MARCON Engineering, Inc.

CourtArmed Services Board of Contract Appeals
DecidedMay 1, 2015
DocketASBCA No. 57471
StatusPublished

This text of MARCON Engineering, Inc. (MARCON Engineering, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
MARCON Engineering, Inc., (asbca 2015).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) MARCON Engineering, Inc. ) ASBCA No. 57471 ) Under Contract No. W912BV-08-D-2026 )

APPEARANCES FOR THE APPELLANT: Theodore M. Bailey, Esq. Kristin E. Zachman, Esq. Bailey & Bailey, P.C. San Antonio, TX

APPEARANCES FOR THE GOVERNMENT: Thomas H. Gourlay, Jr., Esq. Engineer Chief Trial Attorney John F. Bazan, Esq. Engineer Trial Attorney U.S. Army Engineer District, Los Angeles

OPINION BY ADMINISTRATIVE JUDGE PEACOCK

This timely appeal involves three discrete claims by appellant under the captioned contract. The scope of the hearing of the appeal originally encompassed both entitlement and quantum. However, at the hearing, the parties agreed and the Board ordered that the hearing and this decision would address entitlement only. Briefing and finalization of the record in this appeal were completed on 23 November 2014. We sustain the appeal in part and deny it in part.

FINDINGS OF FACT

The Project Generally and Solicitation

1. The United States Army Corps of Engineers (Corps or government) issued a Request for Proposal (RFP) for award of a firm-fixed-price (FFP) task order (TO) to design and construct approximately .97 miles of a fence along the Arizona border with Mexico under the captioned multiple award task order contract (MATOC). The TO solicitation was issued on 6 May 2008 and called for design/construction of a bollard style fence (18 feet high, approximately 6.5 inches in diameter, and spaced approximately 4 inches apart), its foundation, and an immediately-adjacent concrete access road along the fence line. (R4, tab 7 at 154, 802-04, tab 12 at 2512-13; supp. R4, tab 334 at 7096, ex. G-2) 1 The fence was one small section of an extensive project

1 In general, the government's responses to appellant's proposed findings of fact are not in compliance with the Board's Briefing Order. That order mandated that along the Mexican border starting in San Diego, California. The government retained the architectural engineering firm of Michael Baker Jr., Inc. (Baker or A-E), as project manager for the overall project. (Tr. 5/87-88, 7/34)

2. The specifications included in the RFP required that all construction activities were to be "contained within the project corridor," with the exception of work related to installation of two 24 inch corrugated metal pipes (CMPs or culverts) at the western limits of the project (supp. R4, tab 334 at 7093; tr. 3/153, 6/206, 7/63, 204). The "project corridor" was a 60-feet wide strip adjacent to the border also known as the Roosevelt Reservation (RR) (supp. R4, tab 334 at 7093; R4, tab 7 at 196; tr. 1/103).

objections and replies to opposing party proposed findings be specific and detailed, in particular pointing out any inaccuracies in the record citations. For example, appellant's proposed findings often provide a narrative description of the content of key drawings, supplementing depictions of the actual drawings or reasonably accurate (albeit generally not-to-scale) demonstrative representations of key elements of the drawings. Those findings are also supported by extensive citations to transcript testimony of the witnesses discussing the actual drawings. The government's responses to these proposed findings generally interpose simplistic, broad, imprecise, general, conclusory and argumentative objections to the findings on the basis that the original drawing "speaks for itself' or the demonstrative is "non-contemporaneous" or not-to-scale without addressing precisely and in detail the accuracy and substance of the proposed findings or why the proposed finding is otherwise unsupported by, contrary to, or in conflict with the evidence. Nevertheless, the Board has undertaken an independent review of key findings to ensure that they, in fact and substance, are supported and/or reasonably depict the underlying drawing. Those findings in material respects have not been shown to be inaccurate as confirmed by our own independent examination of key evidence of record. Moreover, the government considers that because "Marcon cannot prove a cause of action against the Corps regarding drainage .... The Corps therefore only provides some objections below due to time constraints." (Resp.'s master response to APF 101) The Corps conclusory assertion is, of course, the principal grounds for the dispute and appeal. As we discuss in detail herein that government contention lacks merit. Regardless, the Corps was not excused from the directions in the Briefing Order due to time constraints particularly where the briefing of the appeal was extended at the parties' requests on a number of occasions and was not concluded until approximately eleven months following completion of the trial. The government's post hearing briefs also frequently cite inaccurately or incompletely to documents, transcripts and page numbers and are generally unreliable. As a consequence of all of the above, we have liberally relied on appellant's proposed findings and record citations in this decision. 2 3. The RFP contemplated that the contractor would use the "Appendix 2" drawings, developed by Baker and dated 24 March 2008, including a ditch detail therein, in designing the drainage system for the site (tr. 7/207; R4, tab 7 at 788). In this regard, section OI 00 50 "TASK ORDER REQUIREMENTS," paragraph I.9 "SITE DESIGN AND CONSTRUCTION," subparagraph I .9.6. "On-Site Construction Access Road" provided as follows:

The Design/Build Contractor shall be responsible for the design and construction of the on-site construction access road and drainage ditch modifications adjacent to the fence. A conceptual typical section has been provided in Appendix II. The Design/Build Contractor shall fully design and construct the on-site construction access road and drainage ditch modifications using the conceptual typical section.

(R4, tab 7 at I 96, I 98, 200)

4. The pertinent detail on RFP appendix (appx.) II drawing G-2.I (R4, tab 7 at 790), depicted a typical concrete drainage ditch for essentially the length of the one mile site designed to transport flood waters from the west end to east end of the site through the concrete ditch. The water was to exit the site in a northeasterly direction at its east end. Because of the presence of an existing irregular ditch (as discussed below), the depths of any required excavation/grading and modifications of the ditch varied. The concrete ditch was to be located within the RR between the access road to be constructed immediately adjacent to the fence on the south, and a preexisting road constructed and maintained by the Border Patrol approximately paralleling the future fence line, hereinafter referred to as the Border Patrol Road (BPR), on the north. The BPR was partially within, but for most of its length outside of, the RR to varying degrees at various stations. Although the detail generally showed some filling in of the existing ditch to accommodate the fence access road, the Baker concept did not envision filling in the ditch entirely as would generally be needed to have the water emanating from the south (Mexico) flow more naturally across the site in a north or northeasterly direction. (Supp. R4, tab 304 at 7008-09, tab 342 at 7210-2I; tr. 1/89-90, 92, 4/63, 5/89-90, 7/66, 208-IO, 213-I4, 22I)

5. Section OI 33 I6 "DESIGN AFTER AWARD," Part I "GENERAL," noted that the contract consisted of the "Solicitation requirements and the accepted proposal" and further stated in paragraph I . I :

The information contained in this section applies to the design required after award. The design begins with the pre-contract proposal, which must conform to all

3 requirements of the Solicitation. After award, the Contractor will develop the accepted proposal into the completed design, as described herein.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
MARCON Engineering, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/marcon-engineering-inc-asbca-2015.