (Court of Appeals of Georgia, 2010)
Southern Pine Co. v. Dickey
71 S.E. 1110 (Supreme Court of Georgia, 1911)
Exchange National Bank v. McDonald
176 S.E. 18 (Supreme Court of Georgia, 1934)