Marianas Public Land Corp. v. Guerrero

2 N. Mar. I. 301, 1991 N. Mar. I. LEXIS 19
CourtSupreme Court of The Commonwealth of The Northern Mariana Islands
DecidedOctober 4, 1991
DocketAPPEAL NO. 90-039; CIVIL ACTION NO. 88-685
StatusPublished

This text of 2 N. Mar. I. 301 (Marianas Public Land Corp. v. Guerrero) is published on Counsel Stack Legal Research, covering Supreme Court of The Commonwealth of The Northern Mariana Islands primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Marianas Public Land Corp. v. Guerrero, 2 N. Mar. I. 301, 1991 N. Mar. I. LEXIS 19 (N.M. 1991).

Opinion

OPINION

VILLAGOMEZ, Justice:

This is an appeal from an order granting partial summary judgment in favor of Marianas Public Land Corporation ("MPLC"). The trial court concluded as a matter of law that Bernard S. Guerrero ("Guerrero") breached his lease agreement with MPLC and [303]*303-that the same was subject to termination. Guerrero timely appealed the order.

FACTS

Guerrero1 and MPLC2 entered into a 25 year lease agreement ("lease") on October 23, 1987, in which Guerrero leased 4,000 square meters of public land at Lower Base, identified as Lot No. 038 E 03. Guerrero leased the land in order to operate his sanitation business, maintain his heavy equipment, operate an automobile repair shop, fabrication and welding services, and other support facilities.

The lease provided that, within three months of its effective date, Guerrero was to secure all required permits and submit to MPLC construction plans, specifications, and estimates. The lease required Guerrero to obtain fire, damage, and liability insurance during the term of the lease. It also prohibited Guerrero from abandoning the premise for 90 days or more.

Shortly after the lease was executed, Guerrero went to the Commonwealth Utilities Corporation ("CUC") to inquire about hookups of water, power, and sewer lines to the premises. CUC informed him that there was a moratorium placed on power and water hook-ups to commercial establishments. It further told him that the duration of the moratorium was indefinite. Neither MPLC nor [304]*304Guerrero knew that such moratorium existed when they executed the lease.3

Believing the moratorium to be of temporary duration, Guerrero decided not to start any construction on the premises until the same was lifted. However, he continued paying MPLC the quarterly rent.

On June 8, 1988, MPLC notified Guerrero, in writing, that Guerrero was in default for failing to submit to MPLC the construction plans and drawings; for failing to use (abandoning) the premises, as intended, for over ninety days; and for failing to procure the required insurance coverages.

Guerrero replied that he.had not abandoned the premises; that he was waiting for CUC to lift the moratorium; and that he was still paying the rent. He added that there was nothing on the land to insure and requested a one-year extension' of time on the requirement to construct the building for his business operations.

MPLC denied the request for extension of time. On September 23, 1988, it filed suit seeking termination of the lease. Guerrero raised, as an affirmative defense, the CUC moratorium on commercial hook-ups and his inability to use the premises without the utilities.4 Thereafter, MPLC moved for summary judgment.

[305]*305In the absence of written and customary law,5 the trial court considered the applicability of § 269, Restatement (Second^ of Contracts (1979) ("§ 269"),6 and concluded that the defense of impracticability does not apply because the CUC moratorium was not "temporary." If the moratorium were temporary, then § 269 would apply.

Guerrero assigns as error the trial court's conclusion that § 269 is not applicable. He argues that the question of whether the CUC moratorium is "temporary" raises a question of disputed fact that should go to trial, rather than be disposed of by summary judgment. He also argues that the moratorium is "temporary" and not "permanent." Consequently, § 269 applies.

[306]*306ISSUE and STANDARD OF REVIEW

The issue presented is whether the trial court erred in ruling that the moratorium is not "temporary” and that Section 269 does not apply. This is a question of law which we review de novo. In re Estate of Jose P. Cabrera, No. 90-044 (N.M.I. July 31, 1991). A grant of summary judgment is reviewed de novo. MPLC v. Kan Pacific Saipan, Ltd., No. 90-014 (N.M.I. Nov. 21, 1990).

ANALYSIS

I.

We review initially the appealability of an order granting partial summary judgment sua sponte. since the case below has not been entirely disposed of. We are bothered by the filing of this appeal without the requisite certification by the trial court pursuant to Rule 54(b), Com.R.Civ.P. See Metal Coating Corporation v. National Steel Construction Co., 350 F.2d 521 (9th Cir. 1965). We note, however, that Rule 54(b) pertains to multiple claims or multiple parties. Here, there is only one substantive claim made by one party — MPLC.

Generally, the granting of a partial summary judgment is interlocutory in nature and is not appealable. 10 C. Wright, A. Miller and M. Kane, Federal Practice and Procedure. Civil § 2715 (1983), Cf. CNMI v. Hasinto, No. 90-033,34 (N.M.I. Oct. 15, 1990). However, a partial summary judgment may be appealed if it completely disposes of plaintiff's claim and resolving the appeal promptly would expedite the resolution of any remaining issues [307]*307below. Sheehan v. Atlanta Int'l Ins. Co., 812 F.2d 465 (9th Cir. 1987). A partial summary judgment is also appealable when the claim resolved is separate and distinct from those which remain before the trial court. Hudson River Sloop Clearwater, Inc. v. Department of Navy, 891 F.2d 414 (2d Cir. 1989).

For the reasons set forth below, we are satisfied that the partial summary judgment herein is an appealable order.

First, plaintiff claims substantively for the termination of the lease and the resulting re-possession of the land. It also, requests for attorneys fees and costs. The order granting partial summary judgment completely disposed of the substantive claim. The claim for fees and costs is distinct from the substantive claim and is determined after the merits are decided.

Second, the matter of restitution, raised by the trial court,7 pertains to the return of rental payments (made by Guerrero under the lease) and is not a disputed question of fact. The payments are recorded and can readily be ascertained.

Third, although the trial court stated in its order that the applicability of § 266(1), Restatement (Second) of Contracts. (1979),8 is a matter for trial, it also stated that even if it does [308]*308apply/ the lease is still terminated. Neither party raised this issue. Nor did either of them make any claim under §. 266(1). Thus, the issue of lease termination is distinct and is one that has been fully disposed of by the partial summary judgment.

Fourth, if we determine that § 269 applies in this case, and Guerrero's duty under the lease is temporarily suspended, then there would be no need to try the issue of restitution. Also, if § 269 is found to apply, then § 266(1) does not apply.

For the above reasons, we hold that we have jurisdiction over this appeal.

II.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
2 N. Mar. I. 301, 1991 N. Mar. I. LEXIS 19, Counsel Stack Legal Research, https://law.counselstack.com/opinion/marianas-public-land-corp-v-guerrero-nmariana-1991.