Marett v. BRICE BLDG. CO., INC.

603 S.E.2d 40, 268 Ga. App. 778
CourtCourt of Appeals of Georgia
DecidedJuly 9, 2004
DocketA04A0474, A04A0475
StatusPublished
Cited by1 cases

This text of 603 S.E.2d 40 (Marett v. BRICE BLDG. CO., INC.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Marett v. BRICE BLDG. CO., INC., 603 S.E.2d 40, 268 Ga. App. 778 (Ga. Ct. App. 2004).

Opinion

Barnes, Judge.

Jean and William Marett appeal the trial court’s grant of summary judgment to Brice Building Company, Inc. against them on Brice’s complaint for quantum meruit. Brice appeals the trial court’s denial of summary judgment on its claims for breach of contract and on account. For the reasons that follow, we affirm.

The Maretts are the sole members of Marett Properties, LLC. Marett Properties hired Brice to work on two commercial real estate projects, the USA Floral Project, which began in March 2000 and the Advance Medical Project, which began in June 2000. After the work began, both Jean and William Marett signed guaranties agreeing to be personally liable for Marett Properties’ debt to Brice, but did not sign the contracts Brice submitted. Meanwhile, the parties who had anticipated leasing or buying these commercial properties once they were completed were unable to obtain financing. On August 30,2000, Brice stopped working on the projects because Marett never paid them anything, and the parties communicated back and forth for months about payment of the invoices.

Brice eventually sued Marett Properties, Jean Marett, and William Marett for quantum meruit, breach of contract, and on account for the value of the work it did on both properties. The Maretts answered, and after discovery, Brice moved for summary judgment on all counts. Its vice president swore that Brice performed work valued at $225,585 on one project, and $112,215 on the other. The trial court granted summary judgment against all three defendants for $337,800 plus pre-judgment interest on the quantum meruit counts, and denied summary judgment on the claims for breach of contract and on account.

*779 1. Marett Properties did not appeal the grant of summary judgment against it on the quantum meruit count, and Jean and William Marett do not contest the judgment amount. Instead, they argue that the trial court erred in finding them personally liable for the judgment.

On appeal we review the trial court’s grant of summary judgment de novo to determine whether the evidence, viewed in the light most favorable to the nonmoving party, demonstrates a genuine issue of material fact. Summary judgment is proper only when no issue of material fact exists and the moving party is entitled to judgment as a matter of law. Preferred Real Estate Equities v. Housing Systems, 248 Ga. App. 745 (548 SE2d 646) (2001).

Jean Marett asserts that the trial court erred in finding her personally liable for the value of Brice’s work on the Advanced Medical Project. The trial court found that Jean Marett owned the real property involved, accepted Brice’s work on the project, and benefitted from that work. Marett does not dispute that Brice worked on the project and she owned the property, but contends that an issue of fact exists as to whether she knowingly accepted Brice’s services so that a promise to pay Brice can be implied.

OCGA § 9-2-7 provides that “[ojrdinarily, when one renders service or transfers property which is valuable to another, which the latter accepts, a promise is implied to pay the reasonable value thereof.”

In order to recover under a quantum meruit theory, claimant must show (1) his performance as agent of services valuable to the defendants; (2) either at the request of the defendants or knowingly accepted by the defendants; (3) the defendants’ receipt of which without compensating claimant would be unjust; (4) and claimant’s expectation of compensation at the time of the rendition of the services.

(Citations and punctuation omitted.) Artrac Corp. v. Austin Kelley Advertising, 197 Ga. App. 772, 777 (5) (399 SE2d 529) (1990).

Jean Marett argues that she was not involved directly in the day-to-day business of Marett Properties, and that therefore Brice could not show that she knowingly accepted Brice’s work on the Advanced Medical Project. But Jean Marett owned the property, and signed a personal guaranty agreeing to pay Brice for the work done under the contract that all parties anticipated would be signed shortly. She attended Marett Properties staff meetings at which progress on the Advanced Medical Project was discussed. Her argument that she did not know Brice was working on her property despite her having promised to pay does not create an issue of fact, *780 and we find no error in the trial court’s grant of summary judgment against Jean Marett personally for the Advanced Medical Project.

2. Jean and William Marett contend that the trial court erred in construing their personal guaranties to cover the quantum meruit debt, arguing that the guaranties only covered contractual obligations by Marett Properties to Brice, and because Marett Properties never signed a contract, Jean and William Marett are not personally liable.

A contract of guaranty is primarily one to pay the debt of another which may be due and payable by the principal debtor to the creditor upon default. In construing guaranties, they are to be taken as strongly against the party giving the guarantee, as the sense of them will admit. Thus, as a general rule, if the construction is doubtful, that which goes most strongly against the party undertaking the obligation is generally to be preferred.

(Citations and punctuation omitted.) Town Center Assoc. v. Workman, 227 Ga. App. 55, 58 (1) (487 SE2d 624) (1997).

The guaranty agreements for the two projects begin:

As an inducement to Brice Building Company, Inc., (hereinafter referred to as “Contractor”) to enter into the Advanced Medical Associates (referred to as the “Contract”) with Marett Properties, LLC (hereinafter referred to as “Owner”), and in consideration of Contractor entering into said Contract, the Undersigned, W. W. Marett, Jr. and Jean S. Marett, ... do hereby irrevocably and unconditionally guarantee to Contractor the full and timely performance of all of the terms, promises and covenants set forth in said Contract.

The guaranty for the USA Floral project mirrors the Advanced Medical guaranty. Brice relies on a later paragraph in the documents, which provides that the

Guaranty Agreement shall remain fully enforceable against the Undersigned for the full amount of any obligations of the Owner to the Contractor less only payments thereon actually received and retained by Contractor, irrespective of and without reduction on account of (i) any defense, offset, or counterclaim which Owner may have or assert with respect to any of such obligations.

(Emphasis supplied.)

*781 “[Contracts of suretyship and guaranty are indistinguishable.” Arnold v. Indcon, L.P., 219 Ga. App. 813 (1) (466 SE2d 684) (1996).

A contract of suretyship must be strictly construed in the interest of the surety. A surety’s liability will not be extended beyond by implication or interpretation. The undertaking of a surety being stricti-juris, he cannot, in law or equity, be bound further than the very terms of his contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
603 S.E.2d 40, 268 Ga. App. 778, Counsel Stack Legal Research, https://law.counselstack.com/opinion/marett-v-brice-bldg-co-inc-gactapp-2004.